FY 13 | Eddyville | Dock Repairs | $32,500.00 |
FY 14 | Eddyville | Grain Elevator Ramp Improvements #1 | $22,750.00 |
FY 14 | Eddyville | Security Gate Addition | $7,500.00 |
FY 14 | Eddyville | Grain Elevator Ramp Improvements #2 | $13,750.00 |
FY 15 | Eddyville | Port Road Widening | $18,000.00 |
FY 15 | Eddyville | Asphalt Overlay | $16,500.00 |
FY 16 | Eddyville | Agri Port Road Widening | $39,250.00 |
FY 17 | Eddyville | Truck Queuing and Grain Pit Improvements | $75,000.00 |
FY 20 | Eddyville | Realignment of Agri-Chem Access Road | $49,780.00 |
FY 20 | Eddyville | Roll-Up Garage Doors for Truck Pit | $10,000.00 |
FY 21 | Eddyville | Sheet Pile Shoring Walls Near Boat Repair Bay Project | $109,890.00 |
FY 21 | Eddyville | Guardrail Installation Along Pit #2 | $48,415.00 |
FY 22 | Eddyville | Dock Tieback Repairs | $126,500.00 |
FY 23
| Eddyville
| Barge Positioning Winch System
| $105,058.00 |
FY 23
| Eddyville
| Laydown Yard
| $110,229.00 |
FY 24
| Eddyville
| CAT 330 Hydraulic Excavator
| $184,061.00 |
| | Total | $969,183.00 |
FY 15 | Greenup-Boyd | Asphalt Loading Facility | $93,122.50 |
FY 16 | Greenup-Boyd | Crossings & Crosstie Repair | $64,215.00 |
| | Total | $157,337.50 |
FY 13 | Henderson | Dock Pavement Repairs-Replacement | $41,130.00 |
FY 14 | Henderson | Railroad Bed Improvement | $61,760.00 |
FY 14 | Henderson | Barge Access Catwalk | $37,000.00 |
FY 15 | Henderson | Road Paving Project | $25,000.00 |
FY 17 | Henderson | Crane Restoration | $250,000.00 |
FY 20 | Henderson | Forklift Replacement/Truck Hopper | $137,500.00 |
FY 21 | Henderson | Mooring Dolphin Replacement | $108,000.00 |
FY 24
| Henderson
| Automated Truck Scale
| $122,000.00 |
FY 25
| Henderson
| 15,500 lb Forklift
| $95,360.00
|
FY 25
| Henderson
| 12,000 lb Forklift
| $27,413.00 |
| | Total | $905,163.00 |
FY 13 | Hickman | Barge Access Catwalk | $45,996.00 |
FY 14 | Hickman | Scale Access Improvement | $36,087.50 |
FY 14 | Hickman | Dock Dredging | $27,500.00 |
FY 15 | Hickman | Port Road Access | $15,000.00 |
FY 15 | Hickman | Cargill Access Road Paving | $87,346.50 |
FY 16 | Hickman | Dock Dredging #2 | $25,075.00 |
FY 16 | Hickman | Crane Replacement | $200,000.00 |
FY 16 | Hickman | Grain Conveyor Access Improvement | $5,425.00 |
FY 17 | Hickman | Dock Dredging #3 | $25,200.00 |
FY 17 | Hickman | Crane Bridge Resurface/Warehouse Repairs | $60,000.00 |
FY 18 | Hickman | Conveyor Upgrade | $135,000.00 |
FY 19 | Hickman | Dock Dredging #4 | $32,400.00 |
FY 19 | Hickman | Dock Forklift | $29,025.00 |
FY 22 | Hickman | Front End Loader | $136,265.00 |
FY 23
| Hickman
| Mooring Dock Cell Repair
| $50,000.00
|
FY 23
| Hickman
| Dock Dredging #5
| $31,800.00
|
FY 25
| Hickman
| Dock Dredging #6
| $65,376.00 |
FY 25
| Hickman
| Spreader Bar & Coil Hooks
| $19,600.00
|
| | Total | $1,027,096.00 |
FY 13 | Louisville | Riverport Railroad Rehab #1 | $62,055.00 |
FY 14 | Louisville | Riverport Railroad Rehab #2 | $50,000.00 |
FY 14 | Louisville | Bulk Terminal Access Road Paving | $37,500.00 |
FY 15 | Louisville | Riverport Railroad Rehab #3 | $55,555.00 |
FY 18 | Louisville | Railroad Rehab #4 | $96,750.00 |
FY 19 | Louisville | Riverport Rail Tie Replacement #5 | $106,025.00 |
FY 20 | Louisville | Riverport Rail Tie Replacement #6 | $150,000.00 |
FY 21 | Louisville | Riverport Rail Tie Replacement #7 | $95,792.00 |
FY 25
| Louisville
| Caterpillar 255 Skid Steer
| $65,207.000 |
| | Total | $718,884.00 |
FY 13 | Owensboro | Railroad Maintenance | $26,384.25 |
FY 13 | Owensboro | Harbor Road Entrance Replacement/Resurface | $91,932.00 |
FY 14 | Owensboro | Primary Access Road Paving | $115,000.00 |
FY 14 | Owensboro | Access Drive Spur | $50,000.00 |
FY 15 | Owensboro | Scale Access Improvement | $105,826.00 |
FY 15 | Owensboro | Grain Access Improvement | $83,650.00 |
FY 16 | Owensboro | Railroad Maintenance & Repair | $88,257.50 |
FY 16 | Owensboro | Solvay Milling Facility Paving | $77,777.50 |
FY 17 | Owensboro | Inner Loop Road | $33,704.50 |
FY 18 | Owensboro | Truck/Trailer Staging Area | $180,000.00 |
FY 19 | Owensboro | Improve Gravel Access Roads | $96,330.00 |
FY 19 | Owensboro | Off Road 4x2 Semi Tractors | $116,220.00 |
FY 20 | Owensboro | Railroad Maintenance and Repair | $100,101.00 |
FY 20 | Owensboro | Compact Track Loader (Skid Steer) | $34,480.00 |
FY 20 | Owensboro | Erosion Control (Riprap) | $28,139.00 |
FY 21 | Owensboro | Front End Loader Replacement | $120,082.00 |
FY 22 | Owensboro | Compact Track Loader | $34,807.00 |
FY 23
| Owensboro
| Bucket for Liebherr LH 120
| $57,490.00
|
FY 23
| Owensboro
| Caterpillar 903D Wheel Loader
| $36,790.00
|
FY 23
| Owensboro
| Grapple for Sennebogen 875
| $35,912.00 |
FY 24
| Owensboro
| 25,000 lb Forklift
| $115,859.60 |
FY 24
| Owensboro
| Compact Track Loader
| $31,399.83 |
FY 24
| Owensboro
| 10,000 lb Forklift
| $16,169.57
|
FY 25
| Owensboro
| Low Road Loadout
| $152,749.00
|
| | Total | $1,829,060.75 |
FY 13 | Paducah | Dock Improvement | $100,000.00 |
FY 13 | Paducah | Conveyor Rehab/Maintenance | $50,000.00 |
FY 17 | Paducah | Dock Dredging #1 | $39,730.00 |
FY 17 | Paducah | Truck Scale Replacement | $45,541.00 |
FY 18 | Paducah | Conveyor Refurbish | $88,200.00 |
FY 19 | Paducah | Container on Barge | $72,734.00 |
FY 21 | Paducah | River Belt Discharge Chute Refurbishment | $16,236.00 |
FY 22 | Paducah | Clamshell Bucket Replacement | $23,625.00 |
FY 23
| Paducah
| Bulk Commodity Receiving Hopper
| $72,721.00
|
FY 24
| Paducah
| 4th Street Concrete Aprons
| $30,510.00 |
FY 25
| Paducah
| Bobcat S650 Skid Steer Loader
| $46,055.00 |
FY 25
| Paducah
| 48-Foot Flatbad
| $28,240.00
|
| | Total | $613,592.00 |