Jefferson County: I-264 Bridge Replacement over P & L Railroad - Project 05-10075.00

​​​​05-10075 project area map1.JPG

Purpose
Replacement of bridge structure on I-264 over the P&L railroad. The bridge is in excess of 50 years of age and is in substandard condition. This project aims to improve safety and operational efficiency of the bridge. 
​Project Scope
Replacement of the entire bridge structure, including abutments and piers. No residential properties will be impacted, and traffic will be maintained on I-264.

The existing typical section for the I-264 bridge over the P&L Railroad is depicted below. The new bridge will have a similar lane configuration, with the replacement of structural components. These improvements are geared towards enhancing safety for drivers in Jefferson County.

I-264 Bridges_Typical Section Graphic
​Links

056B00250N 01-11-2023.pdf

056B00250N 01-13-2021.pdf

5-10075.00 project location map.jpg

Historic Geotech for i-264 over P L Railroad.pdf

I-264 Roadway Plans 1969.pdf

Structure Plans 1969.pdf

*Some files are large and may take a few minutes to load.
​Project Timeline

As of Spring 2023 (SUBJECT TO CHANGE)

  • The project is currently in the design phase, with an expected timeline of 2023-2024.
  • KYTC anticipates construction in 2025 and 2026.
*The above project milestone dates are subject to change due to changes in funding availability within the next Enacted Highway Plan.

​Public Input
TBD: online project information presentation only. Note: No residential properties will be impacted, but traffic flow will be affected during construction.
​Project Manager
Chuck Berger
Email: chuck.berger@ky.gov
Phone: 502.764.0488 

This page is maintained by KYTC District 5 Staff, who may be contacted to make corrections or changes.

​Page Last Updated: 11-03-2023