KY 22 and KY 146 ​Improvements - Project 05-597.00​

​​​​​​KYTC_CW_map_project area.jpg​​​​​​​​​​

​​
Project Overview

The Kentucky Transportation Cabinet (KYTC) is exploring improvements in Oldham County at the junction of KY 22, KY 146 and a railroad crossing.

The downtown Crestwood intersection has undergone a series of spot improvements in recent years but has continued to experience a relatively high number of traffic incidents and ease-of-navigation concerns for semi-trailer trucks.

KY State Police records showed 208 incidents on KY 22 and KY 146 within 0.5 miles between January 2019 and July 2024.  Semi-trailer trucks having difficulties making turns is a major issue.

KYTC is working with its engineering partners to develop proposed alternative designs – two on the south side and one on the north – that would improve conditions while minimizing impact to local businesses.

KYTC is seeking public feedback during its comment period on proposed alternatives to develop practical solutions and improvement concepts while making safety, performance and efficiency top priorities.

Purpose

The purpose of the project is to improve safety, capacity and system reliability around the existing intersection and railroad crossing at KY 22 and KY 146.

The intersection has undergone a series of spot improvements in recent years but has continued to experience a relatively high number of traffic incidents and continued concerns about difficult turns for trucks.

Project Scope

This study includes comprehensive analysis of existing conditions along the corridor, which will be used to develop practical solutions and improvement concepts to enhance roadway safety, address congestion issues, and improve traffic flow. 
Type of Project

This roadway reconstruction project will provide safety, capacity, and system reliability to the KY 22 and KY 146 intersection.

Project Timeline

As of Summer 2026 (SUBJECT TO CHANGE)*:

  • Project is currently in Preliminary Design and will identify a preferred alternative. If a Build Alternative is selected, the anticipated schedule is as follows:
  • Final Design phase may begin in 2026. *
  • Right of Way phase may begin in 2029. *
  • Utility phase may begin in 2029. *
  • Construction phase may begin in 2030. *

*The above project milestone dates are subject to change depending on the Cabinet's funding constraints and various other factors.
Public Input 

A Local Officials/Stakeholders Meeting was held on December 3, 2025.

​A 30-day public comment period was closed on January 5, 2026.

​​Links
Project Documents: 
Project Manager

James Maynard, P.E.
Email: james.maynard@ky.gov
Phone: 502-764-0485

 


This page is maintained by KYTC District 5 Staff, who may be contacted to make corrections or changes.

​​​​Page Last Updated: 07-24-2026

Department of Aviation

Airport Zoning Commission

Department of Rural and Municipal Aid

Local Programs
Local Public Agencies

Department of Vehicle Regulation

Drive.ky.gov
Motor Vehicle Commission

Powered by Google TranslateTranslate