Improve safety and traffic operations on KY 155 from MP 2.0 in Spencer County to Floyds fork in Jefferson County (total length 6.247 miles) (portion of 5-8954.0). (2024CCN) (2026CCR) – 5-8954.10
As of Summer 2026, (SUBJECT TO CHANGE*):
- Design Phase – “Current Phase”, Continue developing the final plans. Funding Type: STPF.
- Right-of-Way Phase – Anticipate beginning Federal Fiscal Year 2030 when funding becomes available. Funding Type: STPF.
- Utility Phase – Anticipate beginning Federal Fiscal Year 2031 when funding becomes available. Relocations may begin after the Right-of-Way Phase is completed. Funding Type: STPF.
- Construction Phase – Anticipate beginning Federal Fiscal Year 2032* when funding becomes available. To begin after the Utility Phase has been completed.
- Letting Date to Construction – Date to be determined**
*The above project milestone dates are subject to change due to changes in funding availability within the next Enacted Highway Plan.
**The project's letting date will be set after the needed right-of-way is acquired and the impacted utility relocations have advanced.
Improve safety and traffic operations on KY 55 from KY 1169 to KY 155 and on KY 155 from KY 55 to MP 2.0 (total length 2.71 miles) (portion of 5-8954.0). (2024CCN) – 5-8954.20
As of Summer 2026, (SUBJECT TO CHANGE*):
- Design Phase – Anticipate beginning Fiscal Year 2029 when funding becomes available. Funding Type: SPP.
- Right-of-Way Phase – Anticipate beginning Fiscal Year 2030 when funding becomes available. Funding Type: SPP.
- Utility Phase – Anticipate beginning Fiscal Year 2030 when funding becomes available. Relocations may begin after the Right-of-Way Phase is completed. Funding Type: SPP.
- Construction Phase – Anticipate beginning Fiscal Year 2031* when funding becomes available. To begin after the Utility Phase has been completed.
- Letting Date to Construction – Date to be determined**
*The above project milestone dates are subject to change due to changes in funding availability within the next Enacted Highway Plan.
**The project's letting date will be set after the needed right-of-way is acquired and the impacted utility relocations have advanced.
Improve traffic operations on KY 55 from KY 1169 to KY 155 (MP 10.5 - 11.3) (portion of 5-8954.0). (2024CCN) – 5-8984.30
As of Summer 2026, (SUBJECT TO CHANGE*):
- Design Phase – Anticipate beginning Fiscal Year 2029 when funding becomes available. Funding Type: SPP.
- Right-of-Way Phase – Anticipate beginning Fiscal Year 2030 when funding becomes available. Funding Type: SPP.
- Utility Phase – Anticipate beginning Fiscal Year 2031 when funding becomes available. Relocations may begin after the Right-of-Way Phase is completed. Funding Type: SPP.
- Construction Phase – Anticipate beginning Fiscal Year 2032* when funding becomes available. To begin after the Utility Phase has been completed.
- Letting Date to Construction – Date to be determined**
*The above project milestone dates are subject to change due to changes in funding availability within the next Enacted Highway Plan.
**The project's letting date will be set after the needed right-of-way is acquired and the impacted utility relocations have advanced.
|