Jefferson and Spencer Counties: KY 55 (Taylorsville Road) & KY 155 (Taylorsville Lake Road) - Project 5-8954.00 (5-8954.10, 5-8954.20, 5-8954.30)

​​​​​​​​​​​​​​​​​​​
KY 55 KY 155 Project Area Map.png

Purpose

The highway improvement project will address increasing traffic demands driven by significant population shifts from urban areas to suburban and rural communities while enhancing safety, reducing congestion, and increasing capacity along the nine-mile corridor.

The Kentucky Transportation Cabinet (KYTC) is implementing a multi-phase improvement project to improve roadway system completeness to accommodate current and future traffic demands. 

The goal of the project includes minimizing or avoiding right-of-way, utility, and environmental impacts. 

Project Scope

The entire project corridor extends from KY 55 (Taylorsville Road) at KY 1169 in Spencer County to KY 155 (Taylorsville Lake Road) near KY 148 in Jefferson County. 

Five alternatives were studied and only one alternative fully meets the project purpose and need. The project team met with local officials in October and November 2022 to discuss the other alternatives.

Jefferson and Spencer Counties (5-8954.10)
Widen KY 55 (Taylorsville Road) and KY 155 (Taylorsville Lake Road) to a five-lane section, including a two-way left-turn lane or a raised median.

This segment extends from MP 2.0 in Spencer County to the Floyds Fork Bridge just south of KY 148 in Jefferson County, covering a total length of 6.247 miles.

Spencer County (5-8954.20)
Widen KY 55 from KY 1169 to KY 155 and KY 155 from KY 55 to MP 2.0, covering a total length of 2.71 miles.

Type of ProjectRoadway reconstruction.
Links

Project Updates

Public Meeting

  •  The Kentucky Transportation Cabinet (KYTC) is postponing the Feb. 20 public meeting on preliminary designs for the KY 55 (Taylorsville Road) and KY 155 (Taylorsville Lake Road) highway improvement project in Spencer and Jefferson Counties due to winter weather. KYTC planned the meeting to update residents and gather their input on the project.

    KYTC will share details on the rescheduled meeting as soon as they are available. The public will have an opportunity to review the preliminary designs, receive project information, and provide feedback once the meeting is held. An online survey will also be made available following the rescheduled event.​​ 

KY 55KY 155 PM Postponed Graphic.png

Local Elected Officials Meetings

  • Meeting #1 - Virtual 
    October 12, 2022
    • This meeting was an opportunity to present the layout, operational analysis, and impacts of the 2+1 alternative as a benchmark while providing four other alternatives for evaluation and discussion. The objective of the meeting was to inform the decision-makers on the safety of operational concerns with a 2+1 roadway alternative for KY 155. The project team presented potential alternatives to ensure the project progressed with the appropriate solutions to accomplish the project goals for safety and increased peak-hour capacity.
    • The project team presented five alternatives: 
      • Alternative 1: 2+1: Baseline Configuration - Highway Plan description and budget are on this alternative. 3-lane alternative providing alternating passing lanes for the entire 9 miles.
      • Alternative 2:  5-Lane: Four-lane highway with a center turn lane for 9 miles. Exceeds current budget.
      • Alternative 3:  Hybrid: 2+1 for the 3.2-mile southern section and 5-lane for the 5.68-mile northern section. Exceeds current budget.
      • Alternative 4: Northern 5-Lane: 5-lane 4.60-mile northern section and the improved intersection at Wilsonville.  Build to Budget Alternative – Addresses priority sections based on available funding for Construction with overruns on R/W and Utilities.
      • Alternative 5: Priority Hybrid: 5-lane for 3.39 miles in the northern section and 3-lane for 2.5 miles in the southern section. Build to Budget Alternative – Addresses priority sections based on available funding for Construction with overruns on R/W and Utilities.
      • An explanation was provided on how the current and projected KY 155 traffic volumes of over 15,000 ADT were outside the operational benefits of a 2+1 roadway. The density of access points along the corridor and planned developments are also adverse to the safe operation of a 2+1 roadway configuration.
      • Deviating from the 2+1 alternative would require the project description and budget to be revised in future Highway Plans to correspond to a larger magnitude project.  At the end of Meeting #1, it was agreed that the 2+1 roadway alternative would not accomplish the purpose and need of the project. The LEOs requested an in-person meeting before recommending an alternative based on operational priorities and available funding.​
  • Meeting #2 - In-Person
    November 28, 2022
    • The project team met with the public officials and stakeholders associated with the project.  The objective of the meeting was to inform the decision-makers and seek recommendations to ensure the project progresses with the appropriate solutions.   The meeting allowed the project team to present the layout, operational analysis, and impacts of the 2+1 alternative as a benchmark while also providing four other alternatives for evaluation and discussion.  It was iterated that during the preliminary engineering and traffic operational analysis, the application of a 2+1 roadway configuration is problematic due to the projected traffic volumes, anticipated growth, and a number of access points along the corridor.  
    • The following developed from the discussion with the public officials and stakeholders:
      • The Project team recommends a 5-lane section for KY 155 from just south of Plum Creek Bridge to Floyds Creek Bridge.   Updated phase cost estimates reflecting this alternative are being developed.
      • The current six-year highway plan description for the project would need to be revised to allow us to be more flexible with the design alternatives, and additional construction funds would need to be added.  Additionally, funds must be shifted to more appropriate fiscal years for the right of way, utility, and construction phases.  These funding issues will need to be addressed by the Kentucky Legislature the next time they are in a budget session (2024).  
      • The above two items must be resolved before we can proceed with the above-discussed approach.
Project Timeline

As of Winter 2024/2025:

  • Design (2025) *Current phase*
  • Right of Way (2025-2027 )

  • Utilities (2026, 2028)

  • Construction (2026, 2028)

*The above project milestone dates are subject to change due to changes in funding availability within the next Enacted Highway Plan.

Project Manager

Keith Downs
Email: keith.downs@ky.gov
Phone: 502.764.0515

 


Contact Information:

District 5
8310 Westport Road
Louisville, KY 40242
Phone: (502) 210-5400
Hours: 8:00 a.m.-4:30 p.m. EST, M-F

Follow District 5



This page is maintained by KYTC District 5 Staff, who may be contacted to make corrections or changes.

Page last updated 2-19-2025​

Follow Us