Purpose
The purpose of the project is to address the immediate needs of the corridor by enhancing its capacity, functionality, and overall safety. 
​Project Scope
KY 1819 (Billtown Road) from north of Colonnades Place to South of Easum Road.
​Type of Project
​Three sections of Billtown Road will be reconstructed with the following improvements:

Section 1 | Easum Road through Mary Dell Lane

  • Add a two-way, left-turn lane from Easum Road through Mary Dell Lane, transitioning into dedicated left-turn lanes approaching intersections.
  • Widen lanes from 9- to 11-foot-wide travel lanes.
  • Improve drainage through ditch widening.
  • Minor realignment of Easum Road intersection with Billtown Road to the south.
  • Add left-turn lane from southbound Billtown Road to Easum Road.
  • Realignment of Lovers Lane intersection with Billtown Road to the south.
  • Add left-turn lane from northbound Billtown Road to Lovers Lane.
  • Add right-turn lane from southbound Billtown Road to Lovers Lane.
  • Add right-turn lane from Lovers Lane to Billtown Road.
  • Add oversize signs and pedestrian activated flashing beacons at Mary Dell Lane.
  • Add sidewalk ramps to connect to the existing crosswalk at Mary Dell Lane and Billtown Road.

Section 2 | Michael Edward Drive through Fairground Road

  • Add left-turn lane from northbound Billtown Road to Michael Edward Drive.
  • Add left-turn lane from northbound Billtown Road to Fairground Road.
  • Add right-turn lane from southbound Billtown Road to Fairground Road.
  • Add right-turn lane from Fairground Road to southbound Billtown Road.
  • Add traffic signal at Billtown Road and Fairground Road intersection.
  • Rebuild sidewalk on south side of Fairground Road and west side of Billtown Road, between Fairground Road and Monticello Forest.

Section 3 | Shady Acres Lane through Colonnades Place

  • Add left-turn lane from southbound Billtown Road to Vintage Creek Drive.
  • Add left-turn lane from northbound Billtown Road to Colonnades Place.
  • Add right-turn lane from southbound Billtown Road to Colonnades Place.
  • Keep existing right-turn lane from Colonnades Place to southbound Billtown Road.
  • Improve drainage through ditch widening along the north side of Shady Acres Lane near its intersection with Billtown Road.
  • Improve drainage through curb and gutter along the west side of Billtown Road.
  • The west side sidewalk is also being rebuilt throughout this section.

​Links

Click here for the interactive website.

SAFERoad Solutions: Dedicated Left and Right Turn Lanes

This website will provide general information and details on the developed alternatives/improvement concepts.​

*Some files are large and may take a few minutes to load.​

Project Press Release

​Project Timeline

As of Summer 2026:
  • This project has been completed. 
Project EngineerLouisville Section Office
Phone: 502.764.0858​


This page is maintained by KYTC District 5 Staff, who may be contacted to make corrections or changes.

Page Last Updated:  07-23-2026

Department of Aviation

Airport Zoning Commission

Department of Rural and Municipal Aid

Local Programs
Local Public Agencies

Department of Vehicle Regulation

Drive.ky.gov
Motor Vehicle Commission

Powered by Google TranslateTranslate