PurposeThe design should improve vehicular mobility and improve pedestrian safety throughout the corridor.
Project Scope
KY 864 (Shelby Street and Logan Street) is to undergo a one-way to two-way conversion from Goss Avenue to south of East Chestnut Street. 

Following the conversion, the route of Goss Avenue, Logan Street, Finzer Street, S Campbell Street, and Chestnut Street Connector will remain KY 864.

Within the project corridor, there are ten existing signalized intersections. Four signalized intersections are proposed to be removed and replaced with all-way stops. The remaining six intersections will be rebuilt. 

The project also provides additional traffic calming along the corridor through the construction of curb extensions. The curb extensions will be installed in areas with higher pedestrian volumes. The curb extensions will reduce the length of pedestrian crossings across the roadway while making pedestrians more visible to drivers and vice-versa. 

Project Timeline
As of Winter 2023 (SUBJECT TO CHANGE):

  • Phase 1 Preliminary Designs were received from a Louisville Metro Public Works consultant. Louisville Metro had oversight of Phase 1/Preliminary design.  
  • Louisville Metro Government coordinates all public outreach. Public outreach and coordination with impacted government agencies and the public are ongoing. 
  • KYTC has acquired the necessary survey for roadway and signal design.
  • Work is ongoing to provide additional information for Phase 2 Design. KYTC will oversee Phase 2/Final design and construction phase.

*The above project milestone dates are subject to change depending on the cabinet's funding constraints.
Public and Stakeholder 
Input/Meetings
Louisville Metro Government will coordinate all public outreach.
  • See the website under the LINKS section.
  • Outreach and coordination with impacted government agencies and the public are ongoing.
​Links
Louisville Metro:
https://louisvilleky.gov/government/public-works/two-way-street-conversions​ 

Design Executive Summary (DES):
05-193.00_ShelbyLogan_DES_081922.pdf
Plans:
05-193.00_ShelbyLogan_Plans_10192022.pdf
Project ManagerAndrew Perez, P.E.
Email:  andrew.perez@ky.gov
Phone:  (502) 764-0539 

  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
8310 Westport RoadLouisvilleKY40242KY8:00 a.m.-4:30 p.m. EST, M-F(502) 210-5400KYTC.District5Info@ky.govhttp://maps.google.com/maps?f=q&source=s_q&hl=en&geocode=&q=8310+Westport+Road+Louisville+KY.+40242&aq=&sll=37.704755,-85.871522&sspn=0.006986,0.016512&ie=UTF8&hq=&hnear=8310+Westport+Rd,+Louisville,+Jefferson,+Kentucky+40242&t=h&z=17https://www.facebook.com/KYTCDistrict5/https://twitter.com/KYTCDistrict5

This page is maintained by KYTC District 5 Staff, who may be contacted to make corrections or changes.

​Page Last Updated: 02-10-2023


Follow Us