KY 136 Bridge Project
Ohio County, KY
The $9.6 million project, which started in January of 2025, will ultimately see the replacement of bridges over Stillhouse Branch (0.02 mile point), Hanley Creek (1.07 mp), Barnett Creek (3.4 mp), Toms Branch (5.4 mp), Little No Creek (5.7 mp) and No Creek (5.9 mp) along with grading and drainage upgrades throughout the corridor.
The final completion date for the entire project is Oct. 2026.