Interstate 65 in Louisville will close between the Watterson Expressway (I-264) and downtown Louisville (Jefferson Street) from June 1- July 31 to speed progress on replacing 3 aging bridges.
The closure will save at least a year of construction restrictions, and a signed detour will be in place. Local street closures and ramp closures will also be needed.
Learn more at I65CentralCorridor.com.

News Release

 

Kentucky Department of Highways District 9

Contact: Allen Blair

606.845.2551 (office)

606.748.3716 (cell)

Allen.Blair@ky.gov​


Work under way on $10 million KY 519 rebuild in Rowan County
Work zone between KY 801 and Clack Mountain
 
FLEMINGSBURG, Ky. (Feb. 24, 2016) – Contractors have begun work on a $10 million highway improvement project along KY 519 in Rowan County.
 
The project includes construction of a new KY 519 with wider travel lanes and shoulders, upgraded pavement and new bridges generally along and to either side of the existing highway between KY 801 near Cave Run Lake north two miles to the bottom of Clack Mountain where it ties in with a previous improvement project.
 
Earlier this month, contractors began removing trees and will continue clearing the right of way through March. Motorists should watch for occasional flagged traffic, and reduced speeds through work zones.
 
Culvert, bridge work and roadway excavation will take place through spring, with the first paving and traffic changes expected by late summer. Construction will continue throughout the year. Project completion is expected by the end of 2017.
 
Work is being done by The Walker Company of Kentucky, Inc., under a $10,254,879.28 low-bid contract with the Kentucky Transportation Cabinet.

Photo:

Department of Aviation

Airport Zoning Commission

Department of Rural and Municipal Aid

Local Programs
Local Public Agencies

Department of Vehicle Regulation

Drive.ky.gov
Motor Vehicle Commission

Powered by Google TranslateTranslate