News Release

 

Kentucky Department of Highways District 9

Contact: Allen Blair

606.845.2551 (office)

606.748.3716 (cell)

Allen.Blair@ky.gov​


Bridge painting project to begin this month in Greenup, Boyd counties
Traffic impacts on KY 2, KY 966

 

FLEMINGSBURG, Ky. (March 19, 2018) – A Kentucky Transportation Cabinet bridge painting project will start Friday, March 23, on KY 2 in Greenup County then move to KY 966 in Boyd County by mid-April.

The work, part of a $378,004 low-bid contract awarded to Euro Paint LLC, includes painting steel support beams, cleaning and concrete repairs to ensure the longevity of the structures.

Contractors expect to start March 23 on KY 2 at the Jeremy Gullett Memorial Bridge at mile marker 13 where it crosses the Little Sandy River. Work will continue through mid-April.

Then, on or around April 15, painting work will start on KY 966 (South Big Run Road) at the Williams Creek bridge at mile marker 5, just off US 60 at Coalton.

During construction, traffic will be one lane across each bridge, with temporary signals controlling all traffic. Motorists should expect delays.


Road work schedules are subject to change depending on weather conditions. Motorists are asked to heed all warning signs, slow down in work zones and remain aware of workers and construction equipment when traveling.

 

###

Photo:

Follow Us