Project Information: 

 

Plans: 

  • ​​Striping plans
    • Summary of Plans: 
        • Resurfacing of Broadway between 9th Street and Baxter Ave
        • New pavement markings along the outer lanes to formally establish parking spaces and bus stops
        • Introduction of left turn lanes west of I-65
        • Curb extensions at certain intersections to provide additional protection for pedestrians
        • Rebuild of signal infrastructure at Barrett Ave
        • Closure of the Barrett Ave “slip lane” and adding additional sidewalk width to account for a future project​

Links:  

​               

Project Schedule: 

  • Construction is now underway. 
  • ​All other construction activities are expected to be completed by Fall 2026.
  • Please note that additional traffic control may be in place after the project completion date due to overlap with the ongoing I-65 bridge repair work.

 

Contact: 



This page is maintained by KYTC District 5 Staff, who may be contacted to make corrections or changes.

​Page Last Updated: 07-31-2026

Department of Aviation

Airport Zoning Commission

Department of Rural and Municipal Aid

Local Programs
Local Public Agencies

Department of Vehicle Regulation

Drive.ky.gov
Motor Vehicle Commission

Powered by Google TranslateTranslate