An Official Website of the Commonwealth of Kentucky
The scope of the project includes minor realignment of KY 44 in the vicinity of Dutchmans Creek Road/ Ryder Lane, approximately 0.4 miles from the Bullitt/Spencer County Line.
Multiple alternatives were developed to improve sight distance at the intersection and assess the possibility of replacing the Dutchmans Creek culvert. Alternative 1 was selected due to the budget constraints.
Alternatives considered:
Alternative 1 (Selected): Realignment of KY 44 from MP 0.227 to the Dutchmans Creek crossing.
Alternative 2 (Not Selected) : Realignment of KY 44 from MP 0.227 to MP 0.598.
As of Fall 2025: Future Project Phases (Subject to Change):
The above project milestone dates are subject to change depending on the Cabinet's funding constraints and various other factors.
Previous Project Development on this corridor includes:
This page is maintained by KYTC District 5 Staff, who may be contacted to make corrections or changes.
Page Last Updated: 11-14-2025