Jefferson County: Widening KY 155 (Taylorsville Road) to 4 lanes with a center turn lane or raised median from I-265 to KY-148 - Project 05-8908

Picture1.png

Purpose

This project aims to address various traffic, access, safety, and operational issues along Taylorsville Road from the intersection of Taylorsville Road and KY 148 to the I-265 Gene Snyder Freeway ramps. While also providing continuity throughout the corridor for roadway users, park users, and residents in eastern Jefferson County.

Within the limits of the 5-8908 project, project 5-808 - KY 155 Taylorsville Rd at South Pope Lick Creek is currently under construction. Project 5-808 will improve the intersection at South Pope Lick Road and realign the offset intersection while replacing the structurally deficient bridge over Pope Lick Creek. The bridge will be constructed to the ultimate width needed for project 5-8908. 

Also, with project 5-808, turn lanes will be provided. The intersection realignment of South Pope Lick Road will improve safety and sight distance at this location.  
​Project Scope
Widening KY 155 (Taylorsville Road) to 4 lanes with a center turn lane or raised median from I-265 to KY-148.
​Type of ProjectThe roadway will be widened to four 11-foot lanes with a 13-foot two-way left-turn lane/raised median with sidewalks on either side in the urban section. In the rural section, the roadway will consist of four 11-foot lanes with a 10-foot usable shoulder (8-foot paved with two feet of crushed stone) and a 13-foot two-way left-turn lane/raised median.

From the beginning of the project limit to South Pope Lick Road, the roadway will consist of the rural section (shown below), and from that point, to OT1 an urban section will be provided, which consists of 5-foot sidewalks on both sides of the roadway.

From OT1 to the end project, a 10-foot wide multi-use path will be provided on the south side of the roadway.

This will be a continuation of the Louisville Loop that will run on the south side of KY 155 between New Hopewell Road (logical termini point) and OT1 and tie in at the South Pope Lick Park.

Please see the typical sections below depicting the urban and rural sections. Please note: the raised median is not shown, consisting of a 2-foot curb and gutter on both sides with sodding between the curbs. 

​Links

5-8908.00 KY 155 Recommended Alignment Sheet 1.pdf
5-8908.00 KY 155 Recommended Alignment Sheet 2.pdf
KY 155 Ultimate Typical Sections.pdf
LINK: Project 5-808 - KY 155 Taylorsville Rd at South Pope Lick Creek is currently under construction.

​Project Timeline
As of Summer 2024 (SUBJECT TO CHANGE*):
  • ​Continue developing the final plans and hold Joint Inspection – November 2024 *tentative
  • Right-of-Way Phase –  Anticipate beginning in 2025.  Funding authorized. Funding Type: STPF
  • Utility Phase – Relocations may begin after the Right of Way Phase has been completed.  Anticipate beginning in late 2025.  Funding authorized.  Funding Type: STPF
  • Construction Phase – To begin after the Utility Phase has been completed.  
    • Construction funding is spread over two years. The first allotment will become available in the federal fiscal year 2026, and the final allotment will be in 2027.*  Funding Type: STPF.
    • Letting Date to Construction – Date to be determined**
*The above project milestone dates are subject to change due to changes in funding availability within the next Enacted Highway Plan.

**The project's letting date will be set after the right-of-way is purchased and impacted utility relocations have advanced. 

Typical Section
The project’s typical sections for KY 155:​​typical on 5-8908.png

To view larger, click here: typical on 5-8908.png

​Project Manager
Design Engineer:
Keith Downs
Email: keith.downs@ky.gov
Phone: 502.764.0515

This page is maintained by KYTC District 5 Staff, who may be contacted to make corrections or changes.

​Page Last Updated: 07-23​-2024​