Henry County: KY 146 Realignment and Widening Project 05-80260

KY 146 henry co.JPG

Purpose
Major realignment and widening of KY 146 (LaGrange Road) in Henry County. The project will enhance the safety of what is currently a narrow, two-lane winding roadway.
ky 146 - henry c.jpg
​Project Scope
The section of KY 146 being improved is between KY 153 (Lake Jericho Road), south of the Interstate 71 interchange, and Broko Lane. That’s between mile points 2.169 and 5.333. 
​Type of Project
​The project includes the paving of 2–12-foot lanes and 8-foot shoulders along with two (2) segments of shoulder widening on both sides of the road, known as Farm Vehicle Lanes, to accommodate the need for a safe pull over the area to check equipment and/or allow other vehicles to pass.
The segments to be widened are:
  • MP 3.29 to MP 3.41
  • MP 4.90 to MP 5.02
Also, with the project, minimal waterline will relocate and widen the bridge over the Little Kentucky River to accommodate the widened roadway. 
​Links

5-80260 Henry Co KY 146 - Typical Section - Paved Farm Vehicle lane.png

5-80260 Henry Co KY 146 - Typical Section - Rural CutFill.png

5-80260 Henry Co KY 146 - Typical Section - Rural Rock Cut.png

*Some files are large and may take a few minutes to load.
​Project Timeline

As of Summer 2024 (SUBJECT TO CHANGE*):
  • Project Awarded - December 16, 2022: E & B Paving Inc. of North Anderson, Ind., was awarded the $19.8 million contract.
  • Construction is scheduled to be completed by the fall of 2024.*
  • Final surfacing is set to begin soon
  • Traffic impacts can be found here: Roadshow
*The date and duration of this work may be adjusted if inclement weather or other unforeseen delays occur.
Traffic/Construction
Motorists should expect changing traffic patterns and lane shifts as construction progresses. This may sometimes include being directed through the work zone via flaggers. 
Signs notifying drivers of the upcoming work have been placed in the area.
Excavation and clearing of the land will follow. That phase will include the burning of debris in accordance with local guidelines. Excavation work is expected to advance to the point that requires the blasting of rock in early to middle April. 
Motorists should expect traffic to be stopped in both directions for up to 20 minutes during the blasting. Drivers should heed any restrictions, proceed cautiously through the construction zone, or seek an alternate route.
​Project Manager
Construction Engineer:
Henry/Trimble Section Office
Phone: 502.564.4255 

Keith Downs (Design)

Email: keith.downs@ky.gov 
Phone: 502.764.0515 

​​This page is maintained by KYTC District 5 Staff, who may be contacted to make corrections or changes.
​Page Last Updated: 09-17​-2024​