GALLATIN COUNTY- U.S. 127 – 3.45 – 5.95 mile points – A slide repair project is in progress. This work will include stabilizing the hillside in several locations.
Crews will be working on U.S. 127 in four locations between mile point 3.45 and south of U.S. 42 (mile point 5.95), a distance of 2.5 miles. The four areas crews will be performing slide repairs are located at: - Mile point 3.45
- Mile point 3.7
- Mile point 5.85
- Mile point 5.95
Once work is completed at one location, crews will move to the next location from the list above. The work will include installing soil nail walls to shore up the hillside, drainage work, adding guardrail and resurfacing in the four work zone locations. A 24/7 single lane closure will be in place near the active work zone location. Temporary signals will be in place to guide motorists safely through the work zone. Once the slide repairs have been completed at all four locations, a single lane closure will be in place throughout the entire 2.5 mile project area to complete guardrail installation and permanent striping. The temporary signals will be moved to both ends of the work zone to guide motorists safely through. The project is expected to be completed by June 30, 2025.
GRANT COUNTYElliston-Mt. Zion Road (KY 1942) – 1.76 mile point – A bridge replacement project on Elliston-Mt. Zion Road is scheduled to begin Thursday, May 29. The project involves removing the existing bridge deck and beams over Napoleon Branch Creek then setting new beams and constructing a new deck. To accommodate the work, the bridge will be closed to traffic during construction beginning Thursday, May 29. A signed detour will be in place to guide motorists around the closure. Ahead of the bridge work, crews are completing a waterline relocation near the site. Once the new bridge is finished, the detour will be removed and the crossing will reopen to traffic. Additional work will continue throughout the project area following the reopening. Motorists are encouraged to follow posted signs and use caution in the area. The project is expected to be completed by July 31, 2025.
Interstate 75 – 157.7 – 162.7 mile points – A resurfacing project on a five-mile stretch of I-75, from just south of Dry Ridge to just north of the Sherman Mt Zion Road (KY 1994) overpass, is scheduled to begin Monday, April 14. Work will include pavement repairs and resurfacing, drainage and erosion control improvements, guardrail updates, bridge maintenance and cross slope corrections. The on/off ramps at Exit 159 to KY 22 in Dry Ridge will also be resurfaced as part of the project.
Signage has already been installed throughout the work zone. Beginning Monday, April 14, crews will begin addressing pavement base failures. A left lane and shoulder closure will be in place in both directions along the entire length of the project area during this phase, and will remain in effect until base failure repairs and bridge pier work are complete.
Traffic shifts will be necessary later in the project as paving operations progress. We will share those updates here and our social media accounts.
The project is expected to be completed by Oct. 15, 2025.
HARRISON COUNTYKY 392 – 0.0 – 3.12 mile points – A resurfacing project on KY 392 beginning at U.S. 62 extending east to Diamond Lane is underway. Base failures have been completed. On Monday, May 12, crews will begin milling/paving operations. This work will take place between the hours of 8 a.m. and 6 p.m. Motorists should expect single lane closures throughout the project area. Flaggers will be in place on both sides of the work zone to guide motorists safely through the area.
KENTON COUNTYTurkeyfoot Road (KY 1303) – 4.97 – 6.25 mile point – A resurfacing project on Turkeyfoot Road between Dudley Road and Dixie Highway (U.S. 25) is in progress. Work is expected to take place between the evening/overnight hours of 8 p.m. and 6 a.m.
Base failure repairs are now complete. Milling/paving operations are in progress. Motorists should expect various single lane closures throughout the project area during working hours. One lane of traffic will be maintained in each direction at all times.
Additionally, a new traffic controller cabinet and radar detection system will be installed at signalized intersections located within the project area. These improvements will improve traffic congestion throughout the corridor.
The resurfacing project is expected to be completed by June 30, 2025
Main Street/Pike Street (U.S. 25) – 12.75 – 13.45 mile points – A resurfacing project on Pike Street/Main Street is underway. Crews will resurface U.S. 25 from east of Simon Kenton Way to Fourth Street (KY 8). This section of road is located in Covington.
Milling and paving operations are now complete. Weather permitting, crews are installing thermoplastic striping within the project limits.
Motorists should expect single lane closures throughout the project area during working hours. In areas where there are two lanes, traffic will be maintained using flaggers. In areas where there are three lanes or more, one lane will be maintained in each direction.
This work is being performed during the evening/overnight hours to minimize travel disruptions in a high traffic volume area. No lane closures will be permitted on weekends from Friday at 5 p.m. to Sunday at 8 p.m.
The project is expected to be completed June 30, 2025.
Richardson Road (KY 1829) – 2.72 – 3.98 mile points – A slide repair project is underway. This project will take place on Richardson Road between Sherbourne Drive and Old Richardson Road. Mowing and brush clearing operations have been completed.
Beginning Monday, April 28, our Robertson County KYTC maintenance crew will perform the slide repair portion of the project. This work will require a 24/7 road closure at the 2.9 mile point (east of Sherbourne Drive). Crews will dig out a section of the road and perform a long-term slip repair. Additionally, breaks in the road in the project area will be patched. Tree trimming and ditching will be performed to improve drainage to ensure a longer lasting repair.
Local traffic will have limited access during this portion of the project. Beginning Friday, May 9, residents living north of 3517 Richardson Road will access their homes via Turkeyfoot Road (KY 1303). This includes Webster Road.
The slide repair portion of the project is expected to be completed Thursday, June 19. Once the slide repair has been completed, the 24/7 road closure will be removed. Maintenance crews will then perform ditching and drainage improvements in the project area. This work will require a daily road closure between 8 a.m. and 7 p.m. with the road reopening daily at 7 p.m. KYTC will advise on social media and the District 6 Roadshow when repairs have been completed.
Madison Pike/E. 20th Street (KY 17) – 20.45 – 22.31 mile points – A resurfacing project on Madison Pike/E. 20th Street is nearing completion. Crews have milled/paved Madison Pike/E. 20th Street from Latonia Avenue to Greenup Street. The project includes the resurfacing of E. 20th Street from Madison Pike to Greenup Street.
Thermoplastic striping in the project limits is now complete. In the coming weeks, a new radar detection system will be installed. This is the last phase of this project. This work will require a single lane closure during working hours with one lane maintained in each direction at all times.
Weather permitting, the project has an expected completion date of June 30, 2025.
Access to Royal Drive at Buttermilk Pike (KY 371) – 2.65 mile point – Beginning Friday, Dec. 13, access to Royal Drive at Buttermilk Pike will be closed to motorists until further notice for infrastructure construction and repair. A portion of Royal Drive will be restricted to construction traffic only, and detour signs will be posted to guide motorists. Local traffic should plan to use alternate routes. For further information about this project, please contact the City of Fort Mitchell.
Bristow Road (KY 1303) – 0.0 – 0.92 mile point – A widening and safety improvement project on Bristow Road will begin on Monday, Sept. 16. Crews will be working on Bristow Road from the KY 536/KY 1303 intersection to the Beechgrove Elementary School. The project includes the following improvements: -Widening throughout the project area from two lanes of vehicular traffic, to four lanes to reduce congestion and improve traffic efficiency -A multi-use path will be built on both sides of Bristow Road to improve bicycle/pedestrian connectivity -Curb/gutter improvements along with storm sewer and drainage work. This work will greatly improve drainage in an area that has been prone to flooding Additionally, the project will eventually tie into a new roundabout at the KY 536 and KY 1303 intersection improving traffic flow, reducing congestion and increasing safety. This work may involve several traffic impacts for equipment moving in and out of the work zone. The project will require traffic switches, and other new traffic patterns. Prior to these occurring, KYTC will send out an updated press release, as well as a post on social media to inform the public. Message boards will also be in place to warn motorists of any upcoming traffic pattern changes. The project is expected to be completed Fall 2025. For more information on this project, visit our KY 536 website here.
Howard Litzler Drive (KY 3070) – 0.0 – 0.87 mile point – A resurfacing project on Howard Litzler Drive between KY 17 and KY 16 is in progress.
Base failure repairs and milling/paving operations are now complete. Crews will return to install rumble strips within the project limits next week, beginning Tuesday, May 27. This work is expected to take place between 8 p.m. and 6 a.m. Motorists should expect a lane closure with flaggers guiding traffic safely through the work zone.
The project is expected to be completed by June 30, 2025.
Highland Pike (KY 1072) – 0.73 – 1.83 mile point – A resurfacing project on Highland Pike between KY 17 and Werner Drive is in progress.
Milling/paving operations are now complete. Crews are working on thermoplastic striping throughout the project limits. Work will occur between the hours of 8 p.m. and 6 a.m. Expect lane closures in the project area with a single lane of traffic maintained in each direction at all times.
The project is expected to be completed by June 30, 2025.
Ernstbridge Road (CR 1021) – A bridge replacement project on Ernstbridge Road (CR 1021) is set to begin Monday, March 17. The existing bridge will remain open to traffic throughout construction, minimizing disruptions for motorists. However, travelers should expect occasional minor delays due to work in the area. The overall project has an expected completion date of Nov. 1, 2025.
Fourth Street/Fifth Street/Highway Avenue (KY 8) – A resurfacing project on KY 8 will resume in Spring 2025. The following portions of KY 8 will be resurfaced:
- Highway Avenue from Spring Street (mile point 6.14) to Western Avenue (mile point 6.23), a distance of 0.09 miles.
- Fifth Street from the exit off-ramp of I-71/75 northbound (mile point 6.68) to the Licking River Bridge (mile point 7.6), a distance of 0.92 miles.
- Fourth Street from west of Garrard Street (mile point 7.41) to Philadelphia Street (mile point 6.66), a distance of 0.75 miles.
As part of the resurfacing project, a roadway reconfiguration will take place on a half-mile stretch of W. Fourth Street from Garrard Street (mile point 7.41) to Johnson Street (mile point 6.89). The current right lane on W. Fourth Street through this area will become a dedicated bicycle lane. The five-foot wide bicycle lane will feature a three-foot buffer from the curb, and two-foot buffer from vehicular traffic. This bicycle lane will be one-way with bicyclists traveling westbound on W. Fourth Street.
Milling/paving operations on Fifth Street concluded on Thursday, Sept. 12.
Fourth Street milling/paving operations and roadway reconfiguration will now take place in Spring 2025. We will provide an additional update once the work is scheduled.
Clay Wade Bailey Bridge (U.S. 25, U.S. 42, U.S. 127) – 13.45 – 13.87 mile points – Routine bridge repairs on the Clay Wade Bailey Bridge will resume on Tuesday, May 27. The project consists of replacing joints, sealing joints, repairing steel and approach/truss drainage repairs.
Due to the I-471 Daniel Carter Beard Bridge Fire, the rest of the repair work for the Clay Wade Bailey Bridge was postponed until Spring 2025. On Wednesday, Nov. 20, (2024) at 8 a.m., the lane closure associated with this work was removed.
On Tuesday, May 27, crews will be returning to the project. A southbound right lane closure will be in place. One lane of traffic will be maintained in each direction. The overhead directional signage will be turned off, and motorists will stay in the designated lane. During this time, crews will be jacking portions of the bridge up, and installing new support for the structure.
On Monday, June 2, crews plan to complete all steel/barrier wall work on the bridge.
Once this work has been completed, a ten-day closure will be necessary to install three modular joints on the bridge. The bridge will be closed to all vehicular traffic during tihs time, but pedestrians and bicyclists will still have access. KYTC will advise on social media and the D6 Roadshow when this closure will be in place.
Mt. Zion Road/Bristow Road (KY 536) – 0.96 – 2.5 mile points – a widening and safety improvement project on KY 536 is in progress. Crews will be working on KY 536 from west of the KY 1303 intersection, to west of Williamswoods Drive.
The project includes the following improvements: -Widening throughout the project area from two lanes of vehicular traffic, to four lanes, to reduce congestion and improve traffic efficiency -A multi-use path will be built on both sides of KY 536 to improve bicycle/pedestrian connectivity -Curb/gutter improvements along with storm sewer and drainage work
Additionally, two roundabouts will be built to improve traffic flow, reduce congestion and increase safety. These roundabouts will be located at the following intersections: -KY 536 and KY 1303 -KY 536 and Hogrefe Road
This work may involve several traffic impacts for equipment moving in and out of the work zone.
A traffic switch took place on Tuesday, Nov. 26. Crews switched traffic between Hogrefe Road and Banklick Road. Traffic was shifted to the south half of the bridge. This configuration will be in place through Spring 2025.
The project will require traffic switches, and other new traffic patterns. Prior to these occurring, KYTC will send out an updated press release, as well as a post on social media to inform the public. Message boards will also be in place to warn motorists of any upcoming traffic pattern changes.
The project is expected to be completed Spring 2027. Learn more about this project here.
PENDLETON COUNTY- U.S. 27 – 0.0 – 9.65 mile point –A resurfacing project on U.S. 27 from the Harrison County Line to just south of Kennedy Bridge Road is underway.
Trenching operations and asphalt surface is complete. Thermoplastic markings/striping still remain. Additionally, inlaid pavement marker installation in the City of Falmouth.
This work will require single lane closures throughout the project area between the working hours of 7 a.m. and 7 p.m. Flaggers will be in place to direct traffic around the work zone.
This project is expected to be completed by June 30, 2025.
|