​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​D6 Roadshow Title.png​​


D6 Roadshow banner header.png

ROADSHOW for the W​e​​ek ​​of​ Sept. 14, 2025

New items or changes in project status are italicized.​

*Inclement weather or other unforeseen circumstances may occur, so the information below is strictly of an advisory nature and is subject to change with no notice.

Pothole patching, sweeping, drain & ditch work, litter pick up, brush clearing, culvert repairs and additional work by our KYTC maintenance crews may occur on major interstates/state routes during non-peak daytime hours and at night. 

Motorists should watch for roadside maintenance on interstates/highways throughout the district DAILY. We will send out information to the public if these tasks require significant impacts to traffic.

Follow KYTC D​istrict 6 social media for the latest updates on the rest of the projects below. Facebook or Twitter. To subscribe to District 6 press releases, please click HERE.


I-275 CARROLL CROPPER BRIDGE UPDATES


As of Wednesday, Sept. 10, all expansion joint repairs are now complete. Preparations for floor beam repairs are still in progress — phasing and design have been approved, and the final step is getting a scaffolding plan approved before work can begin. Large steel support beams could be delivered on-site as soon as the end of this week. More updates on the floor beam repairs will follow.​

***

On Tuesday, Dec. 17, KYTC implemented weight limits for emergency vehicles and temporary lane restrictions on the I-275 Carroll Cropper Memorial Bridge. While the bridge remains safe for passenger vehicles, a recent inspection found deterioration in some of its steel.

New Emergency Vehicle Weight Limits:

  • Single Axle: 16 tons
  • Tandem Axle: 23 tons
  • Gross Weight: 31 tons

The weight reduction will not impact commercia​l vehicle traffic due to semi-trucks having more axles to distribute the weight.

Overweight Over-Dimensional vehicles are not permitted on the bridge at this time due to current lane restrictions.

KYTC bridge engineering analysis shows the reduced weight limit and lane restrictions are needed as a precaution, and to prevent further damage until the structure can be repaired. The repairs were added to a previously scheduled steel repair project that is currently in progress.

CURRENT TRAFFIC IMPACTS:

A temporary speed limit reduction of 55 MPH is currently in place. A queue warning system has also been installed on both sides of the river to warn motorists of any stopped or slowed traffic on/near the bridge.

Eastbound Traffic (drivers heading from Indiana to Kentucky):

  • A right lane closure is in place before the bridge approach. Once you're on the bridge, all lanes are open.

Westbound Traffic (drivers heading from Kentucky to Indiana):

  • On Wednesday, Sept. 10, traffic was switched to the left lane from the Petersburg exit to past the truss of the bridge. 

T-1 Steel Repairs:

  • ​The T-1 steel repairs have been completed.

Looking Ahead:

  • Once floor beam repairs are made, current weight restrictions for emergency vehicles will be lifted.
Learn more about the project here.


Districtwide RR Title.png

VARIOUS ROUTES: Districtwide striping is in progress. Contractors will be striping various routes within the district: Boone, Bracken, Campbell, Carroll, Gallatin, Grant, Harrison, Kenton, Owen, Pendleton, and Robertson. Most work will occur during daytime working hours of 8 a.m. to 8 p.m. Routes with higher traffic volume will be completed during nights or weekends to minimize traffic impacts.

Interstate routes will be compl
eted first followed by primary state routes then secondary routes. Striping is a slow-moving mobile operation. Motorists should slow down and expect slow moving traffic in mobile work zones. Please avoid driving over fresh, wet paint. The project has a completion date of late September.

KENTON AND CAMPBELL COUNTIES

A preventive maintenance project began on Tuesday, June 24, on multiple routes in Kenton and Campbell counties.

The project includes crack sealing, electrical work and application of a thin asphalt overlay known as a thinlay. Thinlays are used as a pavement preservation treatment to restore surface conditions and extend the service life of roads that are still structurally sound.

Crack sealing operations, electrical work items, thermoplastic striping and paving work are complete. A few misc. tasks still remain.

Locations:

Madison Pike (KY 17), Kenton County — From Moffett Road (KY 2042) at mile point 7.97 to just north of KY 14 at mile point 4.94. Paving work is now complete. Rumble strips are the last task for this portion and have not been scheduled.

Dixie Highway (U.S. 25), Kenton County — From Hallam Avenue at mile point 6.26 to Carran Drive at mile point 7.88. Paving and thermoplastic striping are now complete. The last task for this portion of the project is reinstalling Qwick Kurb lane separators on the southbound left turn lanes into Crestview Hills Town Center.

Alexandria Pike (U.S. 27), Campbell County — From Bluegrass Avenue at mile point 20.49 to Moock Road (KY 1632) at mile point 19.84. This portion of the project is now complete.

The project has a completion date of Sept. 30, 2025.

BOONE AND KENTON COUNTIES

A resurfacing project is in progress on several routes in Boone & Kenton Counties. This project will also include sidewalk ramp reconstruction in various areas, sidewalk/curb repairs, curb box inlet repairs, radar detection at several intersections and the installation of signal head and other various signage. 

The following locations will be resurfaced:

  • U.S. 42 from east of Ewing Blvd. (14.5 mile point) to Main Street (U.S. 25) (15.28 mile point).
  • Dixie Highway (U.S. 25) from north of Dortha Avenue (10.9 mile point) to the Boone/Kenton County line (11.4 mile point).
  • Dixie Highway (U.S. 25) from the Boone/Kenton County line (4.97 mile point) to north of Hallam Avenue (6.26 mile point). 
  • Dixie Highway (U.S. 25) from north of Marian Drive (8.13 mile point) to Orphanage Road (KY 371) (8.65 mile point)
Milling and paving operations on U.S. 42 in Boone County have been completed. Milling on Dixie Highway from north of Marian Drive to Orphanage Road has been completed. Paving operations are underway. We will provide further updates once milling and paving work has been scheduled on the other portions of the project.


Base failure repairs have not yet been scheduled on the other two portions of the project on Dixie Highway. 


The project also includes a roadway reconfiguration of Dixie Highway from Turfway Road to northeast of Commonwealth Avenue. KYTC will provide additional details related to this safety improvement at a later date.

The project is expected to be completed by Oct. 31, 2025.​


BOONE AND KENTON COUNTIES

A guardrail installation project on a portion of River Road (KY 8) and Richwood Road (KY 338) will begin on Thursday, Sept. 11.

River Road (KY 8), Kenton County – from 641 River Road (mile point 2.27) to just east of 570 River Road (mile point 2.53). Crews will begin work on this portion of the project on Thursday, Sept. 11. This work will require a single lane closure between the working hours of 8 a.m. and 6 p.m. Flaggers will be onsite to direct traffic. This work is expected to take two days.

Richwood Road (KY 338), Boone County – from near Richwood Church Road (mile point 2.51) to mile point 2.44. This portion of the project has not been scheduled. We will provide an update once the work has been scheduled. 

Weather permitting, the project is expected to be completed by Dec. 1, 2025.



CARROLL AND GALLATIN COUNTIES
​​​
  • I-71 – 52.77 – 57.36 mile points – A widening project aimed at reducing congestion and improving safety on I-71 in Carroll and Gallatin counties is in progress. The project will widen I-71 from its configuration of two lanes in each direction, to three lanes.

    A traffic switch on I-71 northbound and southbound between Exit 55 (KY 1039) and Exit 57 (Sparta) has occurred. Motorists will shift toward the median and then shift back over to the existing roadway. This traffic pattern is expected to be in place for several weeks.

    This widening project includes a bridge replacement over KY 47. The current bridges will be replaced with a new, single span bridge matching the median widening throughout the project area.

    The speed limit in the work zone has been reduced to 55 MPH, and law enforcement will be on-site to ensure compliance. Please, drive carefully throughout the work zone. Weather permitting, the overall project is expected to be completed Nov. 1, 2026.


Boone County RR Title.png
  • North Bend Road (KY 237) – 6.49 – 9.21 mile points – A preventive maintenance project on North Bend Road beginning at Golf Club Drive extending north to just south of Petersburg Road (KY 20) is now complete.


  • North Bend Road (KY 237) – 9.21 – 10 mile point – A resurfacing project on North Bend Road from just south of Petersburg Road (KY 20) extending just north of Coral Drive is in progress.

    Base failure repairs and milling/paving operations are now complete. Permanent striping is the final task for this project before completion.

    To limit traffic disruptions, this work will take place during the evening/overnight hours of 7 p.m. to 6 a.m. 

    Weather permitting, the project is expected to be completed Oct. 15, 2025. 

  • Burlington Pike (KY 18) – 8.2 mile point – Burlington Pike has reopened just west of Green Acres Lane following a cross culvert installation project. Motorists should be advised that steel plates are in place to allow time for the concrete at the project site to cure. Appropriate signage is in place to warn motorists of the bump. Crews will return to the project within the next couple weeks. KYTC will provide further updates prior to crews returning to the site. 

    Once crews return, they'll focus on milling/paving near the project area. This work is expected to include a single lane closure with flaggers on both sides of the work zone.


  • Dixie Highway (U.S. 25) – 8.8 mile point – Duke Energy is performing utility work on a portion of Dixie Highway. Work is taking place near the Northern Kentucky Water District water tower, between Empire Drive and the intersection of Dixie Highway/Weaver/Richardson Road. 

    A single lane closure will be in place daily from 9 a.m. to 3 p.m., with flaggers on-site to direct traffic through the work zone. 

    Weather permitting, this permit project is expected to be completed by late September.

  • I-71 – 69.8 – 77.4 mile points – A resurfacing project on I-71 from the Boone/Gallatin County line to the I-71 and I-75 interchange is in progress.  

    This work will require single lane closures as needed from 7 p.m. to 7 a.m. Traffic switches and lane shifts will occur as work progresses. 
    Beginning Friday, Sept. 12 at 7 p.m. through Monday, Sept. 15 at 7 a.m., crews will be performing a weekend blitz in the project area. This work will require a single right lane closure on both I-71 northbound and southbound from the I-71 and I-75 split to the Boone/Gallatin Co. line. 

    Additionally, high friction surface will be added to the I-71 northbound to I-75 northbound ramp to improve traction.

    No lane closures will be permitted during Thanksgiving holiday weekend. The project has an expected completion date of Nov. 30, 2025. Read more about the project here.


  • North Bend Road (KY 237) – 9.56 – 9.98 mile points – The addition of a turning lane along with several other improvements on North Bend Road in Hebron related to a new commercial development near First Financial Bank is now complete.


  • Richardson Road (KY 842)  0.12 mile point  The bridge east of Dixie Highway (U.S. 25) on Richardson Road at the 0.12 mile point now has a weight limit reduction of three tons. While the bridge remains safe for vehicular traffic, a recent inspection found some deterioration. KYTC bridge engineering analysis shows the weight limit reduction is needed as a precaution, and to prevent further damage until the bridge can be repaired. KYTC is working with the railroad company to coordinate a repair plan. We will provide updates once the bridge repair plan has been scheduled. Prohibited vehicles can detour using Industrial Road (KY 1829) or Mt. Zion Road (KY 536).

  • Donaldson Highway (KY 236) 0.0 – 1.6 mile points – A widening and safety improvement project on KY 236 (Donaldson Highway) between KY 842 (Houston Road) and KY 3076 (Mineola Pike) is in progress. The project will widen the 2-mile stretch of road to five lanes with curb and gutter, including two through-lanes in each direction with a center turn lane. A sidewalk and multiuse path also will be added.​
    ​​
    The project has an overall completion date of October ​2025. You can find more information on this project here. ​

Bracken County RR Title.png

  • AA Highway (KY 9) – 0.0 – 5.39 mile point – A resurfacing project on a portion of the AA Highway beginning at the Mason/Bracken County line extending north to just south of KY 19 is in progress.

    Mainline paving is now complete. Shoulder paving operations are currently underway. A single lane closure will be in place during working hours of 7 a.m. to 7 p.m. with flaggers on-site to direct traffic around the work zone. 

    Motorists are advised to plan ahead and expect delays during working hours. Weather permitting, the project is expected to be completed by Nov. 15, 2025.


  • Mary Ingles Highway (KY 8) – 7.07 mile point – Bridge deck restoration and waterproofing work is on the Mary Ingles Highway bridge over Locust Creek is now complete.

Campbell County RR Title.png

  • Martha Layne Collins Boulevard (KY 2345) – 0.0 – 0.59 mile points – A resurfacing project on a portion of Martha Layne Collins Boulevard beginning at Alexandria Pike (U.S. 27) extending to Johns Hill Road (KY 3490) is now complete. Radar installation still remains, but will cause limited traffic impacts.


  • Pooles Creek Road (KY 1998) – 0.0 – 1.73 mile points – A resurfacing project on Pooles Creek Road between AA Highway (KY 9) and Alexandria Pike (U.S. 27) is now complete. Radar installation still remains, but will cause limited traffic impacts.

Carroll County RR Title.png

  • KY 2949 – 0.0 – 2.92 miles – A resurfacing project on KY 2949 from KY 1112 to U.S. 42 is now complete.


  • I-71 – 38.8 – 53.4 mile points – A maintenance repair project is in progress on I-71 from the Trimble County line to the Gallatin County line.

    Crews have been hard at work addressing the roughest sections of pavement along this corridor. The most serious base failures have already been repaired, and contractors are now milling and resurfacing those problem spots to help reduce potholes and improve ride quality.

    Resurfacing work is expected to take place Sunday through Friday from 8 p.m. to 8 a.m. requiring a single lane closure during working hours. All lanes will reopen at 8 a.m.

    ***

    This is a maintenance repair project, not a full resurfacing of all lanes. These operations will be limited to the mainline interstate. Shoulders and on/off ramps will not be included with this project.

    A reduced speed limit of 55 MPH will be enforced throughout the work zone, with law enforcement on-site to ensure compliance.

    No lane closures will be permitted during the Thanksgiving holiday weekend.

    The project began on Friday, Aug. 8, with completion expected by Nov. 30, 2025. Learn more about the project here.​


Gallatin County RR Title.png

  • U.S. 42 – 0.17 – 3.33 mile point – A resurfacing project on U.S. 42 beginning near Nucor Steel extending east to the north ramps of KY 1039 is now complete.

Grant County RR Title.png
  • KY 3373 – 0.0 – 0.14 mile point – A resurfacing project on KY 3373 located between KY 491 in Crittenden will begin on Friday afternoon, Sept. 12.

    Paving operations are expected to take a couple hours. Motorists should expect a single lane closure with flaggers on-site to direct traffic during paving operations.

    Weather permitting, the project is expected to be completed by late September. 

  • Jonesville Road (KY 36) – A slide repair project on two sections of Jonesville Road began on Wednesday, Sept. 3.

    Crews will perform slide repairs at the following locations:
    Mile point 0.81: located just east of Folsom Jonesville Road (KY 1132)
    Mile point 5.02: located near Fords Mill Road

    A 24/7 single lane closure will be in place, with temporary traffic signals installed at each end of the work zone to guide traffic.

    Weather permitting, the project is expected to be completed by the end of October.

  • Cordova Road (KY 36) – 16.56 mile point – A maintenance project that required a full road closure for cross pipe repairs is now complete. 

  • Simpson Ridge Road (KY 1995) – 3.83 – 5.98 mile points – A resurfacing project on Simpson Ridge Road from Heekin Road (KY 2937) to KY 36 is in progress.

    Base failure repairs and milling operations have been completed. Paving operations are in progress. Flaggers will be on-site from 8 a.m. to 6 p.m. to direct traffic around the work zone. Paving operations are expected to be completed by Friday evening, Sept. 12.

    Weather permitting, the project is expected to be completed by early October.


  • Gardnersville Road (KY 491) – 5.42 – 8.36 mile point – A resurfacing project on Gardnersville Road from North Fork Road to the Grant/Pendleton County line is in progress. 

    Base failure repairs are now complete. Milling and paving operations will begin on Monday, Sept. 15. A single lane closure will be in place during daytime working hours of 8 a.m. to 6 p.m. with flagg​​ers on-site to direct traffic.

    Weather permitting, the project is expected to be completed by early October.


  • KY 22 – 10.68 – 11.55 mile point – A diamond grinding and roadway improvement project on KY 22 between Warsaw Road (KY 467) and U.S. 25 is scheduled to begin on Sunday, Aug. 24. 

    Work will be completed in phases and include diamond grinding and grooving of pavement, partial depth pavement repairs, sidewalk and curb work, guardrail replacement, and installation of permanent striping and pavement markers. A new radar detection system will also be added at signalized intersections within the project limits, replacing embedded traffic loops. 

    Overnight single lane closures will be in place from 8 p.m. to 7 a.m., with one lane in each direction maintained at all times. Flaggers will be present when work is occurring in intersections.

    Some work items may also occur during non-peak daytime hours. To minimize traffic impacts, any daytime closures will be limited to the western portion of the project. All work requiring lane closures on the eastern portion will take place overnight.

    No lane closures will be in place during the Thanksgiving holiday weekend.

    Weather permitting, the project is expected to be completed by Nov. 30, 2025.

    ​​
  • KY 491 – 0.02 mile point – A bridge replacement project on the KY 491 crossing over Bullock Pen Creek between Rainbow Drive and KY 1942 is nearing completion.​

    The bridge officially opened to traffic on Thursday, Sept. 11, around 2 p.m. 

    The bridge had been closed since Monday, June 23, for the replacement. While the new bridge is now open, crews will still be working in the project area to wrap up remaining tasks. The project will be considered complete once thermoplastic striping is installed Sunday, Sept. 14. Please use caution and watch for workers as you travel through. 


  • Elliston-Mt. Zion Road (KY 1942) – 1.76 mile point – A bridge replacement project on Elliston-Mt. Zion Road is in progress.

    The project involves removing the existing bridge deck and beams over Napoleon Branch Creek then setting new beams and constructing a new deck.

    To accommodate the work, the bridge was closed to traffic on Thursday, May 29. A signed detour will be in place to guide motorists around the closure.

    Once the new bridge is finished, the detour will be removed and the crossing will reopen to traffic. Additional work will continue throughout the project area following the reopening.

    Motorists are encouraged to follow posted signs and use caution in the area.

    The project is expected to be completed by October 2025.


  • I-75 – 157.7 – 162.7 mile points – A resurfacing project on a five-mile stretch of I-75, from just south of Dry Ridge to just north of the Sherman Mt Zion Road (KY 1994) overpass is now complete. Learn more about this project here.​

Harrison County RR Title.png

NO SIGNIFICANT TRAFFIC IMPACTS/PROJECTS AT THIS TIME.​


Kenton County RR Title.png
  • I-75/I-275 Interchange – A routine bridge inspection of the I-75/I-275 interchange will begin on Monday, Sept. 15. Inspection crews will perform detailed evaluations of the interchange bridges. Work will include standard safety inspections along with specialized testing of bridge components. 

    Traffic impacts will vary throughout the inspection period. Motorists may encounter shoulder closures, single lane closures, or double lane closures on the interchange ramps, as well as on I-75 and I-275 approaching the interchange. Lane closures are scheduled to avoid the morning and evening rush hours.

    Use caution when traveling through the work zone and watch for inspection vehicles and crews.

    Weather permitting, this inspection is expected to be completed by Tues., Sept. 30. 


  • Locust Pike (KY 1930) -- ​3.77 - 4.34 mile points -- A maintenance project from south of Spanton Road to Feiser Road will begin on Monday, Sept. 15. Crews will be performing culvert replacement, driveway pipe replacement, drainage/ditching operations and mowing. This work will require a 24/7 closure in the project area from Monday, Sept. 15 at 8 a.m. to Wednesday, Sept. 17 at 8 p.m. No thru traffic will be permitted. Local traffic will be permitted for those with homes in the project area. 

    Homeowners living at/north of 8819 Locust Pike will use Decoursey Pike (KY 177) via the north entrance. Homeowners living south of 8819 Locust Pike will use Decoursey Pike via the south.

    Weather permitting, this project is expected to be completed Wednesday, Sept. 17 at 8 p.m.

  • Bristow/Shaw/Independence Roads (KY 536) -- 3.1 - 3.37 mile points -- A maintenance project will begin on Tuesday, Sept. 16. Crews will replace a storm drainage system, relocate pipes and perform drainage/ditching operations to improve safety. This work will require a lane closure on KY 536 from east of Greenbrook Drive to between Bristow and Shaw Roads on Independence Road. Temporary traffic signals will be installed on both sides of the work zone. These will remain in place 24/7 throughout the entirety of the project.

    Additionally, a full road closure of Independence Road (KY 2045) at the intersection with Bristow Road (0.0 mile point) is needed to allow our crews a safe area to work.

    Weather permitting, this project is expected to be completed Tuesday, Oct. 7. KYTC will provide updates if additional days of work are needed for the project.


  • Richardson Road (KY 1829) – 2.72 – 3.24 mile points – A maintenance project between Sherbourne Drive and Webster Road is now complete. A more permanent in-place patching project will take place this Fall to improve roadway conditions. We will provide an update on that work is scheduled.

  • ​Madison Pike (KY 17) -- 16.14 - 17 mile points -- A hillside stabilization project will begin on Madison Pike between Pioneer Park and Old Madison Pike on Tuesday, Sept. 16. This work will require a daytime single southbound right lane closure in the project area between the working hours of 7 a.m. and 3 p.m. The lane will reopen daily by 3 p.m. Weather permitting, this project is expected to be completed Tuesday, Sept. 30.

  • Green Road (KY 2043) – 3.35 – 3.40 mile points – Green Road near the 12800 block was reopened to traffic around 1 p.m. on Tuesday, Aug. 12,​ following completion of a culvert replacement project that required an extended road closure.

    During the closure, crews replaced the old culvert, repaved the roadway and restored a smooth driving surface. This work marked the final phase of a larger project that began last year, which included fence relocation, site clearing, waterline relocation and guardrail installation ahead of the culvert replacement.

    Additional guardrail installation is expected to take place the week of Sept. 14. Please drive carefully through the work zone as crews complete this final task.

    The project is expected to be completed by the end of September.
  • Fowler Creek Road (KY 1486) ​ 3.28 ​ 4.44 mile points  ​A resurfacing project on Fowler Creek Road between the Fowler Creek Road Connector (KY 1486C) and Madison Pike (KY 3035) is nearing completion. Base failure repairs and milling/paving operations are now complete. Radar installation is the final task of the project.

  • Whites Road (KY 1930) – 0.0 – 1.19 mile point – A resurfacing project on Whites Road from Decoursey Pike (KY 177) extending north to Locust Pike (1930) will begin on Wednesday, Sept. 3.

    Base failures were completed on Thursday, Sept. 4. 

    Milling and paving operations are expected to follow mid-September. Once scheduled, this work is expected to take place between 7 a.m. and 7 p.m. Motorists should expect a single lane closure. Flaggers will be on-site to direct traffic through the work zone.We will provide an update once that portion of the project is scheduled.

    Weather permitting, the project is expected to be completed by late September.


  • Old Hands Pike/Waymans Branch Road (KY 3716) 0.0  0.05 mile points  A Sanitary District 1 (SD1) sewer project will take place beginning Wednesday, Aug. 13. This project will include a two-month closure of Old Hands Pike/Waymans Branch Road from Madison Pike (KY 17) to Misty Lane. The closure will be in place 24/7.

    Access to nearby businesses will be maintained using a signed detour: KY 17 to Hands Pike (KY 1501), to Madison Pike (KY 3035), and back on to Old Hands Pike/Waymans Branch Road.

    This is a permits project approved by KYTC for SD1. Weather permitting, the project is expected to be completed Oct. 13, 2025.

  • Access to Royal Drive at Buttermilk Pike (KY 371) – 2.65 mile point – Beginning Friday, Dec. 13, access to Royal Drive at Buttermilk Pike will be closed to motorists until further notice for infrastructure construction and repair.

    A portion of Royal Drive will be restricted to construction traffic only, and detour signs will be posted to guide motorists. Local traffic should plan to use alternate routes.

    For further information about this project, please contact the City of Fort Mitchell​.

  • Bristow Road (KY 1303) – 0.0 – 0.92 mile point – A widening and safety improvement project on Bristow Road began in September 2024. Crews will be working on Bristow Road from the KY 536/KY 1303 intersection to the Beechgrove Elementary School.

    The project includes the following improvements:
    -Widening throughout the project area from two lanes of vehicular traffic, to four lanes to reduce congestion and improve traffic efficiency
    -A multi-use path will be built on both sides of Bristow Road to improve bicycle/pedestrian connectivity
    -Curb/gutter improvements along with storm sewer and drainage work. This work will greatly improve drainage in an area that has been prone to flooding

    Additionally, the project will eventually tie into a new roundabout at the KY 536 and KY 1303 intersection improving traffic flow, reducing congestion and increasing safety.

    A traffic shift took place on Wednesday, Aug. 20. This shift moved motorists to the new pavement from south of Beechgrove Drive (0.75 mile point) to north of Timber Lane (0.55 mile point). 

    This work may involve several traffic impacts for equipment moving in and out of the work zone. The project will require traffic switches, and other new traffic patterns. Prior to these occurring, KYTC will send out an updated press release, as well as a post on social media to inform the public. Message boards will also be in place to warn motorists of any upcoming traffic pattern changes.

    The project is expected to be completed Fall 2025. For more information on this project, visit our KY 536 website here​.

  • Ernstbridge Road (CR 1021)  A bridge replacement project on Ernstbridge Road (CR 1021) is in progress. The existing bridge will remain open to traffic throughout construction, minimizing disruptions for motorists. However, travelers should expect occasional minor delays due to work in the area. The overall project has an expected completion date of Nov. 1, 2025.​

  • Mt. Zion Road/Bristow Road (KY 536) ​ 0.96 ​ 2.5 mile points ​ ​A widening and safety improvement project on KY 536 is in progress. Crews will be working on KY 536 from west of the KY 1303 intersection, to west of Williamswoods Drive.

    The project includes the following improvements:
    ​-Widening throughout the project area from two lanes of vehicular traffic, to four lanes, to reduce congestion and improve traffic efficiency
    -A multi-use path will be built on both sides of KY 536 to improve bicycle/pedestrian connectivity
    -Curb/gutter improvements along with storm sewer and drainage work

    Additionally, two roundabouts will be built to improve traffic flow, reduce congestion and increase safety. These roundabouts will be located at the following intersections:
    -KY 536 and KY 1303
    -KY 536 and Hogrefe Road

    This work may involve several traffic impacts for equipment moving in and out of the work zone.

    The project will require traffic switches, and other new traffic patterns. Prior to these occurring, KYTC will send out an updated press release, as well as a post on social media to inform the public. Message boards will also be in place to warn motorists of any upcoming traffic ​pattern changes.

    The project is expected to be completed Spring 2027. Learn more about this project here.

Owen County RR Title.png
NO SIGNIFICANT TRAFFIC IMPACTS/PROJECTS AT THIS TIME.


Pendleton County RR Title.png

  • U.S. 27 – 14.7 – 14.9 mile points – A guardrail installation project on a portion of U.S. 27 near Country Club Drive is now complete.

  • Lennoxburg-Mt. Auburn Road (KY 10) – 6.10 – 7.83 mile points – A resurfacing project on Lennoxburg-Mt. Auburn Road from KY 159 to Fisher Road is now complete.

  • Concord-Butler Road (KY 609) – 0.0 – 1.92 mile points – A resurfacing project on Concord-Butler Road (KY 609) from KY 159 to Davis Road is now complete.

  • Center Ridge Road (KY 3184) – 0.0 – 4.27 mile points  A resurfacing project on Center Ridge Road from KY 467 to KY 491 will begin soon. KYTC will advise once this portion of the project has been scheduled.

    Once work begins, a single lane closure will be in place during the daytime working hours of 7 a.m. and 6 p.m. Flaggers will be on-site to guide traffic safely through the work zone.

    Weather permitting, the project is expected to be completed by Nov. 30, 2025.

  • Lightfoot Fork Road (1657) – 6.1 mile point – A soil nail installation project on Lightfoot Fork Road (KY 1657) is now complete.


  • KY 159 – 2.87 – 4.66 mile points – A resurfacing project on KY 159 from Grimes Road extending north to the southern end of North Little Kincaid Creek bridge is now complete.

Robertson County RR Title.png
NO SIGNIFICANT TRAFFIC IMPACTS/PROJECTS AT THIS TIME.











Click_Here_to_Subscribe_to_our_news_and_traffic_updates_so_you_never_miss_a_update
Go_Kentucky_Applcation_for_planning_your_travel_around_recent_traffic_and_construction_updates
Buttons-Trimarc.jpg
Ohio_Go_Know_Before_You_Go_Traffic_and_construction_project_impacts_on_your_commute
BSBCP BUTTON - RESIZED.png
KY 536 SITE - RESIZED.png
DNKYP BUTTON - RESIZED.png
D6 FACEBOOK Button.png 

​​
D6 TWITTER_X Button.png








​​This page is maintained by Jake.Ryle@ky.gov and James.Heatherly@ky.gov​, who may be contacted to make corrections or changes.

Follow Us