​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​D6 Roadshow Title.png​​


D6 Roadshow banner header.png

ROADSHOW for the W​e​​ek ​​of​ Oct. 5, 2025

New items or changes in project status are italicized.​

*Inclement weather or other unforeseen circumstances may occur, so the information below is strictly of an advisory nature and is subject to change with no notice.

Pothole patching, sweeping, drain & ditch work, litter pick up, brush clearing, culvert repairs and additional work by our KYTC maintenance crews may occur on major interstates/state routes during non-peak daytime hours and at night. 

Motorists should watch for roadside maintenance on interstates/highways throughout the district DAILY. We will send out information to the public if these tasks require significant impacts to traffic.

Follow KYTC D​istrict 6 social media for the latest updates on the rest of the projects below. Facebook or Twitter. To subscribe to District 6 press releases, please click HERE.


I-275 CARROLL CROPPER BRIDGE UPDATES


The scaffolding plan for the bridge has received final approval. Starting the week of Sept. 21, crews will begin installing scaffolding to prepare for floor beam repairs.

Once those repairs officially begin, we’ll provide another update along with a revised completion date for the overall project. Floor beam repairs are the final phase of work for the project. ​


***

On Tuesday, Dec. 17, KYTC implemented weight limits for emergency vehicles and temporary lane restrictions on the I-275 Carroll Cropper Memorial Bridge. While the bridge remains safe for passenger vehicles, a recent inspection found deterioration in some of its steel.

New Emergency Vehicle Weight Limits:

  • Single Axle: 16 tons
  • Tandem Axle: 23 tons
  • Gross Weight: 31 tons

The weight reduction will not impact commercia​l vehicle traffic due to semi-trucks having more axles to distribute the weight.

Overweight Over-Dimensional vehicles are not permitted on the bridge at this time due to current lane restrictions.

KYTC bridge engineering analysis shows the reduced weight limit and lane restrictions are needed as a precaution, and to prevent further damage until the structure can be repaired. The repairs were added to a previously scheduled steel repair project that is currently in progress.

CURRENT TRAFFIC IMPACTS:

A temporary speed limit reduction of 55 MPH is currently in place. A queue warning system has also been installed on both sides of the river to warn motorists of any stopped or slowed traffic on/near the bridge.

Eastbound Traffic (drivers heading from Indiana to Kentucky):

  • A right lane closure is in place before the bridge approach. Once you're on the bridge, all lanes are open.

Westbound Traffic (drivers heading from Kentucky to Indiana):

  • Traffic ic utilizing the left lane beginning at the Petersburg exit to past the truss of the bridge.

T-1 Steel Repairs:

  • ​The T-1 steel repairs have been completed.

Looking Ahead:

  • Once floor beam repairs are made, current weight restrictions for emergency vehicles will be lifted.
Learn more about the project here.


Districtwide RR Title.png

VARIOUS ROUTES: Districtwide striping is in progress. Contractors will be striping various routes within the district: Boone, Bracken, Campbell, Carroll, Gallatin, Grant, Harrison, Kenton, Owen, Pendleton, and Robertson. Most work will occur during daytime working hours of 8 a.m. to 8 p.m. Routes with higher traffic volume will be completed during nights or weekends to minimize traffic impacts.

Interstate routes will be compl
eted first followed by primary state routes then secondary routes. Striping is a slow-moving mobile operation. Motorists should slow down and expect slow moving traffic in mobile work zones. Please avoid driving over fresh, wet paint. The project has a completion date of early October.


BOONE AND KENTON COUNTIES

A resurfacing project is in progress on several routes in Boone & Kenton Counties. This project will also include sidewalk ramp reconstruction in various areas, sidewalk/curb repairs, curb box inlet repairs, radar detection at several intersections and the installation of signal head and other various signage. 

The following locations will be resurfaced:

  • U.S. 42 from east of Ewing Blvd. (14.5 mile point) to Main Street (U.S. 25) (15.28 mile point). This portion of the project is now complete.
  • Dixie Highway (U.S. 25) from north of Dortha Avenue (10.9 mile point) to the Boone/Kenton County line (11.4 mile point).
  • Dixie Highway (U.S. 25) from the Boone/Kenton County line (4.97 mile point) to north of Hallam Avenue (6.26 mile point). 
  • Dixie Highway (U.S. 25) from north of Marian Drive (8.13 mile point) to Orphanage Road (KY 371) (8.65 mile point). This portion of the project is now complete.
Milling and paving operations on U.S. 42 in Boone County have been completed. Milling on Dixie Highway from north of Marian Drive to Orphanage Road has been completed. We will provide further updates once milling and paving work has been scheduled on the other portions of the project.


Base failure repairs have not yet been scheduled on the other two portions of the project on Dixie Highway. 


The project also includes a roadway reconfiguration of Dixie Highway from Turfway Road to northeast of Commonwealth Avenue. KYTC will provide additional details related to this safety improvement at a later date.

The project is expected to be completed by Oct. 31, 2025.​

CAMPBELL AND KENTON COUNTIES
KY 1120 -- 0.96 mile point (Kenton County) - 0.22 mile point (Campbell County): A road reconfiguration will take place as early as Wednesday, Oct. 8 on 12th Street (MLK Jr. Blvd.) in Kenton County extending westerly over the 12th Street (Girl Scout) Bridge into Campbell County. ​​The reconfiguration will feature two lanes of vehicular traffic -- one in each direction, two dedicated one-way bicycle lanes, and a new stop condition on 12th Street in Covington at Wheeler Avenue. Eastbound traffic on 12th Street will use the left lane to continue straight onto the bridge. The right lane will become a 'right turn only' condition onto Wheeler Avenue.


CARROLL AND GALLATIN COUNTIES
​​​
  • I-71 – 52.77 – 57.36 mile points – A widening project aimed at reducing congestion and improving safety on I-71 in Carroll and Gallatin counties is in progress. The project will widen I-71 from its configuration of two lanes in each direction, to three lanes.

    On Monday, Oct. 6 and Tuesday, Oct. 7, crews will shift traffic back to the original configuration. ​

    This widening project includes a bridge replacement over KY 47. The current bridges will be replaced with a new, single span bridge matching the median widening throughout the project area.

    The speed limit in the work zone has been reduced to 55 MPH, and law enforcement will be on-site to ensure compliance. Please, drive carefully throughout the work zone. Weather permitting, the overall project is expected to be completed Nov. 1, 2026. Learn more about the project here.​


Boone County RR Title.png
  • North Bend Road (KY 237) – 9.21 – 10 mile point – A resurfacing project on North Bend Road from just south of Petersburg Road (KY 20) extending just north of Coral Drive is now complete.

  • Burlington Pike (KY 18) – 8.2 mile point – Burlington Pike has reopened just west of Green Acres Lane following a cross culvert installation project. Motorists should be advised that steel plates are in place to allow time for the concrete at the project site to cure. Appropriate signage is in place to warn motorists of the bump. Crews will return to the project within the next couple weeks. KYTC will provide further updates prior to crews returning to the site. 

    Once crews return, they'll focus on milling/paving near the project area. This work is expected to include a single lane closure with flaggers on both sides of the work zone.


  • I-71 – 69.8 – 77.4 mile points – A resurfacing project on I-71 from the Boone/Gallatin County line to the I-71 and I-75 interchange is in progress. 

    Milling/paving operations are now complete. The application of high friction surface treatment on the I-71 northbound to I-75 northbound ramp still remains. We will advise once this work is scheduled. 

    No lane closures will be permitted during Thanksgiving holiday weekend. The project has an expected completion date of Nov. 30, 2025. Read more about the project here.

  • Richardson Road (KY 842)  0.12 mile point  The bridge east of Dixie Highway (U.S. 25) on Richardson Road at the 0.12 mile point now has a weight limit reduction of three tons. While the bridge remains safe for vehicular traffic, a recent inspection found some deterioration. KYTC bridge engineering analysis shows the weight limit reduction is needed as a precaution, and to prevent further damage until the bridge can be repaired. KYTC is working with the railroad company to coordinate a repair plan. We will provide updates once the bridge repair plan has been scheduled. Prohibited vehicles can detour using Industrial Road (KY 1829) or Mt. Zion Road (KY 536).

  • Donaldson Highway (KY 236) 0.0 – 1.6 mile points – A widening and safety improvement project on KY 236 (Donaldson Highway) between KY 842 (Houston Road) and KY 3076 (Mineola Pike) is in progress. The project will widen the 2-mile stretch of road to five lanes with curb and gutter, including two through-lanes in each direction with a center turn lane. A sidewalk and multiuse path also will be added.​
    ​​
    The project has an overall completion date of October ​2025. You can find more information on this project here. ​

Bracken County RR Title.png

  • AA Highway (KY 9) – 0.0 – 5.39 mile point – A resurfacing project on a portion of the AA Highway beginning at the Mason/Bracken County line extending north to just south of KY 19 is in progress.

    Mainline paving is now complete. Shoulder paving operations are currently underway. A single lane closure will be in place during working hours of 7 a.m. to 7 p.m. with flaggers on-site to direct traffic around the work zone. 

    Motorists are advised to plan ahead and expect delays during working hours. Weather permitting, the project is expected to be completed by Nov. 15, 2025.

Campbell County RR Title.png

  • Persimmon Grove Pike (KY 1121) – 2.94 – 6.63 mile point – A resurfacing project on Persimmon Grove Pike from California Cross Roads extending northerly to Stevens Branch Road (KY 1996) is in progress.

    Weather permitting, milling operations will take place through Wednesday, Oct. 1 through Friday, Oct. 3. Crews are expected to return for paving operations beginning Monday, Oct. 6 through Wednesday, Oct. 8. 

    A single lane closures will be in place during daytime work hours of 8 a.m. and 6 p.m. with flaggers on-site to direct traffic. 

    Weather permitting, the project is expected to be completed by the end of October.

  • Pond Creek Road (KY 1936) – 6.78 – 7.77 – A resurfacing project on Pond Creek Road from Visalia Road extending northerly to Creektrace Road (KY 536) will begin on Monday, Oct. 6.
     
    Weather permitting, milling operations will take place on Monday, Oct. 6 with paving scheduled to follow on Thursday, Oct. 9.

    A single lane closures will be in place during daytime work hours of 8 a.m. and 6 p.m. with flaggers on-site to direct traffic. 

    Weather permitting, the project is expected to be completed by the end of October.

  • Combs-Hehl Bridge – 73.4 – 73.1 mile point – A T-1 steel repair project on the Combs-Hehl Bridge, which spans the Ohio River between Kentucky and Ohio, will begin on Sunday night, Sept. 28, at 8 p.m.

    This work follows a federally required inspection of older bridges built with “T-1” steel. During a 2023 inspection, 300 welds were tested, and 16 locations were identified for future repair. While not an immediate safety concern, these repairs will proactively address the findings and ensure the bridge remains safe for years to come.

    I-275 EASTBOUND
    Crews are currently on the eastbound portion of the bridge. 

    Lanes have been narrowed from three 12-foot lanes to two 10-foot lanes and one 11-foot lane. This setup will create room for barrier wall placement while minimizing impacts to traffic. Additional lane closures may be required for crane operations and steel plate installation. KYTC will issue updates when those closures are scheduled. Eastbound work is expected to take about 45 days to complete.

    I-275 WESTBOUND
    When eastbound repairs are finished, crews will shift to the westbound side using the same traffic plan. More details will be provided closer to the start of that phase. Westbound work is also expected to take about 45 days.

    ADDITIONAL REPAIRS
    In addition to the T-1 steel work, crews will also complete several stringer repairs. These repairs were added to the project to further enhance the long-term safety and durability of the structure.

    A queue warning system will be installed on both sides of the river to alert motorists of slowed or stopped traffic on or near the bridge. The speed limit will be reduced to 55 mph through the work zone for the duration of the project.

    Learn more about the project hereWeather permitting, the overall project has an expected completion date of February 2026.

  • AA Highway (KY 9) and KY 709 Intersection  A project to add two new turning lanes at the AA Highway (KY 9) and KY 709 intersection will begin on Monday, Sept. 22.

    -A right turn lane from AA Highway southbound to KY 709 westbound (mile point 12.3 to 12.1)
    -A right turn lane from KY 709 eastbound to AA Highway southbound (mile point 0.4 to 0.46)

    Traffic signals and roadway signage will also be updated to coincide with the new lanes.

    A single right lane closure on AA Highway southbound will be in place from 9 a.m. to 3 p.m.

    Additionally, a closure of KY 709 eastbound from east of the Seasons entrance (mile point 0.36) to the AA highway intersection will also be necessary for the installation of the new turning lane. When the closure is in place, traffic will be detoured via KY 709 to Alexandria Pike (U.S. 27) to AA Highway. We will provide an update once the closure is scheduled.

    Weather permitting, the project is expected to be completed by Nov. 1, 2025. 


  • KY 9 Exit On-Ramp to I-275 Eastbound 0.0  0.2 mile points Beginning Sunday, Oct. 5, KYTC Campbell County maintenance crews will perform drainage/ditching work near the on-ramp to I-275 eastbound. This work will require a full closure of the ramp from 8 p.m. to 5 a.m. The ramp will reopen daily by 5 a.m. Weather permitting, this project is expected to be completed Wednesday, Oct. 8 at 5 a.m.

Carroll County RR Title.png

  • Dividing Ridge Road (KY 2984) – 0.0 – 3.5 mile point – A resurfacing project on Dividing Ridge Road from KY 36 to KY 47 will begin on Monday, Sept. 29.

    A single lane closure will be in place during daytime working hours with flaggers on-site to direct traffic around the work zone.

    Weather permitting, the project is expected to be completed by the end of October.


  • I-71 – 38.8 – 53.4 mile points – A maintenance repair project is in progress on I-71 from the Trimble County line to the Gallatin County line.

    Crews have been hard at work addressing the roughest sections of pavement along this corridor. The most serious base failures have already been repaired, and contractors are now milling and resurfacing those problem spots to help reduce potholes and improve ride quality.

    Paving operations are now complete. Over the next couple of weeks, crews will wrap up final tasks such as permanent striping and inlaid pavement markers. This work will require lane closures and/or mobile operations as needed, Sunday through Friday from 8 p.m. to 8 a.m. All lanes will reopen at 8 a.m.

    ***

    This is a maintenance repair project, not a full resurfacing of all lanes. These operations will be limited to the mainline interstate. Shoulders and on/off ramps will not be included with this project.

    A reduced speed limit of 55 MPH will be enforced throughout the work zone, with law enforcement on-site to ensure compliance.

    No lane closures will be permitted during the Thanksgiving holiday weekend.

    The project began on Friday, Aug. 8, with completion expected by Nov. 15, 2025. Learn more about the project here.​

Gallatin County RR Title.png

NO SIGNIFICANT TRAFFIC IMPACTS/PROJECTS AT THIS TIME.​

Grant County RR Title.png
  • Jonesville Road (KY 36) – A slide repair project on two sections of Jonesville Road began on Wednesday, Sept. 3.

    Crews will perform slide repairs at the following locations:
    Mile point 0.81: located just east of Folsom Jonesville Road (KY 1132)
    Mile point 5.02: located near Fords Mill Road

    A 24/7 single lane closure will be in place, with temporary traffic signals installed at each end of the work zone to guide traffic.

    Weather permitting, the project is expected to be completed by the end of October.


  • Gardnersville Road (KY 491) – 5.42 – 8.36 mile point – A resurfacing project on Gardnersville Road from North Fork Road to the Grant/Pendleton County line is in progress. 

    Base failure and milling/paving operations are now complete. The installation of edgeline rumble strips is the last task for this project.

    Weather permitting, the project is expected to be completed by early October.


  • KY 22 – 10.68 – 11.55 mile point – A diamond grinding and roadway improvement project on KY 22 between Warsaw Road (KY 467) and U.S. 25 is scheduled to begin on Sunday, Aug. 24. 

    Work will be completed in phases and include diamond grinding and grooving of pavement, partial depth pavement repairs, sidewalk and curb work, guardrail replacement, and installation of permanent striping and pavement markers. A new radar detection system will also be added at signalized intersections within the project limits, replacing embedded traffic loops. 

    Overnight single lane closures will be in place from 8 p.m. to 7 a.m., with one lane in each direction maintained at all times. Flaggers will be present when work is occurring in intersections.

    Some work items may also occur during non-peak daytime hours. To minimize traffic impacts, any daytime closures will be limited to the western portion of the project. All work requiring lane closures on the eastern portion will take place overnight.

    No lane closures will be in place during the Thanksgiving holiday weekend.

    Weather permitting, the project is expected to be completed by Nov. 30, 2025.

    ​​
  • Elliston-Mt. Zion Road (KY 1942) – 1.76 mile point – A bridge replacement project on Elliston-Mt. Zion Road is in progress.

    The project involves removing the existing bridge deck and beams over Napoleon Branch Creek then setting new beams and constructing a new deck.

    To accommodate the work, the bridge was closed to traffic on Thursday, May 29. A signed detour will be in place to guide motorists around the closure.

    Once the new bridge is finished, the detour will be removed and the crossing will reopen to traffic. Additional work will continue throughout the project area following the reopening.

    Motorists are encouraged to follow posted signs and use caution in the area.

    The project is expected to be completed by October 2025.


Harrison County RR Title.png

NO SIGNIFICANT TRAFFIC IMPACTS/PROJECTS AT THIS TIME.​


Kenton County RR Title.png
  • VARIOUS ROUTES – The application of high friction surface on various routes in Kenton County will begin on Wednesday, Oct. 8.

    To minimize disruptions, work will take place during both daytime and nighttime hours but will avoid peak travel times. Motorists should expect a single lane closure with flaggers directing traffic as needed. Contractors will apply a high friction treatment to the roadway surface, improving pavement grip to help drivers maintain better control in both dry and wet conditions.

    List of dates and locations:

    Wednesday, Oct. 8 through Friday, Oct. 10:
    Three locations on Pride Parkway (KY 16) northbound in Taylor Mill:
    Between the Interstate 275 interchange and Mason Road (mile points 13.20 – 13.41)
    On the S-Curve just north of Mason Road (mile points 13.49 – 13.71)
    Near the Grand Avenue intersection (mile points 13.92 – 13.97)

    Monday, Oct. 13 and Tuesday, Oct. 14:
    Interstate 75 southbound off ramp to Donaldson Highway (KY 236) (mile points 0.27 – 0.33)

    Tuesday, Oct. 21 and Wednesday, Oct. 22:
    Kenton Lands Road (KY 2373) beginning near the railroad overpass to just north of the Silverlake Entrance in Erlanger (mile points 0.30 – 0.60)

    Thursday, Oct. 23 and Friday, Oct. 24:
    Taylor Mill Road (KY 16) near Stablewatch Drive in Independence (mile points 7.87 – 8.01)

    Monday, Oct. 27 and Tuesday, Oct. 28:
    Visalia Road (KY 536) on the curve near Staffordsburg Road (mile points 7.42 – 7.60)

    This work is weather permitting and dates are tentative. We will update this list if any schedule changes occur.

  • Madison Pike (KY 17) – 19.4 – 19.6 mile point – A slide repair project on Madison Pike from north of Lakeview Drive to Kyles Lane is in progress.

    This work will require a 24/7 northbound single right lane closure. Crews will be performing work to stabilize a portion of road that has slipped. Weather permitting, this project is expected to be completed by Monday, Oct. 13. 

  • I-71/75 Northbound 1​90 - 191.7 mile points There will be a series of overnight rolling roadblocks on I-71/75 northbound beginning Wednesday, Oct. 1. ​

    These roadblocks will take place nightly in 15 minute intervals between 11 p.m. and 5 a.m. as crews survey Brent Spence Bridge deck conditions. The roadblocks will begin south of the Covington 12th Street (KY 1120) exit to the Kentucky/Ohio state line.

    Weather permitting, this work is expected to be completed by Friday, Oct. 3 at 5 a.m.

  • I-75/I-275 Interchange – A routine bridge inspection of the I-75/I-275 interchange is now complete.


  • Dixie Highway/Pike Street (U.S. 25) ​ 10.82  12.64 mile points ​ A resurfacing project on Dixie Highway/Pike Street will begin on Sunday, Oct. 5. Crews will work from north of Kyles Lane (KY 1072) to Lewis Street in Covington. This work will take place between 6 p.m. and 6 a.m. and will include single lane closures throughout the project area. Weather permitting, this project is expected to be completed Nov. 24, 2025.


  • Bristow/Shaw/Independence Roads (KY 536)  3.1 3.37 mile points A maintenance project will begin on Tuesday, Sept. 16. Crews will replace a storm drainage system, relocate pipes and perform drainage/ditching operations to improve safety. This work will require a lane closure on KY 536 from east of Greenbrook Drive to between Bristow and Shaw Roads on Independence Road. Temporary traffic signals will be installed on both sides of the work zone. These will remain in place 24/7 throughout the entirety of the project.

    Additionally, a full road closure of Independence Road (KY 2045) at the intersection with Bristow Road (0.0 mile point) is needed to allow our crews a safe area to work.

    Weather permitting, this project is expected to be completed Tuesday, Oct. 7. KYTC will provide updates if additional days of work are needed for the project.

  • ​Madison Pike (KY 17) ​ 16.14 ​ 17 mile points A hillside stabilization project on Madison Pike between Pioneer Park and Old Madison Pike is now complete. 

  • Whites Road (KY 1930) – 0.0 – 1.19 mile point – A resurfacing project on Whites Road from Decoursey Pike (KY 177) extending north to Locust Pike (1930) is in progress.

    Base failures are now complete. Milling and paving operations are expected to begin on Saturday, Oct. 4. Motorists should expect a single lane closure between 7 a.m. and 7 p.m. Flaggers will be on-site to direct traffic through the work zone.

    Weather permitting, the project is expected to be completed by end of October.


  • Old Hands Pike/Waymans Branch Road (KY 3716) 0.0  0.05 mile points  A Sanitary District 1 (SD1) sewer project will take place beginning Wednesday, Aug. 13. This project will include a two-month closure of Old Hands Pike/Waymans Branch Road from Madison Pike (KY 17) to Misty Lane. The closure will be in place 24/7.

    Access to nearby businesses will be maintained using a signed detour: KY 17 to Hands Pike (KY 1501), to Madison Pike (KY 3035), and back on to Old Hands Pike/Waymans Branch Road.

    This is a permits project approved by KYTC for SD1. Weather permitting, the project is expected to be completed Oct. 13, 2025.

  • Access to Royal Drive at Buttermilk Pike (KY 371) – 2.65 mile point – Beginning Friday, Dec. 13, access to Royal Drive at Buttermilk Pike will be closed to motorists until further notice for infrastructure construction and repair.

    A portion of Royal Drive will be restricted to construction traffic only, and detour signs will be posted to guide motorists. Local traffic should plan to use alternate routes.

    For further information about this project, please contact the City of Fort Mitchell​.

  • Bristow Road (KY 1303) – 0.0 – 0.92 mile point – A widening and safety improvement project on Bristow Road began in September 2024. Crews will be working on Bristow Road from the KY 536/KY 1303 intersection to the Beechgrove Elementary School.

    The project includes the following improvements:
    -Widening throughout the project area from two lanes of vehicular traffic, to four lanes to reduce congestion and improve traffic efficiency
    -A multi-use path will be built on both sides of Bristow Road to improve bicycle/pedestrian connectivity
    -Curb/gutter improvements along with storm sewer and drainage work. This work will greatly improve drainage in an area that has been prone to flooding

    Additionally, the project will eventually tie into a new roundabout at the KY 536 and KY 1303 intersection improving traffic flow, reducing congestion and increasing safety.

    This work may involve several traffic impacts for equipment moving in and out of the work zone. The project will require traffic switches, and other new traffic patterns. Prior to these occurring, KYTC will send out an updated press release, as well as a post on social media to inform the public. Message boards will also be in place to warn motorists of any upcoming traffic pattern changes.

    The project is expected to be completed Fall 2025. For more information on this project, visit our KY 536 website here​.

  • Ernstbridge Road (CR 1021)  A bridge replacement project on Ernstbridge Road (CR 1021) is in progress. The existing bridge will remain open to traffic throughout construction, minimizing disruptions for motorists. However, travelers should expect occasional minor delays due to work in the area. The overall project has an expected completion date of Nov. 1, 2025.​

  • Mt. Zion Road/Bristow Road (KY 536) ​ 0.96 ​ 2.5 mile points ​ ​A widening and safety improvement project on KY 536 is in progress. Crews will be working on KY 536 from west of the KY 1303 intersection, to west of Williamswoods Drive.

    The project includes the following improvements:
    ​-Widening throughout the project area from two lanes of vehicular traffic, to four lanes, to reduce congestion and improve traffic efficiency
    -A multi-use path will be built on both sides of KY 536 to improve bicycle/pedestrian connectivity
    -Curb/gutter improvements along with storm sewer and drainage work

    Additionally, two roundabouts will be built to improve traffic flow, reduce congestion and increase safety. These roundabouts will be located at the following intersections:
    -KY 536 and KY 1303
    -KY 536 and Hogrefe Road

    This work may involve several traffic impacts for equipment moving in and out of the work zone.

    The project will require traffic switches, and other new traffic patterns. Prior to these occurring, KYTC will send out an updated press release, as well as a post on social media to inform the public. Message boards will also be in place to warn motorists of any upcoming traffic ​pattern changes.

    The project is expected to be completed Spring 2027. Learn more about this project here.

Owen County RR Title.png

  • U.S. 127 – 22.96 – 28.48 mile point – A preventive maintenance project on a portion of U.S. 127 beginning at KY 35 extending north to the bridge over Eagle Creek is now underway.

    On Wednesday, Sept. 17, contractors completed chip seal work ahead of the thinlay application. After a chip seal treatment, drivers should expect some loose aggregate and a slight increase in roadway noise. A 25 mph speed limit is in place.​

    Beginning Monday, Sept. 22, crews will return to the site to apply the thinlay to the pavement. During daytime working hours, a single lane closure will be in place with flaggers on-site to direct traffic through the work zone.

    Weather permitting, the project is expected to be completed by Sept. 30, 2025.

Pendleton County RR Title.png

  • Center Ridge Road (KY 3184) – 0.0 – 4.27 mile points  A resurfacing project on Center Ridge Road from KY 467 to KY 491 will begin on Monday, Sept. 29.
    ​​
    A single lane closure will be in place during the daytime working hours of 7 a.m. and 6 p.m. Flaggers will be on-site to guide traffic safely through the work zone.

    Weather permitting, the project is expected to be completed by Nov. 30, 2025.

Robertson County RR Title.png
NO SIGNIFICANT TRAFFIC IMPACTS/PROJECTS AT THIS TIME.











Click_Here_to_Subscribe_to_our_news_and_traffic_updates_so_you_never_miss_a_update
Go_Kentucky_Applcation_for_planning_your_travel_around_recent_traffic_and_construction_updates
Buttons-Trimarc.jpg
Ohio_Go_Know_Before_You_Go_Traffic_and_construction_project_impacts_on_your_commute
BSBCP BUTTON - RESIZED.png
KY 536 SITE - RESIZED.png
DNKYP BUTTON - RESIZED.png
D6 FACEBOOK Button.png 

​​
D6 TWITTER_X Button.png








​​This page is maintained by Jake.Ryle@ky.gov and James.Heatherly@ky.gov​, who may be contacted to make corrections or changes.

Follow Us