Jefferson County: KY 1865 (New Cut Road)/Taylor Boulevard Safety Study - 05-80352

​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​KY 1865 New Cut Road.PNG​​​​​​​



Purpose
This project strives to implement safety improvements for all users along the KY 1865/New Cut Road corridor.

The project will reallocate space within the corridor to discourage speeding, accommodate all users, and facilitate connectivity while creating a safer, more comfortable, and pleasant environment. Known users along the corridor include motor vehicles, transit vehicles/buses, pedestrians/walkers/runners/transit users, and bicyclists. The context along the corridor is mixed and transitions along its length, including commercial areas, single-family residential neighborhoods, multifamily residential, Iroquois Park, an​d several schools and churches.
 ​
​Project Scope
Safety improvements on KY 1865 (New Cut Road)/Taylor Boulevard from MP 0.5 (just south of Old New Cut Road) to MP 5.766 (just north of the I-264 ramp).
​Type of Project
​Safety enhancements.
​Links
*Some files are large and may take a few minutes to load.
​Project Timeline

As of Winter 2025/2026 (SUBJECT TO CHANGE*):
​Final Report 
​​KY 1865 (Taylor Blvd New Cut Road) Safety Study_August 2025.pdf
Appendices for Final Report:

Future Phases 
Funding years for next phases within the 2024 Enacted Highway Plan:
  • Design - 2027
  • Right-of-Way - 2027
  • Utilities - 2028
  • Construction - 2029
 *The above project milestone dates are subject to change due to changes in funding availability within the next Enacted Highway Plan.
​Project Manager

Project Manager:
Mike Vaughn, PE

Mike.Vaughn@ky.gov

502.782.4923


This page is maintained by KYTC District 5 Staff, who may be contacted to make corrections or changes.

​Page Last Updated: 03-02-2026