Project Timeline
|
As of Fall 2024 (SUBJECT TO CHANGE*): - Since the 2003 Public Information Meeting, the project has been delayed (funding appropriation). The project received a lower SHIFT ranking for the district; however, a right-turn lane was constructed for southbound Fegenbush Lane onto Beulah Church Rd.
- KYTC has acquired all necessary right-of-way, including the control of access rights when applicable, including legal and physical possession (As of August 2022)
- According to the utility companies' estimates, utility relocations may begin in 2025. The utility companies anticipate completing the full relocations will take at least two years.
- The construction letting date will be determined once utility relocations have progressed.*
*The above project milestone dates are subject to change due to changes in funding availability within the next Enacted Highway Plan.
|
Elected Official Meeting / Public Meetings
| An elected official meeting was held in September 2001, where preliminary engineering studies were used to develop project alternatives. The first public meeting was held in May 2002 to discuss numerous issues, including the project's scope, existing conditions, design criteria, construction alternatives, historical and ecological considerations, and other relevant project information. At this initial meeting, nine alternatives (labeled A-I) were proposed (developed from the elected official meeting mentioned above). This meeting used an "open format" style, where the public could acquaint themselves with the various exhibits, preliminary design plans, and other pertinent information. Citizens were encouraged to provide feedback on the alternatives via a questionnaire. Questionnaire submissions were accepted until 15 days after the meeting date. A second public meeting was held in November 2003. After receiving public input at the initial public meeting, the number of alternates under consideration was reduced from nine to three: Alternate A, H, and I. Based on the public input, Alternate "I" was moved forward as the recommended alternative, and the construction and right-of-way acquisition plans were developed. |