Purpose
The purpose of the Preston Transportation Plan study is to determine needs and evaluate concepts to improve safety, reduce congestion, and improv​e multi-modal transportation options along KY-61 from Commerce Crossings Drive to Briden Avenue, or just south of I-265 to just north of I-264. 
​Project Scope
This study includes a comprehensive analysis of existing conditions along the corridor, which will be used to develop practical solutions and improvement concepts to enhance roadway safety, address congestion issues, and improve traffic flow. 

The study will focus on short-term and long-term improvements that KYTC and Louisville Metro can use for further project development and implementation.
​Type of Project
​​​​Planning Study
​Links

​Stor​y Map

​Public Input
An initial public meeting was held on May 21, 2024, to update the community on the Preston Transportation Plan and to gather feedback regarding the study.  

A second public meeting was held on Oct. 24, 2024, to share improvement concepts that reflect the input from the initial phase of the study.
​Project Timeline
  • May 2024: 
    • ​​Public meeting 
  • ​October 2024: 
    Present improvement concepts at a second public meeting and collect feedback. 

  • December 2024:
    Draft planning study report 

  • May 2025:
    The final planning study is expected to be completed.
​Final Report and PublishedThe final planning study is available here: Final Report
​Project Manager
Tom Hall
Email: Tom.Hall@ky.gov
Phone: 502.764.0826​ ​


This page is maintained by KYTC District 5 Staff, who may be contacted to make corrections or changes.

​Page Last Updated: 10-17-25​


Follow Us