I-65 Bridges Planning Study​

Jefferson

​The purpose of the study is to assess conditions and prioritize and develop conceptual strategies for repair or replacement of all bridges along Interstate 65 between the Watterson Expressway (I-264) and the rebuilt Kennedy Interchange in Louisville, KY, 28 bridges in all.

  
  
There are no items to show in this view of the "Planning Studies and Reports" document library.
  
  
I-65 Bridges Planning Study - Executive Summary.pdfI-65 Bridges Planning Study - Executive Summary
I-65 Bridges Planning Study - Final Report.pdfI-65 Bridges Planning Study - Final Report
  
  
There are no items to show in this view of the "Planning Studies and Reports" document library.
  
  
There are no items to show in this view of the "Planning Studies and Reports" document library.
  
  
I-65 Bridges Planning Study - Appendix A - Environmental Overview.pdfI-65 Bridges Planning Study - Appendix A - Environmental Overview
I-65 Bridges Planning Study - Appendix B - Highway Capacity Software Output HCS7.pdfI-65 Bridges Planning Study - Appendix B - Highway Capacity Software Output HCS7
I-65 Bridges Planning Study - Appendix C - Under-Bridge Parking Agreements.pdfI-65 Bridges Planning Study - Appendix C - Under-Bridge Parking Agreements
I-65 Bridges Planning Study - Appendix D - Sample Communication Plan.pdfI-65 Bridges Planning Study - Appendix D - Sample Communication Plan
I-65 Bridges Planning Study - Appendix E - Bridge Element Condition State Quantities.pdfI-65 Bridges Planning Study - Appendix E - Bridge Element Condition State Quantities
I-65 Bridges Planning Study - Appendix F - Summary of Repair Quantities.pdfI-65 Bridges Planning Study - Appendix F - Summary of Repair Quantities
I-65 Bridges Planning Study - Appendix G - Similar Projects.pdfI-65 Bridges Planning Study - Appendix G - Similar Projects
I-65 Bridges Planning Study - Appendix H - Sample Special Notes.pdfI-65 Bridges Planning Study - Appendix H - Sample Special Notes
I-65 Bridges Planning Study - Appendix I - Utilities and Constraints.pdfI-65 Bridges Planning Study - Appendix I - Utilities and Constraints
I-65 Bridges Planning Study - Appendix J - Individual Bridge Repair Cost Estimates.pdfI-65 Bridges Planning Study - Appendix J - Individual Bridge Repair Cost Estimates
I-65 Bridges Planning Study - Appendix K - Cathodic Protection Articles.pdfI-65 Bridges Planning Study - Appendix K - Cathodic Protection Articles
I-65 Bridges Planning Study - Appendix L - Minutes from Project Team Meetings.pdfI-65 Bridges Planning Study - Appendix L - Minutes from Project Team Meetings
I-65 Bridges Planning Study - Appendix M - Bridge 183N and 179N Replacement Cost.pdfI-65 Bridges Planning Study - Appendix M - Bridge 183N and 179N Replacement Cost
  
  