Questions and Answers

​​​​​​​​​​​​​​​​​​​​​​​

  
  
County
  
Question
Answer
  
12-1042200Barren, Hart
Is minimum depth for piling 15.0 LF below the bottom of the pile cap?
KYTC will accept minimum of 10 foot pile below the bottom of pile cap.
10/3/2012 2:37 PM
12-1353113Daviess
What wall thickness is required for the force main casing pipe?
Steel casing for force main jack & bore installation shall be 0.375-inch wall thickness in accord with Chapter 5 of the Public Improvements Specifications (www.iOMPC.org)
10/4/2012 3:04 PM
12-1353113Daviess
Are joint restrainers required for the force main bend fittings?
Ductile iron bend fittings along the force main relocation section shall include joint restrainers (MegaLug or equal) in accord with RWRA force main design criteria.
10/4/2012 3:04 PM
12-1042200Barren, Hart
Is the intent of Pay item 02998 Masonry Coating 28,122.00 SQYD’s for coating Concrete Median Barriers?
Yes.
10/4/2012 1:38 PM
12-1042200Barren, Hart
Is any rock expected to be encountered if pre-drilling is required?
Yes.
10/3/2012 2:37 PM
12-1343108Wolfe
Item 0210 is for R/W Marker Rural Type 1.  Should this item be changed to R/W Monument Type 1?
Yes.  An addendum will be posted to the website.
10/8/2012 7:55 AM
12-1042200Barren, Hart
Where is bid item no. 1600, pay item 08904 (Crash Cushion Type VI Class C) to be installed?
Please see plan sheet R51.
10/4/2012 1:40 PM
12-2454307Carroll
Can we get clarification on what the intent of standard integral curb quantity is setup for?
The standard integral curb will be installed in the locations with new concrete pavement.
10/4/2012 10:12 AM
12-1349111Boone
The specification lists the names of approved systems but has left out the Sine Wall System that has been approved by KYTC.  Can you please add Sine Wall System to the specifications?
Sine Wall System is now an approved wall system and is acceptable for this project.
10/8/2012 7:56 AM
12-1343108Wolfe
Are plans of the existing bridge available to be posted on the website?
Yes, they are in the project related information section on the website.
10/8/2012 3:30 PM
12-1352302Muhlenberg
Would the Department consider a 1.00 asphalt base instead of the 0.75 asphalt base?
Yes, the successful bidder may substitute 1.00 asphalt base for the planned 0.75 asphalt base as long as it results in no additional cost to the Department.
10/8/2012 3:31 PM
12-1043309Kenton
Is there a Corps of Engineers permit or Water Quality Certification Authorization applicable to this project?
No.  The note on plan sheet R2T will be removed and additional instructions will be added.  An addendum will be posted to the website.
10/8/2012 7:56 AM
12-2449403Todd
Should a pay item for Portable Changeable Message Sign be added?
Please see the Changeable Message Signs note on page 20 in the proposal.
10/9/2012 8:02 AM
12-1350103Hopkins
Sheet R2L shows the surface as CL3 0.50B while in other places it is listed as CL3 0.50A?
The reference to surface as CL3 0.50B is an error.  The approved pavement design is CL3 0.50A.
10/8/2012 3:31 PM
12-1343108Wolfe
Please verify the opening required for the temporary diversion crossing on plan sheet  R7
The required hydraulic opening for the temporary diversion crossing is 411 sq. ft.
10/10/2012 11:01 AM
12-1358311Fleming
The base of the RDZ line has been plotted well below the elevation at which the first shale/limestone is encountered.  What method was used in determining when the shale/limestone becomes too hard to dig?  Are the rock cores available for viewing?  If so, please provide a contact name and phone number to set up an appointment to view them.
The base of the RDZ is determined by what is considered to be ripable with a D-9 Dozer. This is based on visual inspection of the rock core and any  SDI values. This is an estimation only.  The rock cores may be viewed by scheduling with Christian Wallover or Mike Blevins at telephone number (502) 564-2374.
10/12/2012 1:55 PM
12-2453303Woodford
Will the two existing catch basins to be reconstructed be rebuilt to a KYTC standard?  If so, which KYTC standard structure?  If otherwise, can a structure detail be provided?  Will the existing structures’ castings be re-used, or will new castings have to be purchased? 
The structure does not have to be re-built to a KYTC Standard.  The reconstructed structure should be constructed to field conditions and to accept the existing grate.
10/10/2012 11:03 AM
12-1354206Various
For the piers , it states to pre-drill a 24” diameter hole for a 30” dia. pipe piling. Could you please verify that this is correct?
The allowable range of pre-drilling diameters for the 30-inch pipe piles is 20 to 24 inches as stated in Note 4 of the “Pre-Probing for Piles” notes on Sheet S13 of the lagoon bridge plans.  These diameters are smaller than the pile diameter in order to minimize the loss of resistance due to the pre-drilling process.
10/10/2012 11:03 AM
12-2453303Woodford
On page 29 of 82 in the proposal, under “Construction Phasing,” the proposal states, “KYTC will entertain proposed alternate traffic schemes and phasing. Submit proposed alternate schemes and phasing to the Section Engineer for review and approval.”  Can a contractor submit an alternative traffic scheme and/or phasing to KYTC prior to the letting for review and approval?  Will KYTC consider allowing for more than three weekends on this project?
The Cabinet will not entertain longer than 3 weekends.  Changes to the traffic control plan will be reviewed after the project has been awarded.
10/10/2012 11:04 AM
12-1354206Various
Is it required to pre-drill for test piles L-1 and L-2?
In general, the need to pre-drill piles will be determined as described in the “Pre-Probing for Piles” notes on Sheet S13 of the lagoon bridge plans.  Quantities for pre-probing for test piles L-1 and L-2 have been set up and the need to pre-drill these test piles will be evaluated after pre-probing has been performed at those locations.
10/10/2012 11:02 AM
12-2453303Woodford
Will KYTC allow the use of integral curb in an effort to expedite the construction of this project during the weekend closures?
Yes.  An Addendum will be issued to change the curb bid item to integral curb.
10/10/2012 11:04 AM
12-1354206Various
Will a vibratory hammer be allowed to be used to  install and remove temporary casing, if required?
Vibratory hammers are acceptable to install and remove temporary casing when used as identified for spoil containment for Deep Soil Mixing in the waters of Kentucky Lake.  We are not aware of another situation where temporary casing would be required.  In order to answer this question we would need additional information such as the reason for installing the temporary casing, the specific location, and the proposed diameter and depth of the temporary casing.  The use of a vibratory hammer will be acceptable to install permanent casing at End Bent 2 of the Lagoon bridge.
10/10/2012 11:01 AM
12-1042200Barren
The cross sections show a pre-split wall at both bridge locations.  The bridge plans show a 2 : 1 slope at both bridge locations.  Which plan will be used for construction?
The Bridge plans with 2:1 crushed aggregate slope protection will be used.
10/11/2012 11:51 AM
12-1350103Hopkins
Does the rideability apply to only the mainline or to the ramps also?
Rideability applies to mainline only.
10/8/2012 3:32 PM
12-1358311Fleming
The first sheet indicates there are no plans for the project.  Is this correct?
No, that it incorrect.  There are plans available in the Electronic Planroom.
10/8/2012 3:34 PM
12-1350103Hopkins
Plan sheets R49 and R50 have a statement on signs stating “payment included with traffic control plans”, please elaborate.
The intent of the note was to convey the message that signing quantities were contained in the Traffic Plans which were prepared by another consultant.  The appropriate signing quantities are on Sheet T001 and the note should be disregarded.
10/8/2012 3:32 PM
12-1358311Fleming
The quantities of concrete and steel for culvert have been combined with the quantities from the drainage summary in the bid item quantities.  Could this be separated as they normally are?
Yes, an addendum will be posted to the website.
10/8/2012 3:34 PM
12-1043309Kenton
Diversion 3 has a substantial amount of embankment.  Since this is a waste job, would it be permissible to leave the diversion 3 embankment in place or will we be required to remove this material?
Most of Diversion #3 is to be constructed on Temporary Easements.  These property owners were negotiated with, and accepted compensation, based on their understanding that this diversion would be removed. The material for diversion #3 shall be removed when no longer needed unless the contractor gets the affected property owners’ written approval and submits to the Department.
10/8/2012 3:33 PM
12-1354206Marshall
Will the Department allow construction of granular embankment prior to deep wet soil mixing at the three stations ranges referred to on Sheet R40, Note 10? 
No.  Due to constructability considerations, the deep wet soil mixing needs to be performed prior to installing geotextile fabric and constructing the granular embankment.
10/12/2012 1:56 PM
12-1350103Hopkins
Is there concrete pavement under the asphalt on the existing ramps? 
It appears that only 100’ of the loop ramps and approximately 300’ on either side of the former toll booths are concrete but the Department cannot guarantee this.  Bidders should make their own determinations as per Standard Specification 102.06.
10/12/2012 1:58 PM
12-1358311Fleming
On proposal page 33, it states two (2) impoundments to be constructed, Lt. station 154 +00 calls for a Detention pond, Lt. station 183+45 calls for a Dissipator Basin.  Plan sheet R29D of the roadway plans only shows plan drawings for a Dissipator basin. Are there any design plans for detention pond?
Both the energy dissipater and the detention pond designs are delineated on Sheet R29D.  The detention pond detail is distinct and different from the dissipater basin on the sheet.
10/12/2012 1:59 PM
12-1354206Marshall
The required pile capacities to be developed during driving for the artificially plugged pipe piles (48 to 96 inch diameter) appear to require hammers so large as to be either impractical or commercially unavailable.   Did the Department perform a WEAP analysis for the full range of capacities (6,100 to 17,500) kips required for these piles and if so, what were the anticipated rated hammer energies.  It is understood that hammer selection is a contractor responsibility that is subject to Department approval but it would be informative if the Department would provide minimum hammer energy or anticipated hammer energies for this project.
Wave equation analyses performed for the 48- to 96-inch diameter pipe piles are included in Appendix H of the project geotechnical report which can be downloaded from “Project Related Information” for the current letting.  Appendix H is in the first linked report on the list and begins on page 2303 of the pdf document.
10/12/2012 1:55 PM
12-1350103Hopkins
There is a Bid Item for Temporary Concrete Barrier Wall TY. 9T (Line No. 0660).  However, the traffic control plans do not show where this TY. 9T wall is to be used at.  Can the Department show where this TY. 9T wall is to be used at?
That was inadvertently added to the bid items.  An addendum to remove it will be posted to the website.
10/12/2012 2:44 PM
12-1349111Boone
Is there a detail depicting the difference between Silt Trap Type A (1) and Silt Trap Type A (2)?
Please see Standard Drawing RDX-220-04.
10/12/2012 1:59 PM
12-1358311Fleming
The Sinkhole located at station 144+80, per the Geotechnical Note (#11) has been a possible junkyard/landfill, Roadway Plan sheet R2C states that the removal per Geotechnical Note # 11 for this sinkhole will be incidental to Clearing and Grubbing. Does the Department have any information as to the kind of material that is located within this sinkhole., I.E. Hazardous, toxic, etc.. that would/could require special handling and/or require the material to be hauled to an approved landfill for disposal or requiring personnel certify to remove and dispose of the material?
No additional information is available on the nature of the material at this location.  For bidding purposes, the contractor should draw their own conclusions about the degree of special handling that will be required.
10/12/2012 2:00 PM
12-1343108Wolfe
The open area for drainage through the diversion on the above subject project is pretty sizable (411 SF), which will likely require the use of a temporary bridge.  Would KYTC entertain the use of a KYTC Bailey bridge (assuming a suitable structure is available for the project)? 
The Department will not approve proposals for the temporary structure at this time.  Once the project is awarded, the Department will entertain any proposals the successful bidder may have
10/12/2012 1:57 PM
12-1043309Kenton
The bid items list the diversions as Diversions, #1, #2 and #3.  The traffic control plans show diversions as #3 and #4 with one at Lakewood Drive (not numbered). For bidding purposes, can the Department provide clarification on which bid item goes with which Diversion?
Yes, an addendum to revise the supplemental description in the bid items will be posted to the website.
10/12/2012 1:59 PM
12-1044300Adair
This bridge will be widened and Rail System Type III will be installed.  Should there be 4 EA. Guardrail Connector to Bridge End Type A added to the bid items?
Yes, an addendum will be posted to the website.
10/12/2012 2:45 PM
12-1044300Adair
On sheet 14 of the proposal which details Typical Sections, note 1 says:  “Contrary to standard drawings and standard specifications , 9’0” guard rail posts will be required for all guard rail.  With cost included in bid item for W-Beam Guard Rail”.  Historically, 9’0” guard rail posts are paid under Item 02399-Extra Length Guard Rail Post.  What is the reason for making this incidental to the guard rail? 
This was done because 9’ posts were the only length of post to be used on the project.  This is an attempt to minimize confusion during construction and make it easier on construction personnel.
10/12/2012 2:00 PM
12-1350103Hopkins
There is 338 L.F. of 14C2 Concrete Wall (separate segments) (Line No. 0250).  The Cross Sections (see sheet X98) shows only one segment with an embankment next to it.  Is there another segment?  Can the Department explain what they are wanting with this wall?
The Median Barrier TY 14C2 is shown on the Typical Section Sheet R02c and a construction note for this wall is shown on Sheet R5.  It also shows on the cross section sheets X94-X100.  It is denoted as separate segments because the back face is vertical.  Although separate segments are usually used in the median with earth between them, this wall is on the outside with earth behind it.
10/12/2012 2:44 PM
12-1350103Hopkins
Please elaborate about the “scarifying pavement bid item”.   The bid item (#0540) is “scarifying pavement” but the note on page R40 talks of removing pavement.
The bid item will be changed to Remove Pavement.  An addendum will be posted to the website.
10/12/2012 1:58 PM
12-4032205Various
Are any of the CLRS, ELRS or SRS rumble strips being installed on concrete surfaces at any of the locations listed?
Although it is possible that a small quantity of locations may be in concrete, the Department does not believe there are.  However, it is up to the bidder to verify field conditions.  It is expected that rumbles be installed regardless of the surface material type and that no adjustments will be made for locations based on the type of material that the rumbles are to be milled.
10/16/2012 10:08 AM
12-1361312Bath
The Cabinet indicates (2) permanent Type VI C TL-3 (Line 0720).  I do not see any posted Project Plan Sets on KYTC’s website, so could the design consultant meant to have utilized the pay item code for (2) Type VIB-T TL-3 temporary crash cushions?  Per KYTC Engineering the Type VIC-T pay item is inactive as of October 19th’s letting. 
Yes, the bid item should be Type VI Class BT TL3 Crash Cushion.  An addendum will be posted to the website.
10/16/2012 9:42 AM
12-1050316Rowan
Should the Type VIC permanent pay item be instead a temporary crash cushion pay item Type VIB-T?
Yes, the bid item should be Type VI Class BT TL3 Crash Cushion.  An addendum will be posted to the website.
10/16/2012 9:44 AM
12-4032205Various
Are the rumble strip millings to be swept to the berm of the road or picked up from the surface, loaded and hauled to disposal sites? Answers to questions on past 2012 rumble strip district bids have indicated that the material must be picked up and removed from the project. Please specify which method will be approved by the engineer on this project.
The material shall be swept up off of the roadway surface, loaded, and hauled to an offsite disposal area.
10/16/2012 10:08 AM
12-2444304Butler
The proposal states that one way traffic must be maintained during construction, with a clear lane width of 9 feet, and passage up to 16 feet. Some of the culvert replacements are 9 feet to 15 feet deep, producing top of trench widths over 15 feet wide with requirement of flowable fill backfill.  It will be impossible to maintain 1 way traffic under these conditions. Will the Department consider that road closures / detours be allowed for these deep culvert replacements?
Road Closures may be allowed provided that a temporary detour is established that is reasonable in length and may be contingent on the usage of county roads as part of the temporary detour.  Usage of county roads as part of the temporary detour will require consent from local county officials and this consent will be the responsibility of the contractor.  A minimum of one week notification of the road closure will also be required and the roadway must be reopened to traffic in the same day.  Any required detour signs used will not remain in place for more than three days and therefore will not be paid for under the sign bid item.
10/16/2012 9:46 AM
12-4031204Various
Are the rumble strip millings to be swept to the berm of the road or picked up from the surface, loaded and hauled to disposal sites? Answers to questions on past 2012 rumble strip district bids have indicated that the material must be picked up and removed from the project. Please specify which method will be approved by the engineer on this project.
The material shall be swept up off of the roadway surface, loaded, and hauled to an offsite disposal area.
10/16/2012 10:08 AM
12-1361312Bath
Can KYTC provide the locations and lengths of the type 1 water gates?
Water Gate locations were derived from RCBC locations on existing plans.  The Engineer will determine the need for installation or replacement.  The Contractor shall determine lengths based on field observations.
10/16/2012 1:26 PM
12-1361312Bath
Will the contractor be allowed to clear “as needed” any areas where the “remove and replace WW fence type 1” is intended.
Refer to note 18 under Notes Applicable on page 52 of 169.
10/16/2012 1:26 PM
12-1353113Daviess
What shall the bid items for active and dead line plugs, caps, concrete seals include?
All active and dead line plugs, caps, concrete seals shall be incidental to the Bid Items for line tie-in and waterline installations.  No other compensation will be paid for said caps, plugs and/or concrete seals as required by the utility Project Engineer.
10/16/2012 10:43 AM
12-1353113Daviess
Please clarify the method of tie-in to existing water mains (of respective sizes) and termination of other existing lines (ex.:  existing valved line/future stub in the vicinity of P.C. Sta. 33+53.82/P.T. Sta. 33+53.82)?
A line cap or plug shall be installed on the “live” end of existing line cuts of any line stub/termination not otherwise connected, and the “dead” end of any line cut for a tie-in shall thoroughly sealed/plugged with concrete to prevent future sink hole/settlement issues.
10/16/2012 10:43 AM
12-2453303Woodford
What is the depth of the existing concrete pavement in this intersection?  We believe there is an 1 1/2 of asphalt overlaying the existing concrete. 
The archived as-built plans show the existing concrete pavement to be 9 inches.  However, bidders should make their own assumptions.
10/16/2012 2:16 PM
12-1361312Bath
Will a temporary fencing item be added in case livestock should be encountered on these 2 projects?
Refer to note 18  under Notes Applicable on page 52 of 169.
10/16/2012 1:26 PM
12-4031204Various
Are any of the CLRS, ELRS or SRS rumble strips being installed on concrete surfaces at any of the locations listed?
Although it is possible that a small quantity of locations may be in concrete, the Department does not believe there are.  However, it is up to the bidder to verify field conditions.  It is expected that rumbles be installed regardless of the surface material type and that no adjustments will be made for locations based on the type of material that the rumbles are to be milled.
10/16/2012 10:08 AM
12-1035314Larue
If a borrow area is used  will the contractor be required to get this Nationwide Permit#14? 
If the work to collect material from a borrow area disturbs a Water of the US or if any other work which is not listed in the NOTICE is completed then a permit may be required.
10/16/2012 2:15 PM
12-1050316Rowan
Can KYTC provide the locations and lengths of the type 1 water gates?
Water Gate locations were derived from RCBC locations on existing plans.  The Engineer will determine the need for installation or replacement.  The Contractor shall determine lengths based on field observations.
10/16/2012 1:26 PM
12-1050316Rowan
Will the contractor be allowed to clear “as needed” any areas where the “remove and replace WW fence type 1” is intended.
Refer to note 18 under Notes Applicable on page 52 of 169.
10/16/2012 1:26 PM
12-1042200Barren, Hart
Will line item 1290, Tree and Brush Removal, be used and, if so, at what locations?
Please see “Clearing Limits” note on plan sheet R2R.
10/16/2012 2:14 PM
12-1050316Rowan
Will a temporary fencing item be added in case livestock should be encountered on these 2 projects?
Refer to note 18  under Notes Applicable on page 52 of 169.
10/16/2012 1:26 PM
12-2453303Woodford
Quantities for this project show 275 LF of 3' conduit and 275 LF of Trench and Backfill. Are there plan sheets or detail that show where these items are used and what they are for?     
Currently, there is 3” conduit under the existing pavement for the traffic loops.  The new 3” conduit is to replace the existing conduit.
10/16/2012 2:16 PM
12-1035314Larue
This project has a Nationwide Permit#14 in the proposal. When the contractor applies for the NOI for this project will a "Individual Permit" be required? 
As long as the activities and impacts do not extend beyond those listed in the NOTICE and the attached conditions are followed, no further permits will be required for Section 404/401 of the Clean Water Act.  The NOI is a Notice of Intent which is related to KPDES permits of Section 402 of the Clean Water Act.  An Individual Permit from KPDES is not needed for this project.
10/16/2012 2:15 PM
12-1354206Marshall, Trigg
Has the bridge color been determined?
Yes, it is Off-White FS# 37722
10/15/2012 8:34 AM
12-2456402Henderson
Is there a patching table missing for the section from Intersection of KY 1299 to Canoe Creek?
Yes.  It will be posted in the project related information on the website.
10/16/2012 7:52 AM
12-1358311Fleming
The typical sections indicate milling and texturing on Existing KY 11, but there is no bid item for milling.  Will this be in the addendum?
Yes, an addendum will be posted on the website.
10/16/2012 8:33 AM
12-2454307Carroll
In the Traffic Control Plan on page 29 of 87 in the proposal, it states that all lanes must be maintained and no work between 5:00 am through 9:00 pm.   Then it states on U.s. 42 and KY 36/KY 227, maintain at least one lane of traffic in each direction at all times.  Does KYTC want all lanes open by 5:00 am?  Is the intent by KYTC to perform this project during weekend Saturday’s/Sunday’s and have traffic on new JPC Pavement by 5:00 am? 
Yes, the weekly closures that must be reopened by 5:00 a.m are to perform work such as sawcutting and other operations that can be completed during that allotted time.  The JPC work will need to be completed on the weekends from 9:00 p.m. Friday and be opened to traffic by 5:00 a.m. Monday morning.
10/16/2012 7:47 AM
12-2453303Woodford
Can a plan sheet and/or sketch showing approximate dimensions and/or quantities of concrete pavement work per phase be provided?
An approximation of the quantities in each phase will be posted in the project related information section on the website.
10/16/2012 9:23 AM
12-1043309Kenton
Concerning line number 1090   “Variable Message Sign – Dynamic”, Is there any additional information or any specifications regarding this bid item anywhere in the job proposal or plans?
That bid item will be revised and an addendum posted to the website.
10/16/2012 7:48 AM
12-2454307Carroll
What is bid item 0020- Crushed Aggregate size No. 57 to be used for? 
The crushed aggregate size no. 57 is for the under drains, and also goes under the concrete pavement as part of the sub base.
10/16/2012 9:30 AM
12-1354206Marshall, Trigg
The Typical Sections on Sheet R2A show Type III Geotextile Fabric being utilized as a separation layer between the existing ground line and the Granular Embankment.  A large amount of the fabric will have to be placed under water and at depths up to 30’.  Will the Department consider omitting the use of a separation layer in its entirety?
The fabric (or the use of a separation layer in its entirety) will not be eliminated.
10/16/2012 2:48 PM
12-2453303Woodford
It seems there will be DGA Base needed to reach the 10 inch depth for the 24 Hr. JPC pavement..  Will the state provide a line item for DGA base? 
If DGA Base becomes necessary during construction, a supplemental agreement will be done.
10/16/2012 2:17 PM
12-1354206Marshall, Trigg
Concerning line item 0060 Granular Embankment has a cubic yard (CUYD) pay item, will the Department change this item’s pay unit to Ton in lieu of CUYD?  If the Department elects to not change the pay unit, how will the actual quantity installed be measured?   
The Department will not change this item’s pay unit to Tons in lieu of Cubic Yards. The quantity will be measured the same way that Embankment-in-Place is measured as described in Section 206 of the Standard Specifications.
10/16/2012 2:48 PM
12-1354206Marshall, Trigg
Sheets R23 and R24 Treatment of Embankments at Lagoon Bridge End Bents show 8” perforated underdrain pipes with headwalls exiting the embankment at 4 locations.  There are no bid items set up for this work.  If they are to be installed with the embankment can bid items be incorporated into the bid schedule for this work?
Per Special Provision No. 69, the 8 inch perforated underdrain pipe is incidental to the granular pile core and the 4 inch perforated underdrain pipe is incidental to the structure granular backfill.  Special Provision No. 69 also specifies wrapping the perforated pipe with a fabric of a type recommended by the pipe manufacturer and according to Section 704.04 of the Standard Specifications, the geotextile fabric used for wrapping the perforated pipe is incidental to the perforated pipe.  Additionally, the headwalls for the 8-inch perforated pipe are incidental to the granular pile core and the headwalls for the 4-inch perforated pipe are incidental to structure granular backfill.
10/16/2012 2:48 PM
12-1042200Barren, Hart
Is the 2015 completion date correct for this job?
The completion date of September 15, 2015 is in error.  The completion date shall be September 15, 2014.  Please bid accordingly.
10/18/2012 7:42 AM
12-1354206Marshall, Trigg
The Typical Sections on Sheet R2A show Type III Geotextile Fabric being utilized as a separation layer between the existing ground line and the Granular Embankment.  A large amount of the fabric will have to be placed under water and at depths up to 30’.Will the Department omit this item for the water application and incorporate a bedding material in lieu of the geotextile fabric? 
A bedding layer or other substitution for fabric will not be permitted.
10/16/2012 2:48 PM
12-1354206Marshall, Trigg
There will be over 12,000 tri-axle loads of material that will have to be transported over the Eggner Ferry Bridge.  If the Department reduces the load limit during the work will you allow the contractor an equitable adjustment for reducing the limit?
As with all structures, KYTC’s goal is to maintain the present rating of the existing Eggner’s Ferry bridge, however that cannot be guaranteed.  It is not prudent to answer a hypothetical question as there are several factors involved with oversight, funding and project conditions.  As with all projects, KYTC will evaluate any request for compensation based on the totality of the circumstances.  Any contractor claims resulting from KYTC decisions shall be handled per Section 105.13 in the 2012 Kentucky Standard Specifications for Road and Bridge Construction.
10/16/2012 2:48 PM
12-1354206Marshall, Trigg
The Typical Sections on Sheet R2A show Type III Geotextile Fabric being utilized as a separation layer between the existing ground line and the Granular Embankment.  A large amount of the fabric will have to be placed under water and at depths up to 30’. What quality control measures will the Department use to verify the geotextile fabric is placed properly on the lake bottom?
The Department will inspect and monitor installation of the geotextile fabric for conformance with the plans and specifications.
10/16/2012 2:48 PM
12-1354206Marshall, Trigg
The Typical Sections on Sheet R2A show Type III Geotextile Fabric being utilized as a separation layer between the existing ground line and the Granular Embankment.  A large amount of the fabric will have to be placed under water and at depths up to 30’.  Will the department require sowing of adjoining seams for the fabric being placed in the water?  If not, what measures will the Department use to assure that the contractor has proper lapping of the seams?
Sewing will not be required within the limits of fabric placement under water but will be permitted in accordance with Section 214 of the Standard Specifications.  However a minimum overlap of 36 inches (two times the standard overlap of 18 inches) will be required within these limits.  In accordance with Section 214 of the Standard Specifications, the Department will not measure laps or seems.
10/16/2012 2:48 PM
12-1354206Marshall, Trigg
During the pre-bid meeting the comment was made that the fill material was to be placed using a rear dump method.  Could you please offer further clarification of that statement?
The requirements for placing granular embankment in the lake are described in Note 11 on the geotechnical note sheets in the roadway plans.
10/16/2012 2:50 PM
12-2453303Woodford
Will the state be willing to break each phase into two weekends each to allow the removal of the existing concrete slabs and pour back of the 24 Hr JPC Mix and the standard integral curbs?
No, the Department will not consider breaking the phases into 2 weekends.
10/16/2012 2:17 PM
12-1349111Boone
Regarding the sanitary sewer – The SD1 Spec Section 02610, Pg 1, calls for the 18” pipe to be PVC C905 DR14 from 0’ to 30’.  Our pipe suppliers have confirmed that 18” PVC C905 DR14 is not a product that is produced. The closest rating is C905 DR18. Please clarify.
The pipe type should be C905 DR18.
10/18/2012 7:43 AM
12-1349111Boone
The 15 inch  gravity pipe, specs for less than 20 ft depth ,has SDR-35 as acceptable material in the proposal but plan note requires all PVC including laterals to be SDR-26. What type of pipe will be required?
All gravity sewer that is direct burial 20 feet or less shall be SDR35
10/18/2012 7:43 AM
12-2454307Carroll
Can temporary lane closures remain during non working hours in each work zone?
No.
10/18/2012 7:46 AM
12-2454307Carroll
Can a drawing of where the integral curb is to be placed be provided?  If existing curb is to be removed, how will it be paid?  
The integral curb will be placed in areas where the new concrete pavement is being placed.  The removal of the existing curb will be incidental to the pavement removal item.
10/18/2012 7:46 AM
12-2280408Russell
Does the following note from the Traffic Control Plan, “No lane closures will be allowed during the following hours: US 127X Monday – Friday 7:00 am – 6:00 pm, US 127 Monday – Friday 6:00 am – 5:00 pm”, mean the Department wants the work on the above referenced job to be performed at night?
Yes, the project has to be constructed at night or on the weekends.
10/18/2012 7:44 AM
12-1358311Fleming
Water valve relocation needs to be done before placing fill, who is responsible for said relocation? 
The property owner will be compensated to have this completed prior to the placement of fill.
10/18/2012 7:45 AM
12-1042200Barren, Hart
Please advise where a drawing or procedure for installing Type 1 sign posts using the A type of ground mount can be found.
The drawings for Type 1 sign post are on plan sheet T8.  The details for an “A” type beams installation can be found on the signing detail plan sheets.
10/18/2012 8:51 AM
12-1349111Boone
Sheet T-17 notes reference Maintain Lighting.  However, the bid items list Temporary Lighting.  Are these are meant to be the same?  What will be required for Temporary Lighting?
REVISED ANSWER:  Temporary Lighting is not necessary for the project.  The “Maintain Lighting” was separate from the “Temporary Lighting” with the intent that if there was any existing lighting present, it should be maintained during construction.  Payment for the Maintain Lighting will be made under the Temporary Lighting bid item.
 
10/18/2012 7:47 AM
12-2453303Woodford
The proposal call out installing the pre-formed loops and lead ins before milling.  Will the Pay Item "Loop Saw Slot and Fill" be added?
No, the pay item “Loop Saw Slot and Fill” will not be added.  Any reference to installing loops before milling is for installation when asphalt is the final pavement.  This is project has concrete.  Please see page 19 of 82 in the proposal for concrete (with more than 4 inches) installation.
10/18/2012 8:14 AM
12-1349111Boone
Regarding bid item number 3130, Masonry Coating, where is the masonry coating to be used? 
The Masonry Coating is to be applied on all exposed faces of all MSE walls (except where a form liner pattern is present).
10/18/2012 10:12 AM
12-1349111Boone
Regarding bid item number 3120,Granular Embankment, is the granular embankment item is for material behind the retaining wall? 
This quantity is for the granular replacement behind the reinforced fill of Wall #2 and under Wall #5 (per the Geotech Report; See Drawing Number 26350—Sheets 18 and 27).
10/18/2012 10:12 AM
12-1349111Boone
Can Crushed Concrete DGA be used in lieu Crushed Stone Base?
No, Crushed Concrete DGA cannot be used in lieu Crushed Stone Base?
10/18/2012 9:27 AM
12-1349111Boone
There is a discrepancy between the sanitary specs in the proposal and the notes on  the plans referencing PVC gravity sewer. The plan note #8 page U88  specify SDR-26 pipe. The proposal sect 02610 page 173  gravity sewer 0-30ft depth requires PVC C905 DR 14. Should all the PVC gravity pipe 18” 0-30ft depth use SDR-26? 
Plan note 8 is correct; all 6" or less size lateral piping and fittings are to be SDR 26.
10/18/2012 7:43 AM
12-1043309Kenton
Regarding the sanitary sewer, are there any existing flow rates available from SD1, in order to size the by-pass pumping?
Flow rates are unknown at this time.  The contractor shall draw his own conclusions as to bypass pumping needs. SD1 does not have consistent flow data for this line.  Contractor is responsible to maintain flow without bypassing sewage into the environment.  By- Pass pumping must be designed to carry full capacity of line being diverted.
10/18/2012 10:54 AM
12-1043309Kenton
Regarding the sanitary sewer, will there be a pay item for the 6” lateral on Page U42?
Installation of the 6 inch lateral shall be considered incidental to sanitary sewer construction.  This incidental work includes labor, equipment, and materials to install the lateral complete and ready for use per SD1 specifications.  Materials shall include; but, is not limited to, 6 inch PVC pipe, transition coupling for connecting the existing pipe to the new lateral, tee in the main line for connecting the lateral, any bends, and a 6 inch clean-out extended to ground level where the new lateral is connected to the existing pipe.
10/18/2012 10:54 AM
12-1349111Boone
There is no Bid Item for SIGNS (Item 2562). Is this an oversight?
The temporary construction signs will be paid for with bid item line no. 2080, item no. 2562, Signs, as per Standard Specification 112.
10/18/2012 7:47 AM
12-1043309Kenton
Regarding the sanitary sewer, where is the reconstruct manhole located?
The Reconstruct Manhole is approximately 63 feet left of ML station 90+55.  This manhole is shown on sheet U2.
10/18/2012 10:54 AM
12-1358311Fleming
Can Crushed Concrete DGA be used in lieu Crushed Stone Base?
No, Crushed Concrete DGA cannot be used in lieu Crushed Stone Base?
10/18/2012 9:21 AM
12-1349111Boone
Regarding bid item number 3150, Concrete Form liner, Where is this?      
The plans state that the form liner shall go on the face of Wall #4 only (see Drawing Number 26350—Sheet 10).
10/18/2012 10:12 AM
12-1354206Marshall, Trigg
Sheet R40, Note No. 9 states that the contractor shall remove the existing riprap (above and below the water line) in the footprint of the proposed embankment.  The note also states that the work is incidental to the Granular Embankment item.  Will the Department consider changing this requirement and add an excavation item for the removal of the riprap (paid by the cubic yard) based on the following: There is not enough information provided in the bid documents to estimate the potential quantity of riprap to be removed, the note does not specify a termination depth for the riprap removal, there is no definitive way to estimate the removal quantity for the areas under water, and an excavation item will allow the Department to pay only for the quantity removed, and alleviate risk on the contractor.
The Department will add a bid item for “Special Excavation” (CY) for the removal of the rip-rap.  Additionally, the extent of the required rip-rap removal will be reduced.  All rip-rap above elevation 359 feet will need to be removed.  However, below elevation 359 feet rip-rap will be removed only in the areas where wet soil mixing will be performed.  These areas are defined in the Soil Cement Column layouts on Sheet R83 of the Roadway Plans.  Additionally, turbidity curtains will be required to be installed around the perimeter portions of the wet soil mixing areas that are adjacent to the lake and lagoon.  The turbidity curtains will be required to be in place during the removal of rip-rap below elevation 359 and during wet soil mixing operations.  The turbidity curtains will be incidental to the unit bid price for “Wet Soil Mixing”.  An addendum will be issued to add the bid item and estimated quantities for “Special Excavation”, revise Geotechnical Note No. 9 on Sheet R40 of the Roadway Plans, and provide an addendum to the Special Note for Wet Deep Soil Mixing.
10/16/2012 3:05 PM
12-1349111Boone
Can any geogrid be used that meets section 304, or must only TX-5 or equivalent be used?”
The only geogrid reinforcement that will be permitted is Tensar TX5 or equivalent.
10/17/2012 10:36 AM
12-1041107Grayson
Is there an asbestos/hazardous material report required prior to demo?  If so, who pays for the testing?
Asbestos testing may be required. This will be determined upon coordination with the Division of Air Quality. This work shall be incidental to structure removal.
10/16/2012 3:43 PM
12-2661102McCracken
For bid item # 0100 - Concrete Patching Repair – Deck, will Class M concrete be allowed?
Class M can be used for Concrete Patching Repair-DECK for area’s where patch has a depth of at least 3.5” into the slab and temperature limitations can be maintained.  All other areas shall receive rapid set material.
10/17/2012 9:20 AM
12-1349111Boone
Traffic control plans call for West-North Temporary Connector and a North South Temporary Connector on plan sheet R113  There is no item for diversion.  Under what item would the prep and removal of these two connectors handled?
The prep was accounted for with the MOT quantities for pavement and the earthwork quantities. The removal will be incidental to the bid item, Maintain & Control Traffic.
10/17/2012 10:41 AM
12-1354206Marshall, Trigg
What is the purpose of Sheet S60 in the Bridge plans?
Sheet S60 “Future Deck Replacement” is included in the plan set to ensure that on future contracts the intended phasing of the original designer can be followed for this work.  This information will not be utilized for the current contract.
10/17/2012 12:36 PM
12-1353113
This project has a 10” Force Main that is being relocated near the intersection of Worthington Road and KY 56.  Will you be shutting down the line to make the relocation or will we be required to bypass the flow? 
It is anticipated that the down time to make the reconnections of the sanitary force main can be kept short enough to allow for shut down of the pump stations, and no need to bypass flow.  This will depend on the Contractor's means and methods to complete the project.  With adequate notification RWRA can have the system pumped down and shut down for 6-8 hours (dry weather only).  If conditions can't be met, we will require bypassing.  Containment and clean-up of any discharges will be required.
10/17/2012 1:57 PM
12-2454307Carroll
Will the state allow the temporary shutdown of Park Avenue during construction?
Yes, as long as the shutdown period does not exceed 2 weeks.
10/17/2012 1:10 PM
12-2454307Carroll
The proposal states that no work will be allowed when Carroll County Schools are in session.  Does this mean we cannot start work until the end of the school year or can we work on weekends during the school year?
The Contractor can work on weekends or nights during the school year, but all lanes must be open for school traffic during the day.
10/17/2012 1:10 PM
12-1041107Grayson
How is the low-water crossing shown in the conceptual drawing on page 41 of the bid proposal to be paid?
The low-water crossing is incidental to the maintenance of traffic, bid item 2560.
10/18/2012 7:30 AM
12-1042200Barren, Hart
Is the intent to construct the wing walls with piling during phase 1 for the KY 2746 bridge over I-65 and keep traffic maintained  on existing KY 2746 during construction of bridge?  It appears the piling for the wing walls on the end bents are under the existing bridge / and / or coincide with the existing roadway.
See revised plan sheet R124.
10/18/2012 11:29 AM
12-1358311Fleming
How will Pipeline Video Inspection be paid?
The bid item will be added by addendum and posted on the website.
10/18/2012 11:31 AM
12-1043309Kenton
Regarding the sanitary sewer, is the proposed sanitary sewer that is located in the existing pavement to be constructed under traffic, or can the road be closed during this phase?
The sanitary sewer is to be constructed while maintaining traffic.  The contractor may choose to employ temporary pavement widening, trench plating, or other methods that may be approved by the KYTC Section Engineer.  Any expense for maintenance of traffic is incidental to sanitary sewer construction as stated in the sanitary sewer specifications contained in the proposal under section 8.2. of the “Specification Explanation for Sanitary Sewer Construction”
10/18/2012 10:54 AM
12-1350103Hopkins
Does the existing lighting that is to be removed become the property of the contractor or KYTC?
The existing lighting that is to be removed on this project shall become the property of the contractor.
10/18/2012 1:08 PM
12-1350103Hopkins
Why is blasting not allowed on the project?
The Department made the determination based on the information available.  Blasting will not be permitted.  Please bid accordingly.
10/18/2012 12:49 PM
12-1353113Daviess
It appears there is concrete under the pavement that is to be removed and used as embankment.  Do your record or information show that to be true?
Archive plans do indicate the presence of concrete on KY 81.  Archived plans do not exist for KY 56 to verify.
10/18/2012 10:56 AM
12-1353113Daviess
There is an 10IN DUAL SHUT-OFF W/ FLOW MONITOR LOOP (ITEM 24556ED) AND AN 8IN DUAL SHUT-OFF W/ FLOW MONITOR LOOP (ITEM 24556ED) but there is no detailed drawings for the assembly. Can you provide a detail on what those items need to consist of?
The detail is posted in the Project Related Information section on the website.
10/18/2012 1:20 PM
12-2454307Carroll
Has the INSPECT & CERTIFY EDGE DRAIN SYSTEM bid item been entered twice accidentally?
Yes, the item was inadvertently entered twice.  Both pay items will be paid when the work is accepted.  The contractor will only be required to inspect and certify once.  Please bid accordingly.
10/18/2012 1:39 PM
12-1349111Boone
Concerning electrical items of PVC conduit and pole bases in barrier wall. Will the electrical contractor be required to install these items?
The conduit must be installed to meet all KYTC electrical specifications as well as national electric codes by a contractor qualified to do so.
10/18/2012 1:40 PM
12-1354206Marshall, Trigg
Can the Cabinet provide a list of Contractors pre-qualified/pre-approved to perform the Wet Soil Mix work item?
There is not a Wet Soil Mix prequalification item with KYTC.  However, a resource that list contractors who do this type of work is the Deep Foundation Institute at the following website: http://www.dfi.org/ .  By conducting a search for “Deep Soil Mixing” on the website, a list of contractors who may perform this work will be returned.  Please note that anyone performing this work must meet the qualifications in the proposal which includes but is not necessarily limited to Section 2.1 of the Special Note for Wet Deep Soil Mixing on Page 21 of 177.
10/19/2012 3:47 PM
12-1354206Marshall, Trigg
Reference- Bid Line No. 740 thru 780, the bid item quantities appear to be based on the Extended Drive criteria, plus 10 feet additional penetration, for the proposal page 42 of 177 driving chart using the assumed mudlines given on Paragraph 1.6.3 (Proposal page 46 of 177). If the pile meet refusal at or above the extended criteria tip elevation, the pay quantity will be reduced, however the effort needed will likely be the same regardless of tip elevation reached.  Can the pile installation be paid for by each pile, or a reasonable reduced penetration footage for bid purposes?
The pile installation bid quantities were determined as described in the question in order to allow for the potential that the piles could be driven deeper than the “Extended Drive Approximate Pile Tip Elevations” in the Special Note for Pile Load Test Program.  As stated in the question it is also possible that piles could be terminated higher than anticipated.  Therefore, applicable  “Test Piles – Install” unit prices will be paid for the actual pile lengths installed as defined in Section 1.6.3 of the Special Note for Pile Load Test Program.  However, applicable “Test Piles – Furnish” unit prices will be paid for the entire order lengths specified in Table 1.4.1 of the Special Note for Pile Load Test Program regardless of the pile length actually installed.
10/25/2012 8:02 AM
12-1353113Daviess
Please explain the  "Maintain Lighting " note on Sheet T1.  Is the existing lighting on this project to be maintained?
The intersection needs to be lit throughout the construction process, whether that is maintaining the existing lighting while the new lighting is being installed or using temporary lighting.  If using temporary lighting the proposed plans need to be submitted to the Central Office Division of Traffic for approval.
10/18/2012 2:33 PM
12-1353113Daviess
There is an 10IN DUAL SHUT-OFF W/ FLOW MONITOR LOOP (ITEM 24556ED) AND AN 8IN DUAL SHUT-OFF W/ FLOW MONITOR LOOP (ITEM 24556ED) but there is no detailed drawings for the assembly. Can you provide a detail on what those items need to consist of?
The detail is posted in the Project Related Information section on the website.  There was an error in the first drawing.  An updated drawing was posted at 2:10 pm, 10/18/12.
10/18/2012 2:34 PM
12-1354206Marshall, Trigg
Concerning the Special Note for Wet Deep Soil Mixing, there are several notable provisions that inflate costs and require significantly more time to complete than reflected in the current bid documents.  Pre-production field and laboratory testing program which includes additional soil borings, DSM binder mix testing program and three non-production test sections – These initial steps require significant and costly efforts as the soil borings would be required to be retrieved from a barge operation.  The binder mix testing program requires that a mix be developed for “each type of soil where ground improvements will be performed “with each mix requiring a 28 day compressive strength test.  Additionally, this same specification section requires that “a minimum of twenty (20) specimens per soil stratum at each bent location using four (4) different DSM binder mixes.”  Finally, prior to production, at each of the three different DSM locations a “minimum” of one 25’ x 25’ test section is required.  All of this work must be completed prior to production work can commence.  Could this provision be revised?
The scope of Deep Soil Mixing (DSM) in this contract will be significantly reduced by eliminating the DSM at the Kentucky Lake End Bents and requiring it only at the Lagoon Bridge End Bent 2.  This will result in a reduction of bid quantity from 57,500 CY to 12,500 CY.  Additionally, portions of embankment construction adjacent to the Kentucky Lake End Bents will be eliminated from this contract.  Furthermore, the contract time will be increased by 90 days.  These changes will be made via an addendum.  As the result of the reduced DSM work scope only three borings will be required at End Bent 2 of the Lagoon Bridge.  The contractor could cut a bench in the causeway and perform these borings on land and they would not necessarily have to be performed from a barge.  If the contractor provides a binder mix that results in the specified 75 psi compressive strength being achieved prior to 28 days then the contractor may proceed with constructing the test section.  However, some testing at 28 days will be required in order to obtain test data.  The test section will also not necessarily have to be performed from a barge.  Again, if the specified 75 psi compressive strength is achieved prior to 28 days then the contractor may proceed with production mixing.
10/26/2012 1:17 PM
12-1354206Marshall, Trigg
Could a redesign of the abutments be utilized that would still be founded on the piles but would be more cellular in nature and therefore less dependent on the embankment and would therefore not be impacted by settlement from a seismic event?
A redesign of the abutments is not currently being considered.
10/26/2012 1:17 PM
12-1354206Marshall, Trigg
The geotechnical report included a WEAP drivability analysis for driving the 96 inch diameter pile using an IHC S-2000 pile hammer with a maximum energy of approximately 1,300,000 ft-lb.  We have contacted both IHC and Menck, which makes a comparable hammer, the MHU 1900S which has a maximum energy rating of 1,401,368 ft-lb.  We are not currently aware of any other hammer manufacturers with equivalent hammers.  With an anticipated notice to proceed in early December and given the time frame quoted for the pile hammer delivery it is unlikely that the 96” and 72” diameter pile load tests can be completed within the KYTC’s required timeframe required by the Special Note for Pile Load Test Program, paragraph 1.3 Schedule.  Can an additional 90 calendar days given to complete this portion of the pile load test program?
The wave equation analyses included in the geotechnical report were performed by the Department’s consultant to evaluate the feasibility of driving the specified pile sizes.  However, these analyses are for information only and the hammer energies used for those analyses are not contractually specified hammer energies.  Bidders are advised to retain an engineering consultant to perform independent wave equation analyses in order to select hammer(s) that meets the specified requirements for this project.  This engineering consultant should meet the criteria for “Wave Equation and Pile Driving Analyses” in Section 1.3.2 of the Special Note for Dynamic Pile Testing and have extensive experience performing wave equation analyses, dynamic pile testing and signal matching analyses on projects with pile and hammer sizes similar to those to be used on this project.  The hammer(s) selected based on these independent analyses may differ from the hammers used in the analyses included in the geotechnical report.
 
The Department will modify the hammer selection criteria so that for the hammer(s) required to drive the 72- and 96-inch diameter piles may be selected based only on the Initial Driving Criteria defined on page 5 of 14 of the Special Note for Dynamic Pile Testing, which is proposal page 69 of 177.  (Extended driving does not apply to the lagoon bridge, so the hammer selected to drive those piles may also be based on the Initial Driving Criteria.)  However, for the 48-inch diameter piles the Extended Driving Criteria defined on page 5 of 14 of the Special Note for Dynamic Pile Testing will apply for hammer selection.  Furthermore, during actual driving the Extended Driving Criteria defined on page 8 of 11 of the Special Note for Pile Load Test Program will apply for the 48-, 72-, and 96-inch diameter piles.  An addendum will be issued to document these changes.
 
If the contractor’s consultant performs wave equation analyses based on the modified criteria it is likely that smaller hammer(s) can be utilized to meet the criteria and achieve the goals of the pile testing program and maintain the specified project schedule.  Therefore, the Department will not grant an additional 90 days to complete testing on the 72- and 96-inch diameter piles.
 
10/23/2012 7:46 AM
12-1354206Marshall, Trigg
Concerning the Special Note for Wet Deep Soil Mixing, there are several notable provisions that inflate costs and require significantly more time to complete than reflected in the current bid documents.  Techniques required to penetrate through the zones of chert – The Special Note requires that the DSM ground improvement penetrate through and extend below the existing chert layer.   Based on our experience with this material, and according to the DSM contractors we have contacted, it will not be possible to penetrate this layer of with conventional DSM equipment and techniques, nor is this material suitable for mixing if you could.   Consequently, an additional barge mounted drilling operation will be required to excavate through and dispose of this material, and the hole will have to be backfilled with purchased material prior to beginning the soil mixing operation. Could this provision be revised?
At the Lagoon Bridge End Bent 2  location only minimal amounts of chert were encountered during geotechnical investigations in the sand layer in which DSM is required.  None of the DSM columns extend into the bedded chert layers.
10/26/2012 1:17 PM
12-1354206Marshall, Trigg
Concerning the Special Note for Dynamic Pile Testing, Please explain how the quantities for Line Items 0800-Initial and 0810-Restrike were determined relative to the referenced special provision. 
A total of three (3) initial tests and four (4) restrike tests were set up for each of the seven (7) Kentucky Lake test piles.  There are some contingency test quantities to account for the potential that some testing beyond that described in the Special Notes may be required based on obtained test results and encountered conditions.
10/23/2012 1:32 PM
12-1354206Marshall, Trigg
Why was Deep Soil Mixing (DSM) chosen in this case, given the apparent density of the ground underlying the site already. 
DSM is required only in the liquefiable sand layers.  These are above the dense bedded chert layers.
10/26/2012 1:17 PM
12-1354206Marshall, Trigg
Concerning the Special Note for Wet Deep Soil Mixing, there are several notable provisions that inflate costs and require significantly more time to complete than reflected in the current bid documents. Temporary casings– Installation of the columns through water and containing the spoils as required by the Note will require a temporary casing at each location.    These casings will require a template in order to accurately locate and support them during installation, which will require a separate floating operation. Could this provision be revised?
Turbidity curtains will be required as described in an answer posted at  3:05 pm on 10/16/2012.  An addendum to the Special Note for Wet Deep Soil Mixing and a Geotechnical Note Sheet related to this has been prepared and will be issued.  As a result of the turbidity curtain, the use of temporary casing is not required for spoil containment but may be used at the discretion of the contractor.
10/26/2012 1:17 PM
12-1354206Marshall, Trigg
To eliminate the extensive cost of the marine equipment along with the impact of the slower productions of the DSM operation, could the granular embankment be placed in a larger footprint that would allow for all of the DSM to be performed from land? 
The specified construction sequence was determined after extensive conversations with DSM specialty contractors who advised the Department’s geotechnical consulting team that performing DSM through granular embankment would be difficult, if not impossible.
10/26/2012 1:17 PM
12-1354206Marshall, Trigg
Concerning the Special Note for Wet Deep Soil Mixing, there are several notable provisions that inflate costs and require significantly more time to complete than reflected in the current bid documents. Survey, coring/sampling and grouting of each of the DSM columns – Each of the approximately 1,800 columns will need to be surveyed by a professional surveyor to locate its proper location prior to installation and after the DSM is completed the specification requires approximately 30 confirmation cores once the columns have been completed.  These core holes will then need to be grouted.  All of this work will need to be performed from a barge and prior to placing the granular embankment. Could this provision be revised?
Surveying is required to determine where to install the DSM columns.  Core sampling is required to ensure that the completed soil mix columns have sufficient strength to satisfy the design criteria.  We understand that this is typical practice for this type of construction.  With the reduced scope of work it appears that approximately 6 to 8 core holes will be required.  The requirement to grout the core holes will be eliminated.
10/26/2012 1:17 PM
12-1354206Marshall, Trigg
What is the required load for the pseudo-static lateral load test?
500 kips
10/23/2012 7:52 AM
12-1354206Marshall, Trigg
The design is based on a 2500 year seismic event.  Could this design criterion be relaxed to seismic events with a shorter return period, such as a 1,000 year seismic event as discussed in the Geotechnical report? 
The seismic design criteria are not being relaxed for the revised scope of work on the current contract.
10/26/2012 1:17 PM
12-1354206Marshall, Trigg
Section 1.3.2.2 of the special note for static and pseudo static pile testing indicates if failure occurs during loading to maintain the load until movement is 15% of the pile diameter.  In this case, that would be 7.2 inches for the 48 inch diameter pile.  Will it be required to have 8 inch dial indicators and a jack with enough stroke (likely 10+ inches) to move the pile this far?
The referenced 15% criterion is consistent with ASTM Test Method D1143.  The contractor will be required to furnish necessary equipment to meet this requirement.
10/29/2012 9:33 AM
12-1354206Marshall, Trigg
The size of each of the improved areas is significantly larger than the abutments and much larger than what is suggested in the geotechnical report.  Could a smaller zone around the abutments be improved so the same results could be achieved while also saving significant costs and time?
The size of the improved area at the Lagoon Bridge End Bent 2 is required in order to ensure that the embankment within the zone of influence of the end bent meets the 2500 year seismic design criteria which is necessary to ensure that the bridge meets the design criteria.  The  DSM areas indentified in the contract documents are identical to the areas identified in the Geotechnical Report.
10/26/2012 1:17 PM
12-1354206Marshall, Trigg
One other point to be mindful of is that, due to the congestion created by two DSM operations occurring on the western side of the causeway, along with the Shallow Water Pile Load Testing work area which is between the two, it will not be possible to begin the granular embankment in this location until these operations are complete. 
With the revised scope of DSM work and extension of contract time, we believe that these issues will be less significant than originally anticipated.
10/26/2012 1:17 PM
12-1354206Marshall, Trigg
Will a turbidity curtain be required during the placement of granular embankment?
No.
10/24/2012 1:50 PM
12-1354206Marshall, Trigg
Included in the geotechnical report is a one page schedule intended to represent the approximate construction duration for the DSM (noted as Attachment Section 3 Estimated Construction Schedule, Plan and Typical Sections).  The author of this schedule has included an allowance for the specification requirements for pre-production testing, the soil improvements and acknowledgments that the DSM must be completed in time to allow for final embankment operations.   Based on the requirements for preproduction testing and after discussions with the soil mixing subcontractors the preproduction testing could take between 6 and 8 months depending upon the amount of retesting required.  The schedule as illustrated allows for 120 days or 4 months.  Of the 275 days allowed for the DSM work, only 100 days are allowed for the actual production work.  The 100 days is noted as using “two rigs” and appears to be based on calendar days.  There are approximately 1,800 DSM columns required to be installed.  Working 7 days per week for 100 days, each “rig” would have to produce 9 soil columns per calendar day.  There is a plan note that stating that the contractor may only work during “daylight hours from April 1 through November 14” due to the potential for occupation of Gray Bats around Kentucky Lake.  This requirement would negate the possibility of working double shift during these 7.5 months which fall directly into the time frame that the production work would have to be performed.  Furthermore, based on the discussions with the soil mixing subcontractors and due to the extra steps necessary to prepare the holes for soil mixing and even using two rigs, the duration of the production work would last closer to 300 work days.  Working six days per week the work would take approximately 350 calendar days.  In total the entire project would last two calendar years.    Could this requirement be adjusted or the time increased.
The scope of Deep Soil Mixing (DSM) in this contract will be significantly reduced by eliminating the DSM at the Kentucky Lake End Bents and requiring it only at the Lagoon Bridge End Bent 2.  This will result in a reduction of bid quantity from 57,500 CY to 12,500 CY.  Additionally, portions of embankment construction adjacent to the Kentucky Lake End Bents will be eliminated from this contract.  Furthermore, the contract time will be increased by 90 days.  These changes will be made via an addendum.  As the result of the reduced DSM work scope only three borings will be required at End Bent 2 of the Lagoon Bridge.  The contractor could cut a bench in the causeway and perform these borings on land and they would not necessarily have to be performed from a barge.  If the contractor provides a binder mix that results in the specified 75 psi compressive strength being achieved prior to 28 days then the contractor may proceed with constructing the test section.  However, some testing at 28 days will be required in order to obtain test data.  The test section will also not necessarily have to be performed from a barge.  Again, if the specified 75 psi compressive strength is achieved prior to 28 days then the contractor may proceed with production mixing.  Because the pre-production borings and test sections can be performed on land rather than water the Department believes that the time impact associated with this work will be reduced.  Some of the production work associated with this revised scope will be performed from a barge and some can be performed on land.  As a result, the Department believes that the contractor could potentially perform this work using two rigs simultaneously if they so choose.
10/26/2012 1:17 PM
12-1354206Marshall, Trigg
Neither DSM nor stone columns are conducive in a marine environment for the various reasons stated above.  If the work needs to be completed from a marine-based operation, could a drilling and grouting operation that could be performed in a smaller footprint and with less equipment be used?
No, the specified footprint is required to meet the seismic design criteria for the bridge.
10/26/2012 1:17 PM
12-1354206Marshall, Trigg
In the Special Note for Wet Deep Soil mixing section 4.3-Pre-Production DSM Binder Mix Design Report, page 26 of 177, for costing purposes, please clarify what it the maximum number of days KYTC could take to review and approve the submittal.
A response to the submittal will be provided within 5 Business Days.
11/2/2012 1:52 PM
12-1354206Marshall, Trigg
In the Special Note for Wet Deep Soil mixing section 9.1-Coring and Sampling, sub. 1, page 32 of 177, the specification refers to “…drilling prequalification requirements…”: our understanding is that the coring can be performed only by a Third Party pre-qualified with KYTC. Please confirm.
Yes, this is confirmed.
11/2/2012 1:52 PM
12-1354206Marshall, Trigg
In the Special Note for Wet Deep Soil mixing section 4.2-Pre-Production Laboratory Testing, page 26 of 177, the last paragraph of this specification instructs the Contractor to test the mix for UCS at 7, 14 and 28 days while successive specification 9.3.4 adds also a test at 56 days. Please clarify which specification prevails.
Testing at 56 days will not be a requirement although samples should be retained in case the minimum strength is not meet at 28 days.  If this occurs, 56 day testing to verify strength will likely be required by the Engineer.  This will be clarified in the revised Special Note for Wet Deep Soil Mixing.
11/2/2012 1:52 PM
12-1354206Marshall, Trigg
In the Special Note for Wet Deep Soil mixing section 6.1-DSM Column Construction Tolerances, sub. 1, page 27 of 177, please further elaborate on the meaning of group column spacing (GCS) and block column spacing (BCS): we have not been able to find their definition so the meaning of the specification is unclear. Furthermore, the columns do not overlap according to the bid drawing so also the meaning of the last sentence of these paragraph is not clear (“…in order to obtain sufficient DSM column overlap…”). Please clarify.
The spacing for these columns is column type with square spacing.  Section 6.1.1 will be modified for clarity in the revised Special Note for Wet Deep Soil Mixing.
11/2/2012 1:52 PM
12-1354206Marshall, Trigg
In the Special Note for Wet Deep Soil mixing section 9.2-Wet Grab Sampling, sub. 2, page 33 of 177, please confirm if the additional testing mentioned is up to the Contractor or instructed by the Engineer; in case of the latter, please explain how the additional sampling and testing would be paid for to the Contractor.
The minimum grab sampling and testing is specified in the Section 9.2 (2) of the Special Note for Wet Deep Soil Mixing.  Additional grab sampling and testing beyond what is required may be performed at the discretion of the Contractor will be at the expense of the Contractor and at no cost to the Department.
11/2/2012 1:52 PM
12-1354206Marshall, Trigg
In the Special Note for Wet Deep Soil mixing section 7.1-Construction Equipment, sub. 11, page 29 of 177, please clarify who should certify the calibration: independent Third Party? If yes, having which kind of credentials?
The Contractor will be required to have a third party certify this calibration.  The third party doing the required calibrations will need to be a representative of the manufacturer of the soil mixing tool that is being used and have knowledge and experience performing these type of calibrations.
11/2/2012 1:52 PM
12-1354206Marshall, Trigg
In the Special Note for Wet Deep Soil mixing section 9.2-Wet Grab Sampling, page 33 of 177,  in our opinion wet-grab samples should not be taken on DMM elements because this kind of sampling has proven itself very difficult for the relatively thick mixtures and because there is substantial risk that wet-grab sampling could leave a defect at the location of sample extraction. Please confirm.
Wet Grab Sampling will be required as called out in Section 9.2.
11/2/2012 1:52 PM
12-1354206Marshall, Trigg
In the Special Note for Wet Deep Soil mixing section 8.3-Unforeseen Conditions and Corrective Remediation, page 31 of 177, the Contractor is required to remediate deficiencies of DSM columns due to unforeseen conditions at no cost for the Department. In our opinion, this specification translates into the Contractor forced to cover itself with heavy provisions and therefore inflating the cost of the project; we respectfully suggest to modify the specification so that if an unforeseen condition is encountered, the Contractor, after immediately notifying the Engineer, is compensated on the basis of time and material plus 15% markup. Please confirm.
Deficiencies due to unforeseen conditions that are no fault of the contractor are expected to be remediated by relatively minor design modifications (e.g. installing additional adjacent columns at closer spacing).  If the Engineer directs to the contractor to terminate a DSM column at an elevation higher than the plan tip due to an unforeseen condition that is no fault of the contractor and subsequently directs the contractor to install additional DSM quantities to remediate the high termination then the Department anticipates paying the contractor for the additional quantity installed at the contract price per cubic yard rather than on the basis of time and material plus markup.  This will be addressed in the revised Special Note for Wet Deep Soil Mixing.
11/2/2012 1:52 PM
12-1354206Marshall, Trigg
In the Special Note for Wet Deep Soil mixing section 1.1-DSM Mixing Method, page 20 of 177,  please further elaborate on the meaning of “…without use of externally directed high pressure jets.  Furthermore, specification 7.1.3 at page 28 of 177 seems to contradict 1.1 (refer to “…If grout injection jets are used…”).
The Special Note for Wet Deep Soil Mixing will be modified to allow the use of high pressure jets attached to the soil mixing tool.  The original language was intended to exclude jets external to the soil mixing tool.
11/2/2012 1:52 PM
12-1354206Marshall, Trigg
In the Special Note for Wet Deep Soil mixing section 4.1-Geotechnical Subsurface Investigation, page 25 of 177,  the spacing between exploratory boreholes is specified as minimum 5ft; the length of, for instance, Kentucky Lake Bridge Bent 1 is 216ft (Sta. 987+40 to 989+56) and therefore approx. no. 43 boreholes would be required well above the minimum quantity specified of no. 5. Please clarify what rules in this regard: the minimum quantity of boreholes (no. 5), the minimum spacing between them (5ft – unless the distance shown is a typo and it was meant 50ft) or the Contractor’s experience and engineer judgment.
The required minimum horizontal spacing between borings is not 5 feet.  The maximum allowed vertical spacing between sampling intervals in the borings is 5 feet.
11/2/2012 1:52 PM
12-1354206Marshall, Trigg
It is preferred to perform the soil mixing from an aggregate platform and not from barges.  Is the granular embankment a riprap type material or something smaller such as #57 aggregate?  Can it be clarified in the next addendum that temporary earthen/aggregate platforms can be used to perform the soil mixing at the contractors risk and option?
The contractor will not be permitted to install DSM columns through permanent Granular Embankment and a size #57 stone will not be permitted for the permanent Granular Embankment.  However, temporary earthen/aggregate working platforms will be allowed at the Contractor’s risk and option and as alternate to and/or in conjunction with working on a barge over the water.  In order to satisfy permitting requirements, these temporary working platforms will need to remain within the footprint of the proposed permanent embankment.  However, if the contractor obtains any necessary permits for this temporary platform to extend outside the permanent footprint and meets all applicable requirements (e.g. any necessary erosion, sedimentation, and turbidity controls, etc.) then it will be acceptable to the Department for the contractor to construct the temporary working platform outside the limits of the proposed permanent embankment.  The temporary platform will have to be removed prior to placing the permanent Granular Embankment.  This is an alternate that the Department will accept in order to provide some flexibility.  However, the contractor will ultimately be responsible for installing the DSM columns in accordance with the plans and specifications and for implementing the detailed means and methods.  An addendum/revision to the Special Note for Wet Deep Soil Mixing is currently being prepared and will include applicable clarifications to this issue.
10/31/2012 11:59 AM
12-1354206Marshall, Trigg
In the Special Note for Wet Deep Soil mixing section 2.0-Submittals, page 21 of 177, for costing purposes, please clarify what it the maximum number of days KYTC could take to review and approve the submittals.
Responses will be provided within 5 Business Days for all of the submittals except for the Review of the Shop Plans, Working Drawings, Schedule and Construction Plan which will be 10 business days.
11/2/2012 1:52 PM
12-1354206Marshall, Trigg
Concerning the Special Note for Pile Load Test program- Page 44/177, clarify the elevation of the artificial plugs to be installed.  For Pile K-6 is the plug installed 84 feet above the Initial Driving Criteria Highest Anticipated Tip Elev.(220 ft) or the Estimated Tip Elevation (200 ft)?
The artificial plug for Pile K-6 is to be installed 84 ft. above the tip of the pile.  (The elevation of the plug will then be 84 ft. higher than the pile tip elevation whether the pile tip is at Elevation 220 ft., 200 ft., or any elevation.)  For Pile K-7, the artificial plug is to be installed 82 ft. above the tip of the pile.
11/2/2012 3:26 PM
12-1354206Marshall, Trigg
Concerning this excerpt , “However, if the contractor obtains any necessary permits for this temporary platform to extend outside the permanent footprint and meets all applicable requirements (e.g. any necessary erosion, sedimentation, and turbidity controls, etc.)” from an answer given on 10/31/2012 11:59 AM, has KYTC obtained all permits required to initiate the project?  Will the KYTC provide a list of all necessary permits?  What was the duration to obtain approval of such permits? Will KYTC consider amending permits to allow for the additional footprint discussed in the previous answers?
KYTC has applied for the necessary permits from the Tennessee Valley Authority, U.S. Army Corps of Engineers, and the Kentucky Division of Water; but KYTC has not yet received approval as of 11/2/2012.  Public Notices issued by these agencies are scheduled to be complete in early November, and KYTC anticipates receiving a response regarding the permit applications subsequent to that.  The areas to the north of the causeways were identified in the permit application as a Temporary Construction Area.  KYTC does not object to the contractor obtaining an amendment to these permits for construction methods that result in impacts outside of the footprint in the original permit application.  However, it will be the contractor’s responsibility to obtain the amended permit, to produce all information required by the agencies, and to estimate the duration of that process.
11/5/2012 9:03 AM
12-1354206Marshall, Trigg
In the Special Note for Wet Deep Soil mixing section 2.1-Qualifications, page 21 of 177, the Contractor is required to prove its competence thru previous DSM projects having “…a minimum total treatment volume of not less than 20 percent of the DSM treatment volume of this project or 30,000 cubic yards…”; the total volume of DSM treatment for the subject volume being approx. 50,000cy (without contingency quantity – refer to drawing Sheet No. R83), 20% of it should be 10,000cy. Please clarify.
The revised bid quantity for DSM on this contract will be 12,500 CY including contingency and includes only the work at Lagoon Bridge End Bent 2.  Based on this quantity, 20% will be 2,500 CY.
11/2/2012 1:52 PM
12-1354206Marshall, Trigg
The KYTC specifications for Granular Embankment would allow for the use of #57 aggregate.  In the response listed below the KYTC indicates that #57 aggregate would not be acceptable.  Can the KYTC clarify  in the next addendum?
The Granular Embankment will be limited to a gradation size of No. 2 stone or larger up to a maximum size of 12 inches.  This will be clarified in the addendum.
11/5/2012 9:58 AM
12-1354206Marshall, Trigg
Concerning the Special Note for Dynamic Pile Testing , a previous answer indicated the Dept will change the hammer criteria for 72”/96” pile to Initial Driving Criteria. Table 1.4.1 Note 2 states resistances include the plugs and setup, not initial driving.  Page 69 of 177. For hammer selection…”when verifying the TNAR at the end of initial drive”. Does this mean the wave equation can be run to evaluate the hammer for the End of Driving Resistance (70% of TNAR) as this is when initial driving stops  (page 43 of 177)?
The geotechnical design team has estimated a setup factor of approximately 1.4.  However, the pile hammer will be required to be sized such that the contractor can confirm both 70% of the Target Nominal Axial Resistance (TNAR) at the End of Initial Drive (EOID) condition and 100% of the TNAR at the Beginning of Restrike (BOR) condition.  Wave equation analyses submitted for hammer acceptance must indicate that both of these resistances can be achieved with 0.5 to 0.1 inches of set (2 to 10 blows/inch) and driving stresses not exceeding 90% of the yield stress.
11/2/2012 3:26 PM
12-1354206Marshall, Trigg
Does the KYTC currently have the permits for placement of the granular embankment?  If so, how long did they take to obtain?  If not, could the permits be modified prior to being approved?
KYTC has applied for the necessary permits from the Tennessee Valley Authority, U.S. Army Corps of Engineers, and the Kentucky Division of Water; but KYTC has not yet received approval as of 11/2/2012.  Public Notices issued by these agencies are scheduled to be complete in early November, and KYTC anticipates receiving a response regarding the permit applications subsequent to that.  KYTC does not object to the contractor obtaining an amendment to these permits for construction methods that result in impacts outside of the footprint in the original permit application.  However, it will be the contractor’s responsibility to obtain the amended permit, to produce all information required by the agencies, and to estimate the duration of that process.
11/5/2012 9:58 AM
12-1354206Marshall, Trigg
Can the KYTC estimate the time required to obtain the necessary permits should the contractor chose to build the temporary embankments outside of the permanent embankment foot print?
No, it will be the contractor’s responsibility to obtain the amended permit, to produce all information required by the agencies, and to estimate the duration of that process.
11/5/2012 9:58 AM
12-1354206Marshall, Trigg
Special Note for Static Pile Testing- Section 1.2.1 of the Project Proposal (Page 81 of 177) states, in part, the following: “Apparatus will be designed to a minimum of 1.5 times the maximum expected test load (6000 kips for Pile K-1, 600 kips for L-1, and 1600 kips for L-2)”.  Is the required design load of “1.5 times the expected test load” to be interpreted as a “service load” by which the apparatus would be designed using an “allowable stress design method” such as AASHTO Service Load Design Method or is the load intended to be a “factored load” and the apparatus designed using a “strength design method” such as AASHTO Strength Design Method?
The piles will be loaded to maximum test loads of 6000 kips for Pile K-1, 600 kips for L-1, and 1600 kips for L-2.  The reaction system design engineer will be responsible for proposing an AASHTO design code (or another code allowed by the Department) and associated load factor(s) to apply to the maximum test loads based on the code.  The appropriate load factor(s) will apply rather than the referenced 1.5 multiplier.
11/2/2012 3:26 PM
12-1354206Marshall, Trigg
Concerning the Special Note for Pile Load Test program- Page 44/177, for the artificial plugs in the shallow water, clarify the sentence “…at a distance 12 feet below the mudline based on the Highest Allowable Pile Tip Elevation…”. Is the plug 12 feet below the mudline, or 12 feet from the tip elevation (also there is no Highest Allowable in Table 1.4.1)?
In the shallow water area, the mudline elevation could vary depending on the specific pile locations.  The artificial plugs for the shallow water piles (K-1, K-2, K-3, K-4, & K-5)  are to be located such that they are 12 feet below the mudline when the pile tips are at the Highest Anticipated Tip Elevation (El. 230 ft.).  The sentence should have read “..at a distance 12 feet below the mudline based on the Highest Anticipated Pile Tip Elevation…”
11/2/2012 3:26 PM
12-1354206Marshall, Trigg
Referring to USACE Permit General Conditions (Addendum 1 Page 129g of 177), item 5 implies that special conditions may affect work in the April 1-June 30 spawning season time period.  Will Item 5 have any effect on performing or scheduling work on the shallow and/or deep water test pile program in this time frame?
It is not anticipated that periods of high stream flow or fish spawning season will require any special conditions that would impact the schedule for the pile load testing program.
11/7/2012 3:13 PM
12-1354206Marshall, Trigg
Can a version of the Special Note for Deep Soil Mixing be provided that denotes changes that have been made?
Yes, a version with changes highlighted has been posted under “Project-Related Information” for the October 19, 2012 letting.
11/13/2012 3:25 PM
12-1354206Marshall, Trigg
Will the Department accept an Osterberg Cell bi-directional test for the three required static load tests?  The bi-directional test could also be used on some of the larger diameter higher capacity piles, if desired.
Because of types, sizes, and anticipated depths of these piles, the geotechnical team did not believe that the Osterberg method was feasible for these tests.  There are several issues that would need to be addressed prior to making a decision to allow this method and there is not enough time to address these issues prior to the letting.  Therefore, bidders are advised to bid the load tests as specified in the bid documents.  The Department may consider a proposal to change to the Osterberg method after the contract has been awarded if the successful contractor believes that this method is feasible and may result in cost and/or time savings and chooses to propose this method at that time.
11/13/2012 12:51 PM
12-1354206Marshall, Trigg
In regards to the Granular Embankment, could the Department please clarify which Specification will control the limits of the fines in this material?  Will Specification section 805.10 Granular Embankment or the spec for the gradation of size no. 2 material govern?
The No. 2 gradation will control the limits of the fines.
11/14/2012 9:18 AM