Questions and Answers

​​​​​​​​​​​​​​​​​​​​​​​

  
  
County
  
Question
Answer
  
12-1026101Fayette
Is granular backfill required?
No, granular backfill is not required.
8/1/2012 3:06 PM
12-2442317Johnson
In the proposal it does not specify if the Department is providing the used guardrail material for the lagging or the contractor needs to supply it.  Can you please clarify that for us?
REVISED ANSWER: CRIBBING will be furnished by the Department of Highways. An Addendum adding information to the special note has been posted to the website.
8/7/2012 11:03 AM
12-3132314Todd
On page 11 of the proposal section II Materials item B. Culvert Pipe it states to "Furnish Type 3 Metal End Sections" Should there be a bid item for " Metal End Sections"?
Metal End Sections will not be required on this project.  The note indicating the use of Metal End Sections was erroneously included in the proposal.
8/9/2012 11:19 AM
12-1341318Carroll
Line No. 0490 Remove Structure:  Should there be a separate line item for the removal of the two existing box culverts or just include with bridge removal or remove structure(s) price?
Revised Answer: As stated in the notes for the project, all three structures are included in the remove structure bid item.
 
8/8/2012 10:30 AM
12-1341318Carroll
Should there be an item for fabric geotextile Type IV for pipe?
Revised Answer:No there is no bid item for this, please bid accordingly.
8/8/2012 10:31 AM
12-2603100Jefferson
PROPOSAL NOTE PAGE 22 OF 84 – LAST SENTENCE OF IV.A – STATES TO SEE SPECIAL NOTE FOR USE OF HYDRODEMOLITION METHOD.  THIS SPECIAL NOTE HAS NOT BEEN INCLUDED IN THIS PROPOSAL.  WHAT IS THE DEPARTMENT’S INTENT REGARDING HYDRODEMOLITION FOR THIS PROJECT?
REVISED ANSWER:  There will be no direct payment for Hydro demolition if the contractor  chooses to use this method, it will be at his cost.  See section 606.03.03 and NOTE for methods.  In addition hydro demolition will not substitute for blast cleaning. An addendum will be posted to the website.
 
8/10/2012 11:51 AM
12-4025202Various
The above referenced projects both include language relating to the cleanup of milled debris from the milling of centerline and shoulder rumble strips as follows:  “Clean rumble strip and roadway grease, oil, mud, dust, dirt, grass, loose gravel, millings, or other deleterious material upon completion of the milling operation.  Use only Engineer approved cleaning methods.”  Does the Department want the material swept up off of the roadway surface by use of a pickup type broom, loaded, and hauled to an offsite disposal area or can the material  be wasted to the side of the road by use of a sweep to side type broom?
The material shall be swept up off of the roadway surface, loaded, and hauled to an offsite disposal area.
8/6/2012 9:52 AM
12-3132314Todd
On the proposal on page 4 it states that the project starts at mp8.244 and ends at 11.703.  On page 24 there is a culvert pipe to be installed at MP 11.89 this is past the end of the project is this MP correct and if so, is this the cross drain pipe across HWY 106?
The proposal incorrectly states that the pipe is at MP 11.89.  The pipe is to actually be installed at MP 11.089.
8/9/2012 1:17 PM
12-1341318Carroll
Is the completion time of 90 calendar days correct?
Revised Answer:No. KY 36 may be closed for 90 consecutive calendar days and work must be completed by June 30, 2013.  An addendum has been posted to the website.
 
8/10/2012 12:58 PM
12-3130406Logan
On page 10 of the proposal in section II Materials line item B Culvert Pipe states" to Furnish Type 3 Metal End Sections" Should there be a bid item for the Metal End Section?
Metal End Sections will not be required on this project.  The note indicating the use of Metal End Sections was erroneously included in the proposal.
8/9/2012 11:20 AM
12-1027300Perry
The Paving Summary sheets and drawing sheets 40 & 41 of 157 show a CL3 1.5D PG64-22 mix and the Bid Item sheet (Bid Item 70) lists CL3 1.00D PG64-22. Please specify which mix is intended to be used.
The mix should be CL3 1.5D PG 64-22 as shown on the Paving Summary Sheet.
8/8/2012 2:30 PM
12-1027300Perry
The Paving Area Summary sheet page 16 of 157 shows a total of 86,077.37 square yards of CL3 ASPH BASE 1.50D PG64-22 at a 4.5” thickness.  This calculates to 21,304.15 Tons at 110lb/SY/in of depth.  The Paving Summary sheet 17 of 157 and the bid item sheet (Bid Item 70) shows 19,584.47 Tons.  This leaves a remaining 1,719.68 Tons unaccounted for.
Please refer to sheet 31/157 for the following explanations.  The original paving quantity computation for this section assumed the raised median (14’ wide, 3” height) will be removed and  replace with a layer of asphalt base.  The typical section was later revised to keep the existing raised median and overlay with Level and Wedge.  Instead of revising the paving area summary, I deduct a quantity of 1720 tons of asphalt base to reflect the above revision.  The computation was based on 6700 feet (approx. length of raised median on the tangent section) x 14’ (raised median) / 9 = 10422 sq yd; 10422 sq yd x 3” x 110 /2000 = 1720 ton.
8/8/2012 2:30 PM
12-1026101Fayette
The plans show to install weepholes at 8-ft on center for culvert sidewalls. Are fabric wrapped drains required at weepholes?
A fabric wrapped drain is required in accordance with section 603.03.05 of the Standard Specifications.
8/1/2012 3:06 PM
12-1341318Carroll
Note 1b in Geotechnical Notes says rock drainage blanket is incidental to embankment in place.  Can you clarify?
Revised Answer:“Note 16” states that placement of the material is incidental and there is a separate bid item for drainage blanket. Please refer to the description in specification 210.01 which indicates that the bid item is for construction of embankment drainage blankets for embankment stabilization. The Geotechnical Branch’s intention is to avoid paying twice for placement of the material and the drainage blanket quantities have been separated out on the applicable cross sections.
 
8/8/2012 10:30 AM
12-2440303Pulaski
Where is the diamond grinding located on this project?
The  “PCC PAVEMENT DIAMOND GRINDING” bid item will be removed.  An addendum will be posted to the website.
8/13/2012 4:01 PM
12-2440303Pulaski
With regard to the Phase 1 note which states “construct the right shoulder and half the width of the right thru lane” , will a longitudinal joint be required at the intersection of the 10ft shoulder and the 12ft thru lane?
Yes. Install tie bars and saw a longitudinal joint at the intersection of the 10 ft shoulder and the 12 ft through lane.
8/13/2012 4:02 PM
12-1337301Jackson
The plans include 2,483 CY of Granular Embankment between US 421 and Laurel Fork. It is adjacent to the stream. The mandatory prebid minutes states “Clean/Quarried rock shall be used in all erosion and sediment controls.” The minutes clarified that this applied only at locations along the project that discharge into Laurel Fork. Since the Granular Embankment is adjacent to Laurel Fork, is it required to be clean/quarried rock?
Contrary to Section 805.10 of the Standard Specifications, Granular Embankment for this location will be required to be clean/quarried rock.
8/14/2012 1:32 PM
12-1341318Carroll
The language in the “Proposal Note” in Addendum #1 is confusing.  It states now work in the area Covered by the COE permit can be initiated until “the Receipt of the permit by the Contractor.”  It appears the COE NWP No. 14 and the KY DOW Water Quality Certification documents are both included in the project proposal.  Please explain.
The language concerning the permit was inadvertently included in Addendum #1.  KYTC has receipt of the permit; all documents have been included in the proposal and therefore all work under that permit can be begin as soon as the contractor receives their notice to proceed.
8/14/2012 3:10 PM
12-2603100Jefferson
Page 24 in the proposal says the Asphalt for the Overlay of the Approach pavement is CL4 0.50A 76-22, yet the drawing on Page 25 states it is CL4 0.38A PG 76-22.  What asphalt approach overlay material is to be used on this project CL4 0.38A PG 76-22 or CL4 0.50A PG 76-22?
CL4 0.50A PG 76-22 is to be used as the material in the asphalt approach overlay.
8/14/2012 2:27 PM
12-2955402Hickman
Can the Department please publish the existing square footages?
The existing structural steel square footages for the structures will be posted under project related information on the Construction Procurement website.  The Square Foot Figures for the structures posted is for information only and shall not be intended for bidding purposes.
8/14/2012 1:31 PM
12-1337301Jackson
Review of the two controlled fill locations Left Sta. 670+00 to 682+50 and Left Sta. 705+50 to 709+00 indicate that fill volumes are included in the embankment quantity shown on the earthwork summary-sheet R2C and supplemental earthwork spreadsheet. Can the KYTC review and verify statement provided in 8/10/12 pre-bid meeting minutes with regard to quantity of excess material to be disposed of at contractors’ responsibility?
In the final version of the pre-bid meeting minutes, the waste volume stated in the minutes will be revised as the volumes listed on the General Summary Sheet R2C do include the controlled fill volumes.
8/14/2012 2:25 PM
12-2440303Pulaski
Is there concrete pavement under the existing asphalt pavement?
The Department is unsure if there is concrete pavement under the existing asphalt pavement.
8/14/2012 9:58 AM
12-2440303Pulaski
With regard to the Phase 1 note which states “construct the right shoulder and half the width of the right thru lane” , is a tied longitudinal construction joint required at the center of the 12ft thru lane since it is being constructed in half’s?
Yes.
8/13/2012 4:02 PM
12-2440303Pulaski
Are transverse baskets required in the 11” JPC Shoulder? 
Yes.
8/13/2012 4:02 PM
12-1027300Perry
Will this project utilize Crash Cushion TY VI CT or Crash Cushion TY VI BT style systems for line no 0570 Crash Cushion Type VI-T?
The Type VI-CT shall be used due to the required MPH (45+) and ADT.
8/13/2012 10:20 AM
12-2603100Jefferson
Page 25 of the proposal references the 2008 Standard Specifications.  Is this correct?
No, page 25 should have referenced the 2012 Standard Specifications.  Any reference in this proposal to 2008 Standard Specifications is changed by this question and answer to the current 2012 Standard Specifications.
8/14/2012 2:27 PM
12-1028304Rockcastle
Per the drawing on page 23 of the proposal indicates that the Cl.3 Asph. Base 1.00D PG 64-22 is incidental to Item 20757ED Pavement Repair. There seems to be enough tonnage within bid item 00214 Cl.3 Asph. Base 1.00D PG 64-22 to cover this. Is  bid item 00214 correct?
Asphalt related to pavement repairs is incidental to pavement repair.  However, an error was discovered in that particular item and the quantity will be updated by addendum.
8/15/2012 11:15 AM
12-1337301Jackson
Is contractor required to place excess material in the waste areas/controlled fill located at Left Sta. 670+00 to 682+50 and Left Sta. 705+50 to 709+00?. 
Revised Answer:
The contractor will be required to utilize the controlled fill locations provided in the plans.  
8/14/2012 2:26 PM
12-2256413Russell
Does the following note from the Traffic Control Plan,  “No lane closures will be allowed during the following hours: US 127X Monday – Friday 7:00 am – 6:00 pm, US 127 Monday – Friday 6:00 am – 5:00 pm”, mean the Department wants the work on the above referenced job to be performed at night?
Yes, the work must be done at night or on the weekend.
8/13/2012 10:18 AM
12-1341318Carroll
Can any work which does not require full closure of the roadway be done before the start of the 90-day period?  Clearing and grubbing\tree removal, for instance?
Yes
8/14/2012 3:11 PM
12-2440303Pulaski
Can the Department please provide the existing typical section for the pavement that is to be removed?  
The Department knows what was initially constructed.  The changes in the pavement structure since the original construction are not known.
8/13/2012 4:01 PM
12-1026101Fayette
Is any more geotechnical information available besides what is shown on plan sheet S5?
The Geotechnical report can be accessed at the Division of Structure Design Website at: http://transportation.ky.gov/Structural-Design/Pages/Geotech.aspx  using S-026-2012 as the report number.  As a disclaimer, some of the stationing on the plans may vary from the stationing used in the Geotech Report, so bidders need to keep that in mind as they interpret the report. Also, on the Geotechnical report, the Subsurface data sheet shows Sheet 2 of 12, it should read Sheet 2 of 2.
8/15/2012 10:51 AM
12-2603100Jefferson
There are two, Item #08905, “CRASH CUSHION TYPE VI-CT” on the project.   This is a reusable crash cushion as indicated by the CT in the description.  My question is, could a “partially reuseable” cushion like a CRASH CUSHION TY VI CLASS BT TL2 or TL3 be bid in place for this?  Also, what would this be for a TL2 or TL3?
The standard drawing that applies is RBE-100-09.  Crash Cushion TY VI CT is a TL3 item.  No alternatives allowed as indicated in the bid item description.
8/14/2012 1:22 PM
12-1028304Rockcastle
Per the specifications for Ditching, cleaning cross drain structures is incidental. What does item 03262, Clean Pipe Structure, refere to?
An addendum will be issued to include the pipe drainage summary.  Bid item 3262 is for cleaning the 60” Pipe at Mile point 58.94
8/15/2012 11:15 AM
12-1028304Rockcastle
The bid item quantities do not match the summary sheet on proposal pages 28 and 29.  Which is correct?
The summary sheet is correct on pages 28 and 29.  An addendum to correct the bid item quantities will be posted to the website.
8/15/2012 1:06 PM
12-2653320Cumberland
What is the movement requirement for the expansion joint at end of bridge?
Design Range -30 to 120 degrees F—(1) For Abutment 1 Burkesville End 365 ft Expansion Length increment per 10 degrees F 1/4” and (2)For Abutment 2 570 ft Expansion Length increment per 10 degree F 7/16”.  Manufacturer shall place a table in the shop drawings specifying all necessary construction dimensions adjusted for temperature.  Range shall be 0-100 degrees F with 10 degree increments.
8/15/2012 1:35 PM
12-2982308Jefferson
On pages 16 and 18 of 47 in the proposal,  there is language concerning Temporary Barrier Wall.  One locations specifically calls for “CONCRETE”.  Does the wall have to be Concrete OR may Water Filled OR Steel be used?
Only Concrete Barrier will be allowed.  No alternatives to Concrete Barrier will be allowed.
8/15/2012 11:57 AM
12-1339104Hickman
Plans say metal diaphragms are incidental to precast beams and an item for armored edges is included.  Can you explain what the structural steel item covers?
The structural steel item should not have been included.  An addendum will be posted to the website.
8/15/2012 1:34 PM
12-3132314Todd
The proposal lists a bid item for pipe removal, but  on page 11 of the proposal under Item III, Construction Methods, Part C (Site Preparation) , it states that removal of existing pipe under the site preparation for the job will not be measured for payment, but incidental to the culvert pipe.  Which is correct?
Contrary to this note in the proposal, KYTC will pay for the length of pipe to be removed in linear feet.
8/15/2012 11:37 AM
12-1337301Jackson
The roadway Plans shows area for waste material more particularly the Area along M.L. station 670+00 - 682+00 Left, Is the contractor required to use this site as shown or can the contractor place waste material from this site in other sites obtained by contractor.
The contractor will be required to utilize the controlled fill locations provided in the plans.
8/15/2012 1:33 PM
12-1337301Jackson
The Geotechnical Notes  Number 15, does not allow for the use of Non - Durable shale above or below the RDZ in the Sub grade, based on the Core log information, it does not seem, that there are sufficient amounts of durable shale and/or sandstone material available for construction of the Sub grade and other areas encountered (I.e. Saturated, Unstable, ) that would require 4.0'feet of Durable Shale and/or Sandstone. Has the department generated any computations( earthwork calculations) that would show that there are sufficient amounts of Durable Shale and/or Sandstone to complete the sub grade as stated in the Geo notes
Sandstone or Durable Shale (SDI >= 95) are required in Geotechnical Notes # 6, 7, 11, and 15.  The thickness of rock required for Notes # 6, 7 and 11 is a minimum of two feet.  The thickness of rock required for subgrade in Note # 15 is two feet.  Non-durable shale may be used in the embankment below that depth, if placed according to the Standard Specifications.  Based on information used during the design phase, sufficient sandstone and durable shale quantities appear to be available for all geotechnical uses.   The Contractor will be required to stockpile the sandstone and durable shale so that sufficient quantities are available for the areas requiring this material (see Geotechnical Note # 16).
8/15/2012 1:33 PM
12-2653320Cumberland
What is in the bid item for joint sealing?
See pages 33 and 34 curb view for limits of Joint sealing and the Note in Addendum #2.
8/15/2012 1:35 PM
12-2440303Pulaski
The removal of the existing pavement paid by the cubic yard under the roadway excavation bid item. Thus, are we to assume the existing pavement to be removed is asphalt?
This is a link to the archived plans form 1970.  http://maps.kytc.ky.gov/planarc/dms96689/Pj15735.pdf  They do not show concrete.  The contractor can draw his own conclusions from these old plans but the Department is not guaranteeing that concrete pavement is not present.
8/15/2012 1:35 PM
12-2653320Cumberland
What “modular” joints are approved? 
Watson Bowman Acme: WABO Flex, SR 9 with Corrosion Resistant Aluminum Wear Plates With an “A” dimension 6” at 60 Degrees.  Any Alternate Expansion Joint must be approved by the Central Office Division of Maintenance, Bridge Maintenance Section.
8/15/2012 1:35 PM
12-1026101Fayette
Will shot rock be allowed as backfill for over-excavation under the box culvert base slab in solid/competent rock situations?
No. The culvert cannot be placed on a yielding foundation.
8/16/2012 9:07 AM
12-2955402Hickman
On page 37 in the proposal, it calls for “reinforcing bars V2” diameter”.  What is V2?
The note should have included the “#4 bar” designation.  An addendum will be posted to the website.
8/16/2012 8:08 AM
12-3132314Todd
How many inches of asphalt base is the Department planning on putting on the trenches @ the pipe crossings? 
Match existing depth but no less that 4” asphalt base material in each cut.
8/15/2012 11:37 AM
12-2983319Jefferson
Concerning the bid item “Structural Steel”, what does this entail?
All structural steel for all steel retrofits including the pin and hanger repair shall be included in the lump sum bid for "Structural Steel"
8/15/2012 12:01 PM
12-2982308Jefferson
What is included in the Structural Steel Bid Item?
“Structural Steel” includes structural steel for the sidewalk reconstruction and handrail repairs.
8/16/2012 8:52 AM
12-1337301Jackson
How will relocation of temporary concrete barrier wall be paid if used for Phase 1B construction along US 421?
Placement of temporary concrete barrier is optional for Phase IB construction along US 421.  If used, contrary to Section 509 of the Standard Specifications,  relocation of the barrier and crash cushions will be incidental to Concrete Barrier Wall Type 9T.
8/16/2012 10:06 AM
12-3347425Scott
On line number 0050 there is an extra Demobilization.  Is this correct?
No, it is not correct.  An addendum removing the extra demobilization item will be posted to the website.
8/16/2012 8:58 AM
12-1337301Jackson
Is Concrete Barrier Wall Type 9T is required for Phase IA?
Yes, Concrete Barrier Wall Type 9T is required for Phase IA and is to be placed as depicted on cross section sheets X139 to X146 during Phase IA.
8/16/2012 10:06 AM
12-1341318Carroll
If a flood or inclement weather occurs, will the ninety days be extended?
Any extension of time will be based on Standard Specification 108.07.03.
8/16/2012 9:47 AM
12-3130406Logan
Should there have been a pay item for embankment to backfill & dress around the new culvert pipes & box culvert or is this incidental?
No item is necessary.  This work will be done by the Department.
8/16/2012 8:58 AM
12-1021304Rockcastle
The Spring Box Inlet Type A is suitable for locations with over 10’ fill.  Is the flow line elevation or the depth of this box known?
The flow line elevation and the depth of box are not known.  The intention is to connect to the next median box inlet.
8/16/2012 11:34 AM
12-2330343Carter
Project phasing (p 23 of 93) states that no work will occur “6:00 a.m. Monday through 6:00 p.m. Friday”.  Is the intent for this project to be all weekend work. 
Yes, the intent is all work be on weekends except as noted in paragraph three of the project phasing.
8/16/2012 10:33 AM
12-1027300Perry
On Page 66 --- Phase III, may the assumption be drawn that the Breaking and Seating of the West bound lane would take place after saw-cutting for the edge drains and prior to the construction and capping of the edge drains?  It appears the existing reference to Eastbound in paragraph 3 (same page) should be Westbound.
Yes, this assumption is correct.
8/15/2012 4:40 PM
12-1028304Rockcastle
Is there a breakdown of the quantities for Embankment in Place?
No, there is not a breakdown of the quantities of the Embankment in Place.
8/15/2012 3:47 PM
12-2955402Hickman, Marshall
Concerning the STEEL REPAIR Bid Item, there are a total of (5) EACH included in the (1) LUMP SUM Bid Item.  On pages 47 and 48 in the proposal, the drawing appears to show that EACH Repair is only ½ width of the structure.  Is that correct? OR Does the EACH Repair go full width?
The drawing is half view.  The repair shall be the full width.  The drawing does note the sketch is symmetrical about the center.
8/15/2012 4:03 PM
12-2603100Jefferson
Can you verify exactly what material KYTC is wants for the joint replacement on page 33 of the proposal? 
Yes, use neoprene compression seal to reseal joints equal to or exceeding 1.5”.  Joint sealing for joints less than 1.5” use silicone with backer rod.
8/15/2012 4:10 PM
12-1027300Perry
Due to the extent of the required drainage and edge drain work items coupled with a probable September work order and the Seasonal and Temperature limitation for asphalt placement has/would the Department considered extending the completion date to August 1st, which would still be prior to the new school opening?
Yes, the completion date will now be July 31, 2013.
8/15/2012 4:41 PM
12-2333344Perry
Per proposal sheet 19, Contractor is required to transfer millings to the state maintenance facility. Can you please provide address for this location?
The address is: Perry County Maintenance Facility, 51 Industry Drive, Hazard, KY 41702.  For future reference, all maintenance facilities can be found here: http://transportation.ky.gov/Maintenance/Pages/Highway-Districts.aspx
8/15/2012 4:53 PM
12-1027300Perry
Concerning Phase II & Phase III, the phasing on pages 65 and 66 indicate that 3 inches of Drainage Blanket Type IV – ASPH (page 65) and 3 inches of Drainage Blanket Type II – ASPH (page 66) shall cap the Edge Drain trench in the Median.  However the detail for Pavement Edge Drain (Median) on page 41 only indicates the trench being filled with Crushed Aggregate Size No. 57, please clarify the proper material and if Asphalt Treated Drainage Blanket is correct please verify that Type II is correct for both phases and that a pay item will be added for the material.
The trench should be filled with Crushed Aggregate Size No. 57 as shown on the typical section on page 41 of the proposal.
8/15/2012 4:40 PM
12-1033322Marshall
Will there be any utilities that will impact construction?
Utilities are relocated except the sewer line that goes through the box culvert.   The sewer agency will coordinate this replacement with the  contractor.
8/15/2012 4:06 PM
12-2982308Jefferson
Is Concrete Barrier Wall be required for the “median work (7) day closure”?  If so will it be required on BOTH sides?
Yes, the concrete barrier wall will be required on both sides for the median work.
8/16/2012 1:13 PM
12-2982308Jefferson
Are Crash Cushions required for the ends of the Barrier Wall(s)?
Yes and Crash cushions shall be incidental to "Maintain and control traffic".
8/16/2012 1:13 PM
12-1341318Carroll
Will the bridge be removed before construction, or will it be used during construction?
The contractor will be removing the existing bridge; when it is removed is dependent on the contractor’s proposed schedule agreed upon by the KYTC Construction Engineer.
8/16/2012 2:51 PM
12-1028304Rockcastle
At the areas that receive cut ditch repair, is the ditching incidental to the 8” perf. pipe, or will it be paid under the ditching item?
This work will be paid under the “ditching” item.
8/16/2012 2:24 PM
12-4025202Various
Could the KYTC provide us with a drawing with regard to the pattern required for the concrete cuts?
Similar to the requirements for CLRS on roadways with Raised Pavement Markers, discontinue rumble strips at least 12” (no more than 18”) before and after the transverse joints on PCC pavement.  Install as many rumble strips as possible between adjacent transverse joints while maintaining the cycle spacing.
8/16/2012 2:55 PM
12-1341318Carroll
Planned quantities for 4” Perforated Pipe (5430 LF), 4” Non-Perforated Pipe (1250 LF), and 4” Perforated Pipe Headwalls (16 EA) do not seem to match what is in the project plans (126 LF, 52 LF and 3 EA, respectively).  Please confirm the quantities are correct.
The perforated and non-perforated pipe and headwall quantities are for the required foundation embankment benching underdrains, the transverse benching underdrains and the subgrade drainage discussed in the Geotechnical Notes.  Reference sheet R19 for details.
8/16/2012 2:37 PM
12-4025202Various
Could the KYTC provide a bid item and/or quantity for the concrete rumble strips?
The location that KYTC believes has PCC Pavement are in the project related information on the Construction Procurement website.  This for information only and shall not be intended for bidding purposes. It is estimated that approximately 1,136,995 LF of Rumbles would be installed on PCC Pavement.
8/16/2012 2:49 PM
12-2603100Jefferson
Will the old style 9-T barrier wall with 1" gaps be allowed for use on this project?
9-T barrier wall per KYTC Standard Specifications for Road and Bridge Construction and KYTC Standard Drawings shall be used.
8/16/2012 2:50 PM
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
200 Mero StreetFrankfortKY40622KY8:00 a.m.-4:30 p.m. EST, M-F(502) 564-3500rachel.mills@ky.gov?subject=Construction%20Procurement%20Website:%20Comments%20and%20Suggestionshttp://maps.google.com/maps?hl=en&q=200+mero+street+frankfort+ky&ie=UTF8&hq=&hnear=200+Mero+St,+Frankfort,+Franklin,+Kentucky+40601&gl=us&sqi=2&z=16&iwloc=A
​This page is maintained by ​Cherie.Shelton@ky.gov, who may be contacted to make corrections or changes.​​​

Follow Us