Questions and Answers

​​​​​​​​​​​​​​​​​​​​​​​

  
  
County
  
Question
Answer
  
25-1311100Franklin
Page 139 of the proposal specifies a maximum aggregate size of 0.75" for the asphalt base. However, the bid item listed is CL2 ASPH BASE 1.0D PG64-22, which is referenced again on Page 142. Could the Department clarify which aggregate size is correct?

The maximum size aggregate for the base course is 1.00”. The bid item is correct. An addendum will be issued to correct the proposal pages.
5/12/2025 9:40 AM
25-1311100Franklin
Page 142 of the proposal identifies the surface course as CL2 ASPH SURFACE 0.38D PG64-22, while the bid item specifies a 0.38B mixture. Could the Department confirm which surface mixture type is intended?

The reference in the proposal is correct. An addendum will be issued to change the bid item to CL2 ASPH SURFACE 0.38D PG64-22.
5/12/2025 9:41 AM
25-1011200Jefferson
Regarding the recent revision related to transformer bases, could the Department provide a drawing or specification for the door lock assembly so it can be shared with our manufacturer?
A specific detail drawing is not available. However, the following link provides information on the type of lock assembly typically used by the Department: https://lockdowninc.com/products/lightpolelock/
5/15/2025 9:03 AM
25-1310101Martin
Plan sheet S5 states the piles are to pre-drilled in the Foundation Layout. Can KYTC verify is this correct?
Contrary to the predrilled notation on the plan view of the foundation layout, no predrilling is anticipated to be required for the installation of the piling. All piling shall be driven to practical refusal as detailed in the notes.
5/15/2025 10:09 AM
25-1011200Jefferson
Would the Department provide typical sections for the temporary pavements?

Typical Sections for the temporary pavement widening are shown on the MOT sheets. The minimum pavement design required for temporary widening will be: 1.5” Class 2 Asphalt Surface 0.38D PG 64-22, 3.0” Class 2 Asphalt Base 1.00D PG64-22, 3.0” Class 2 Asphalt Base 1.00D PG 64-22, and 6.0” Crushed Stone Base.
5/16/2025 8:06 AM
25-1011200Jefferson
Where is the Asphalt Prime Coat bid item to be utilized?

 
The Asphalt Prime Coat is applied to the top of the Drainage Blanket layer for the interstate typical sections and on the top of the Crushed Stone Base layer for the US 42 and KY 22 typical sections
5/16/2025 8:06 AM
25-1011200Jefferson
Will the Department coordinate traffic closures and etcetera on other significant nearby projects, such as River Road and Zorn Avenue/I-71 Interchange, to minimize traffic impacts to this project?
Every effort will be made to coordinate traffic control among all the projects. The Department will not impose restrictions on other projects solely to accommodate this project.
5/16/2025 10:16 AM
25-2974323Jefferson
Could the Department provide the detail drawings, showing the limits of work, that is referred to in the Special Note for Preventive Maintenance?

The detailed drawing showing the limits of the preventive maintenance work has been posted on Project Related Information.
5/16/2025 12:32 PM
25-4301201Fayette
Will material that is used for wedging drop offs be paid for?
The Department will measure and pay for any Crushed Stone Base used for wedging drop-offs that is also subsequently used for, and final placement is within, the proposed 9-inch layer of Crushed Stone Base within the Widening & Full Depth Shoulders areas. The Department will NOT pay for any Crushed Stone Base or any other material that is only used for wedging drop-offs.
5/16/2025 3:01 PM
25-4301201Fayette
There is a section of specifications in the proposal from HDR / LFUCG.  Which apply to the project, these or KYTC Standard Specifications?
The specifications included in the proposal from HDR / LFUCG only apply to the proposed sanitary sewer work. The Department’s Standard Specifications apply to all other proposed work.
5/16/2025 3:04 PM
25-1011200Jefferson
Would the Department allow nightly full closures of the I-71 SB ramp to I-264 WB ramp and I-71 NB to safely perform overhead bridge construction activities? 

The Department will allow a total of five (5) nightly closures of the ramps beneath the bridge: two (2) nights for removal, one (1) for beam setting, and two (2) for concrete pours (deck and wall). The Contractor must submit a detailed detour signing plan for approval, which may be extensive. The closure shall begin no earlier than 8:00 pm and be completely removed from the roadway by 6:00 am. All times are local time. The disincentive schedule listed in note 18 on plan sheet R164 will apply to these closures.
5/16/2025 3:11 PM
25-1011200Jefferson
During Phase 2 construction of the I-71 flyover, will the Department permit a single-lane configuration like Phase 1?

 
Maintaining two lanes of traffic during Phase 5A is preferred, given the ramp’s average daily traffic (ADT) of approximately 9,000 vehicles (roughly 900 during the design hourly volume). However, any proposed deviations should be supported with a traffic analysis and submitted for Department review and approval.
5/16/2025 3:12 PM
25-4301201Fayette
Are turn lanes required to be maintained throughout the project, or is maintaining two through lanes in each direction sufficient?

Turn lanes should be maintained throughout the project as shown on the Maintenance of Traffic plan sheets, unless otherwise approved by the Engineer. There are certain phases when certain turning lanes will be closed (for example, the turn lanes for traffic turning from Athens-Boonesboro onto Aphids Way will be closed while Aphids Way is closed for reconstructing Aphids Way in Phases 1 & 2). See the Maintenance of Traffic plan sheets for other instances of turn lanes that may be closed during specific traffic control phases. There may be other times when a short-term closure of a specific turn lane may be allowed to perform specific work. Such closures shall be coordinated with, and approved by, the Engineer.
5/16/2025 3:15 PM
25-4301201Fayette
Is there any flow information available for the force main that must be relocated? 
No flow information was provided by LFUCG during development of the sanitary sewer plans. Force main flows are supplied by the pump station at 5301 Athens Boonesboro Road. Depending on dates and times, LFUCG may be able to manage flows with adequate wet well capacity to accommodate necessary tie-ins. The Contractor shall coordinate with LFUCG for operational impacts.
5/16/2025 3:17 PM
25-1011200Jefferson
Can the Department provide existing structure plans?
Yes. The existing plans have been posted in Project Related Information.
5/19/2025 9:45 AM
25-2975327Jefferson
It appears new asphalt has been placed over the joint. Has anything foreign been placed in the joint to hold the asphalt in place?
In southbound lanes, the sliding plate is still in place and is loose. In the northbound lanes, portions of the sliding plate have been cut out. Timber formwork or backer rod is holding the asphalt in place.
5/19/2025 2:33 PM
25-2975327Jefferson
Is the new joint set at the same elevation as the asphalt or the original bridge deck?
The new joint is set at same elevation as the asphalt/overlay.
5/19/2025 2:34 PM
25-2167409Nelson
Can the Department provide additional information on the blow ups for FD05 090 031E 016-021?
The Department will not provide any additional information regarding depth or location of blowups. Milling is intended to plane the existing surface where blowups have occurred. Normal leveling may or may not be required upon completion of the milling.
5/19/2025 4:00 PM
25-4301201Fayette
How will removal of existing striping be paid?

As noted on proposal page 272 of 605, pavement marking removal will be incidental to the Maintain & Control Traffic bid item. The exception to this will be the turn lane arrows along the Squires Road approach. Squires Road was recently resurfaced and the turn arrows along Squires Road may need to be updated to match the final RCUT design. As noted on proposal page 307 of 605, a quantity for Pavement Marking Removal has been included to remove the existing turn lane markings along Squires Road and replace them as shown on the RCUT Pavement Markings plan sheet.
5/20/2025 8:07 AM
25-2220319Scott
On page 20 of the proposal, there is a special note for Shoulder Preparation.  In this note, it states the intent is to prepare the shoulders for the shoulder resurfacing. Will the Department require the Contractor to build up shoulder?

The Special Note for Shoulder Preparation on page 20 of the proposal was included in error and does not apply to this project.
5/20/2025 8:49 AM
25-2221318Scott
On page 16 of the proposal, there is a special note for Shoulder Preparation.  In this note, it states the intent is to prepare the shoulders for the shoulder resurfacing. Will the Department require the Contractor to build up shoulder?

The Special Note for Shoulder Preparation on page 16 of the proposal was included in error and does not apply to this project.
5/20/2025 8:50 AM
25-1011200Jefferson
Will the Department allow more than 5 nights of I-71 ramp closures?
The Department will consider requests to close the ramp for additional days, however, any proposed deviations from the Maintenance of Traffic plan should be supported with analysis and submitted for review and approval by the Engineer.
5/20/2025 9:15 AM
25-1011200Jefferson
At cross section Station 5132+50 Rt., it appears rock removal and excavation will be required behind the wall for construction of the moment slab and wall. These items are not shown in the cross sections. Additionally, backfill will be necessary behind the wall, and there is a ditch referenced that lacks detail. Can applicable details, quantities, and pay items for this work be provided?

The rock behind the wall will need to be removed by continuing the 0.25:1 presplit to the bottom of subgrade and will be paid for under the unit cost bid for Roadway Excavation (bid code 02200). Backfill will be paid as Granular Embankment (bid code 02223) behind the wall or a similar aggregate size can be utilized if agreed to by the Engineer. The ditch at the top of the backfill shall be a minimum of six inches below the top of the wall and graded to drain. Note: the roadway excavation quantities for this were already calculated as part of the cross section although not shown that way. The overall quantity not shown is miniscule compared to the total excavation on the project.
5/20/2025 9:18 AM
25-1011200Jefferson
Will the Department consider extending the closure limitations of twenty(20) minutes for blasting operations?
No, the Department will not extend the twenty (20) minute closure limit for blasting operations.
5/20/2025 11:50 AM
25-1011200Jefferson
Will the Department pay for additional MOT needed to process the work per current phasing? For example, additional temp barrier wall required for bore pit construction and construction of center pier at the US 42 bridge.

If a bid item is in the contract and it is deemed necessary by the Engineer for construction operations, the Department will pay for said items, barrier wall, signs, etc.
5/20/2025 12:42 PM
25-1011200Jefferson
Will the Department pay for additional temporary crash cushions for gate access on mainline?

If the Contractor chooses to put additional locations for ingress/egress, the Department will NOT pay for the crash cushions.
5/20/2025 2:08 PM
25-1311100Franklin
Is the unsuitable excavation item a calculated quantity for undercut that will take place on the project or is the item included to cover any potential undercuts in the earthwork phase?

The geotechnical report for the project area has been posted in Project Related Information. Unsuitable excavation will only be used in areas where the subgrade fails to pass a proof roll under the proposed pavements.
5/21/2025 8:36 AM
25-1311100Franklin
The unclassified excavation bid item quantity appears to be substantially low. Can additional earthwork calculation information or clarification be provided?

The Engineer completed the earthwork calculations in CAD by comparing the finished grade surface to the existing surface. The proposed pavement section was deducted from this amount. Subsequently, the topsoil CY to be placed was deducted from the volumetric amount as well. It is intended the Contractor will be able to reuse the material cut on-site.
5/21/2025 8:37 AM
25-1311100Franklin
The borrow excavation bid item quantity appears to be substantially low. Can additional earthwork calculation information or clarification be provided?

The Engineer completed the earthwork calculations in CAD by comparing the finished grade surface to the existing surface. The proposed pavement section was deducted from this amount. Subsequently, the topsoil CY to be placed was deducted from the volumetric amount as well. Borrow excavation will be material needed from OUTSIDE the proposed project limits.
5/21/2025 8:37 AM
25-1311100Franklin
The topsoiling-4 in thick obtained on site bid item quantity appears to be low. Can additional earthwork calculation information or clarification be provided?

The Bidder shall refer to the geotechnical report posted in Project Related Information. The report indicates that up to 6 inches of topsoil is available in 12 of the 14 borings. The Contractor shall make every effort to strip the topsoil within the project limits and stockpile it for reuse, as described in Item T-905. An addendum will be issued to increase the plan quantity.
5/21/2025 8:38 AM
25-1311100Franklin
Can asphalt depths be provided for the asphalt pavement removal bid item?
The Contractor shall refer to the geotechnical report for boring information identifying the depths of the asphalt pavement section. The Contractor shall also refer to the project plans for the final depth of pavement removal.
5/21/2025 8:39 AM
25-1311100Franklin
Can gravel entrance depths be provided for the remove gravel entrance bid item?

No geotechnical borings were conducted in the area of the gravel entrance to be removed. The Contractor is encouraged to conduct a site visit to determine the depth of the gravel roadway. The design intent is to remove a portion of the gravel roadway to complete the grading and drainage as shown on Sheet CG-102.
5/21/2025 8:40 AM
25-1011200Jefferson
Due to the nature of the work and blasting (e.g., presplitting), it is anticipated that insufficient appropriately sized material will be available for rock roadbed at the appropriate time considering there is limited space on-site to process the material. Will the Department compensate for any resulting shortage under the current pay item for Crushed Aggregate No. 2?
If there is a shortage of suitable material due to blasting and on-site constraints, the Department will address it through a change order. Any necessary quantity of Crushed Aggregate No. 2 beyond what is available from site-generated material will be paid at the contract unit bid price.
5/21/2025 9:30 AM
25-1011200Jefferson
Would the Department consider reducing or eliminating liquidated damages as related to blasting operations?
The Liquidated Damages, as they are related to blasting, will be amended. For this purpose, the disincentive schedule listed in note 18 on plan sheet R164 - “A DISINCENTIVE FEE WILL BE CHARGED FOR FAILURE TO REOPEN I-264 WITHIN 20 MINUTES, AS NOTED BELOW:” will be reduced in the following manner for the failure to reopen I-264 within 20 minutes: 20 TO 40 MINUTES - $10,000, Reduced to $5,000. 40 TO 60 MINUTES - $20,000, Reduced to $10,000. 60 TO 80 MINUTES - $40,000, Reduced to $20,000. AFTER 80 MINUTES - $1,000 PER MINUTE.
5/21/2025 9:35 AM
25-1311100Franklin
The proposed sanitary sewer lines for the project appear to be gravity sewer lines, however the bid item references force main. Can the Department clarify the sanitary sewer line bid items?

The sanitary sewer lines are gravity sewer lines. An addendum will be issued to revise the bid items.
5/21/2025 9:45 AM
25-1011200Jefferson
Will "Higher Fine Zone" be utilized?

Yes, the Department will allow the use of “Higher Fine Zones” on this project.
5/21/2025 9:46 AM
25-4301201Fayette
How will the steel encasement for the signal poles be paid?
The steel encasement for the signal poles is incidental to the pole base.
5/21/2025 12:56 PM
25-4301201Fayette
What are the specifications for the steel encasement for the signal poles?
The specifications for the steel encasement are on proposal page 402 of 605.
5/21/2025 12:57 PM
25-4301201Fayette
Who will be responsible for the maintenance of lighting during the project? 

The Contractor shall coordinate with the local utility on maintaining the utility owned roadway lighting.
5/21/2025 12:58 PM
25-4301201Fayette
Who will provide the anchor bolts for the new light pole bases? 
The Contractor shall provide the anchor bolts and coordinate with the local utility on the proper bolt circle for the new light pole bases.
5/21/2025 12:58 PM
25-4301201Fayette
Can the Department add clarification to the Temp Signal 2 Phase bid item?
There is a total quantity of 6 EACH of the bid item Temp Signal 2 Phase and there are two different purposes for the Temp Signal 2 Phase bid item. One purpose is for the potential use at the existing and proposed signalized intersections during construction to aid with Maintenance of Traffic IF the permanent mast arm signals are not available for installation. A quantity of 5 EACH is listed within the Traffic Signal Estimate of Quantities on proposal page 396 of 605 and on this same page, under the heading MOT Temp Signal Requirements, there are notes that cover these Temp Signals. Since these 5 Temp Signals will only have the potential to be used at the existing and proposed signalized intersections while waiting for the permanent mast arm signals to be completed, there should not be any reason for relocating these Temp Signals. The second purpose for the Temp Signal 2 Phase bid item is for the use of a portal Temp Signal 2 Phase during the construction of the tie-in of the realigned Aphids Way. During the tie-in construction, one lane of alternating traffic will have to be utilized, so a quantity of 1 EACH of the bid item Temp Signal 2 Phase has been established under the Roadway category to assist with Maintenance of Traffic during this work. There could be other uses for the portal Temp Signal 2 Phase; however, the portal Temp Signal 2 Phase shall only be measured once for payment, regardless of how many times the portable Temp Signal 2 Phase is set, reset, removed, and/or relocated during the duration of the project.
5/21/2025 1:00 PM