| Jefferson County | |
I-65 Central Corridor  | A two-mile section of southbound I-65 reopened to two lanes of traffic on Sunday, June 29, from University Boulevard to I-264. I-65 North remains closed from downtown Louisville (Jefferson Street) to I-264, while I-65 South remains closed from downtown Louisville (Jefferson Street) to University Boulevard through Friday, July 31. Following the closure, I-65 will reopen to two lanes in each direction as construction continues. THROUGH TRAFFIC - The signed detour is to I-264 (Georgia Davis Powers Expressway) on the west side of Louisville.
- The signed detour is the shortest distance, utilizes roadways with the most capacity, and creates the least traffic impacts.
- The route takes through traffic around the closure, minimizing impacts to local traffic.
LOCAL TRAFFIC
- Local detours include many different beginning and end points.
- Mapping apps will help drivers find the best route at their time of travel.
- The Kentucky Transportation Cabinet is an Agency Partner with Waze, a free GPS navigation app with real-time traffic updates.
DOWNTOWN ACCESS - Downtown is accessed via the Jefferson Street exit from southbound I-65.;;
- Traffic leaving downtown can use the East Liberty ramp to access northbound I-65, I-64 and I-71.
- I-64 ramps at Third Street and Ninth Street also provide access to and from downtown.
Additional information related to the I-65 Central Corridor project can be found online at i65centralcorridor.com.
|
U.S. 31E (Main Street) *Main Remade* | TRAFFIC ADVISORY: Contract crews will complete permanent pavement striping on the north side of U.S. 31E (Main Street) beginning the week of Monday, July 6. Once the striping is complete, traffic will be shifted to the north side of the roadway in its permanent configuration. After traffic has been shifted, most intersections along the corridor will temporarily operate as all-way stops using stop signs while crews transfer power to the new traffic signals and remove the existing signal equipment. The intersections of Second Street at Main Street and Second Street at Market Street will remain signalized during this phase. Contract crews will then complete the remaining permanent striping on the south side of U.S. 31E (Main Street). Although all pavement markings will be in place at that point, traffic control devices will continue to prohibit eastbound traffic until the new traffic signals have been energized. Once power has been connected to all new traffic signals, U.S. 31E (Main Street) will open to its new two-way traffic configuration. The anticipated completion of this work is by the end of July, weather permitting. Motorists should expect changing traffic patterns throughout this work. Drivers are encouraged to follow posted signage, obey temporary traffic control devices and stop signs, and allow extra travel time through the work zone. |
| U.S. 60 (Shelbyville Road) | Traffic Impacts: Daily lane closures are possible. Date/Time: Daily. Project Limits: U.S. 60 (Shelbyville Road) between KY 2861 (Eastwood Cutoff Road) and Rockcrest Way. Type of work: Widening and improvement project. Other Details: Please visit the project webpage for additional information. |
| U.S. 60A (Berry Boulevard) and KY 1931 (7th Street Road) Intersection | Traffic Impacts: Closure of the intersection. Date/Time: Through noon on Monday, July 13. Type of Work: The closure is necessary out of an abundance of caution due to anticipated heavy rainfall. Once weather conditions improve, crews will begin repairs to the pump station located near the railroad viaduct. |
| I-64 East and West | Traffic Impacts: No traffic impacts to I-64 travel; however, periodic lane and shoulder closures on surface streets beneath the interstate are possible. Date/Time: Daily/nightly. Project Limits: I-64 East and West from Second Street in downtown Louisville to the I-64/I-264 interchange near the Sherman Minton Bridge in west Louisville. Type of Work: Preventative maintenance project. Other Details: ******Overnight single lane closures and shoulder closures will NOT occur during the two-month closure of I-65 from downtown Louisville to the Watterson Expressway (I-264) as part of the I-65 Central Corridor project. Work will occur beneath the bridge structures through Aug. 1, limiting impacts to interstate travel during the planned two-month closure of I-65. The majority of construction activities will take place beneath the bridge structures, limiting impacts to interstate traffic.****** |
| I-64 East and West | Traffic Impacts: Lane closures are possible as final items as part of the project are underway. Date/Time: Daily/nightly. Project Limits: I-64 East and West at mile point 11.799, near Exit 10 (Cannons Lane) on I-64 West, and near Exit 12 to I-264 (Watterson Expressway) on I-64 East. Type of Work: Bridge replacement project. Other Details: *Project announcement press release |
I-65 South Ramp to I-64 West I-65 North Ramp to I-64 West
| Traffic Impacts: Ramp Closures Date/Time: 7/22/2026 07:00 PM through 7/23/2026 07:00 AM Project Limits: I-65 South Ramp to I-64 West and I-65 North Ramp to I-64 West Type of Work: In-Place Patching Other Details: Signage will be placed to alert drivers of the closure. Use WAZE to navigate around the closure.
|
| I-65 South (John F. Kennedy Memorial Bridge) | The work as part of the expansion joint replacement project is nearing completion, with final pavement markings and minor remaining work left to complete the project. Following the reopening of I-65 as part of the I-65 Central Corridor Project on Aug. 1, a final short-term closure of I-65 South (Kennedy Bridge) will be scheduled to complete the remaining work. Additional details will be announced once scheduled. |
| I-71 Widening and Improvement Project | **Traffic impacts available here.** |
| U.S. 150 (East Broadway) | *Signal and median installations are underway and lane closures are possible on the east side of Barrett Avenue at Broadway and on Broadway between 9th Street and Barrett Avenue from 9 a.m. to 3p.m. daily. Traffic Impacts: Lane closures are possible. Date/Time: Daily/nightly. Project Limits: U.S. 150 (East Broadway) between South 9th Street and Baxter Avenue. Type of Work: Highway safety improvement project. Other Details: Preliminary work is underway. Additional details on traffic impacts and project updates will be shared when available. |
| I-264/U.S. 42 (Brownsboro Road) Improvement Project | **Traffic impacts available here.** |
| KY 864 (Logan Street/Shelby Street) | Traffic Impacts: Sidewalk and lane closures are possible. Date/Time: Daily and nightly. Project Limits: Between Goss Avenue and East Gray Street. Type of Work: One-way to two-way conversion of the roadway. Other Details: Link - Project Webpage |
| KY 1819 (Billtown Road) | *The KY 1819 (Billtown Road) project is substantially complete with final items remaining. Lane closures and delays are possible while final items are underway. Traffic Impacts: Lane closures and delays are possible. Date/Time: Daily – 9 a.m. to 4 p.m. Project Limits: Three sections of KY 1819 (Billtown Road): - Easum Road through Mary Dell Lane
- Michael Edward Drive through Fairground Road
- Shady Acres Lane through Colonnades Place
Type of Work: Reconstruction of KY 1819 (Billtown Road) from North of Colonnades Place to south of Easum Road with new traffic signals, signal optimization, turn lanes, storage lanes, etc. (varying by intersection based on existing conditions and future traffic projections). Other Details: The reconstruction project is substantially complete with final punchlist items remaining. *Project webpage |
| KY 1932 (Chenoweth Lane) | Traffic Impacts: Lane closures and delays are possible. Date/Time: Daily from 9 a.m. to 3 p.m. Project Limits: KY 1932 (Chenoweth Lane) between U.S. 60 (Shelbyville Road) and U.S. 42 (Brownsboro Road). Type of Work: Construction activities include roadway modifications, sidewalk and pedestrian crossing improvements, and drainage enhancements designed to reduce flooding and improve overall travel conditions in the area. Other Details: This project is expected to be completed by the Fall of 2026. Motorists will be directed through the work zone via flagging operations. Drivers should heed flagging operations and use caution when traveling through the work zone. |
| KY 2054 (Algonquin Parkway) | Traffic Impacts: Lane closures and delays are possible. Date/Time: Daily/nightly. Project Limits: KY 2054 (Algonquin Pkwy) between 40th Street (mile point 0.0) and Winkler Avenue (mile point 3.3). Type of Work: Resurfacing and improvement project. Other Details: KY 2054 (Algonquin Pkwy) between 40th Street (mile point 0.0) and Winkler Avenue (mile point 3.3) is currently four travel lanes. The reconfiguration project consists of converting the roadway to two travel lanes with the addition of a two-way left-turn lane (TWLTL). Additional improvements include installing new signage & pavement markings, rebuilding traffic signals, and constructing concrete sidewalk ramps & median modifications. The project is expected to be completed by the Fall of 2026. |
| *Various Locations | Traffic Impacts: Lane closures and delays are possible as part of a mobile operation. Date/Time: Daily – 8 p.m. to 5 a.m. Type of Work: Pavement striping. Other Details: Motorists should provide plenty of space to crews displaying "WET PAINT" signage and be observant of slowed vehicles while traveling through the work zone. |
| *Various locations along I-265/KY 841 (Gene Snyder Freeway) | Traffic Impacts: Shoulder closures are possible. Project Limits: KY 841 and I-265 within Jefferson County. Date/Time: Daily/nightly. Type of Work: Staking poles for bases of new signage. |
| | |
| Bullitt County | |
| KY 245 (Clermont Road) | Traffic Impacts: Daily lane closures are possible. Date/Time: Daily. Project Limits: KY 245 (Clermont Road) between the I-65 interchange and Happy Hollow Road. Type of Work: Widening and improvement project. Other Details: Please visit the project webpage for additional information. |
| KY 1526 (Brooks Hill Road) | Traffic Impacts: Lane closure. Date/Time: Beginning Monday, July 20, through Monday, Aug. 3. Project Limits: KY 1526 (Brooks Hill Road) between Holsclaw Hill Road and Brook View Road. Type of Work: Slope stabilization on the hill at mile point 9.68. Other Details: Motorists will be directed through the work zone via automated flagger assistance devices. Drivers should heed the automated flagger assistance devices, reduce speeds, and use caution when traveling through the work zone. |
| | |
| Franklin County | |
| KY 12 (Flat Creek Road) | Traffic Impacts: N/A. Date/Time: Beginning Aug. 11, through the Fall of 2026. Project Limits: KY 12 bridge over Flat Creek at mile point 12.46 (at the Franklin/Henry County line). Type of Work: Bridge replacement project. Other Details: Traffic will be maintained on the existing bridge until construction has been completed on the replacement bridge. |
| U.S. 60 (Capital Avenue) | Traffic Impacts: Weekend closure of the bridge. Date/Time: Beginning Friday, July 17, at 7 p.m., through Monday, July 20, at 5 a.m. Project Limits: U.S. 60 (Capital Avenue) bridge over the Kentucky River. Type of Work: Bridge maintenance project. Detour: During the weekend closure, motorists should follow the signed detour route via KY 420 (Old Lawrenceburg Road, KY 676 (East-West Connector), KY 1659 (Martin Luther King Jr. Boulevard), and U.S. 60 (East Main Street) before reconnecting with U.S. 60 (Capital Avenue). Other Details: The approximately $925,000 project will include placement of a latex concrete overlay, bridge rail repairs, pier maintenance, and sidewalk repairs. The improvements are designed to preserve the structure and extend its service life. The bridge was originally constructed in 1938. Additional weekend closures will be announced as work progresses. In addition to the weekend bridge closures, traffic on the bridge will be reduced from three lanes to two lanes during construction. Sidewalk closures will also be in place periodically throughout the project, but one sidewalk will remain open during construction. Additional information regarding traffic impacts will be shared when available. |
| I-64 East and West | TRAFFIC ADVISORY: The ramp closures listed below are necessary for contract crews to perform asphalt paving operations. - Beginning Wednesday, July 15, at 8 p.m., through Thursday, July 16, at 12 a.m.
- Closure of the I-64 East off-ramp to U.S. 127 North at Exit 53B
- Beginning Wednesday, July 15, at 12 a.m., through Thursday, July 16, at 6 a.m.
- Closure of the I-64 East off-ramp to U.S. 60 (Versailles Road) at Exit 58
- Beginning Thursday, July 16, at 8 p.m., through Friday, July 17, at 6 a.m.
- Closure of the I-64 East on-ramp from U.S. 127
Traffic Impacts: Lane closures and traffic shifts, and delays are possible. Date/Time: Daily/nightly beginning Thursday, Sept. 4. Project Limits: I-64 East and West, between the Frankfort exits (mile markers 53 and 58). Type of Work: The I-64 improvement project, between the Frankfort exits (mile markers 53 and 58), includes the milling and removal of the existing asphalt surface followed by resurfacing with new asphalt pavement. Other improvements to the 5-mile corridor include bridge repairs and bridge crash wall repairs. Other Details: - U.S. 60 (Versailles Road):
U.S. 60 (Versailles Road) will be reduced to one lane in each direction under the I-64 overpass bridge nightly from 9 p.m. to 6 a.m. beginning Monday, Sept. 15, 2025.
**Overnight alternating lane closures will occur nightly from 7 p.m. to 6 a.m. beginning Monday, July 6, through Tuesday, July 21, on I-64 East between mile markers 53 and 58 (between U.S. 127 and U.S. 60). The overnight alternating lane closures are necessary for contract crews to perform asphalt paving operations. Motorists are advised to follow all lane closure restrictions, use caution when traveling through the work zone, and plan for additional travel time. |
| U.S. 127/Vandalay Drive Intersection | Traffic Impacts: Lane closures and traffic shifts are possible. Date/Time: Daily from 9 a.m. to 3 p.m. Project Limits: U.S. 127/Vandalay Drive intersection. Type of Work: The scope of the project includes constructing a new roundabout at the intersection of Vandalay Drive and Westridge Drive; extending Vandalay Drive to Limestone Drive to create a direct connection to KY 676 (East-West Connector); extending Vandalay Drive to U.S. 127 near the I-64/U.S. 127 interchange; and adding dual receiving lanes to improve left-turn movements from U.S. 127 onto Westridge Drive. Other Details: The project is scheduled to be completed by the summer of 2026. |
| | |
| Oldham County | |
| KY 393/KY 146/Allen Lane | Traffic Impacts: Lane closures are possible. Date/Time: Daily/nightly. Type of Work: Major infrastructure improvement project along KY 393, KY 146, and Allen Lane. The project includes reconstruction and realignment of KY 393 north of the I-71 interchange to KY 146 and Allen Lane from the Commerce Parkway/Ernie Harris Parkway intersection to KY 146, and the construction of two rail-over-road bridges to replace existing at-grade railroad crossings. Additional improvements as part of the project include: - Widening and reconstruction of KY 393, including expanded travel lanes and turn lanes - Construction of a new KY 393 extension connecting to KY 146 - Widening and reconfiguration of Allen Lane from Commerce Parkway to KY 146 - Intersection improvements at Ernie Harris Parkway and Spring House Pike - Addition of dedicated turn lanes at KY 146 and Allen Lane Other Details: Motorists are encouraged to slow down, remain alert, and follow all work zone signage and flagging personnel. Drivers should also expect changing conditions throughout construction. Additional project information and traffic updates will be provided as work progresses. |
| | |
| Spencer County | *Routine Maintenance* |
| | |
| Shelby County | |
| U.S. 60 East (Main Street) | Traffic Impacts: Closure of the U.S. 60 East (Main Street) bridge. Date/Time: Beginning Monday, July 6, through Dec. 18. Project Limits: U.S. 60 East (Main Street) Bridge over Clear Creek. Type of Work: Bridge replacement project. Other Details: To ensure construction can be completed safely and efficiently, a closure of the U.S. 60 East (Main Street) bridge is scheduled to begin Monday, July 6. During the construction of the new bridge, two-way traffic will be shifted to the U.S. 60 West (Washington Street) bridge. The newly constructed bridge is expected to open to traffic on Friday, Dec. 18. |
| U.S. 60 (Shelbyville Road) | Traffic Impacts: Daily lane closures. Date/Time: Daily from 9 a.m. to 3 p.m. beginning Monday, July 13, through Friday, July 17. Project Limits: Westbound U.S. 60 (Shelbyville Road) between KY 55 (Freedoms Way) and Ardmore Crossing Drive Type of Work: The daily lane closures are necessary for crews to perform milling and paving operations as part of permitted work associated with a commercial development. As part of the work, a turn lane is being constructed on westbound U.S. 60 (Shelbyville Road) between KY 55 (Freedoms Way) and Ardmore Crossing Drive. Detour: A signed detour will direct motorists via Midland Industrial Boulevard to Discovery Boulevard, where they will reconnect with U.S. 60 (Shelbyville Road). Drivers should follow posted signage, allow extra travel time, and use caution while traveling through the work zone. |
| I-64 Widening and Improvement Project | **Traffic impacts available here.** |
| KY 55X/KY 43 | Traffic Impacts: Daily lane closures are possible. Date/Time: Daily from 9 a.m. to 3 p.m. beginning on or after Monday, March 2. Project Limits: Intersection of KY 55X and KY 43. Type of Work: Intersection improvement project. Intersection improvements include upgrading the existing traffic signal, adding right-turn lanes on all approaches, and constructing dedicated left-turn lanes for northbound and southbound KY 55X. These enhancements will improve traffic flow, reduce delays, and enhance safety for motorists traveling through the corridor. Other Details: The project completion date anticipated for late this Summer. Additional project information is available online. |
| | |
| Henry County | *Routine Maintenance* |
| | |
| Trimble County | |
| *Various Locations | Traffic Impacts: Lane closures and delays possible as part of a mobile operation. Date/Time: Daily – 7 a.m. to 9 p.m. Type of Work: Pavement striping. Other Details: Motorists should provide plenty of space to crews displaying "WET PAINT" signage and be observant of slowed vehicles while traveling through the work zone.
|