U.S. 25E Concrete Intersection Project will Begin Monday, June 21 in Bell County

MANCHESTER, Ky. (June 15, 2021) The Kentucky Transportation Cabinet (KYTC) advises motorists that a concrete intersection project on U.S. 25E (mile point 14.2) in Bell County will begin Monday, June 21.

The project is located at the intersection of U.S. 25E and KY 2015/Tennessee Avenue in Pineville. It consists of removing existing asphalt pavement and placing new concrete pavement. 

U.S. 25E will be reduced to one lane in each direction for the duration of the project. Left turns will be restricted from U.S. 25E onto KY 2015/Tennessee Avenue and left turns will be restricted from KY 2015/Tennessee Avenue onto U.S. 25E. 

KY 2015 traffic will be detoured for several weeks during this project. Currently, the KY 2015 detour is scheduled from Tuesday, July 6 to Monday, August 2, 2021. Traffic will be in normal operations for the July 4 holiday weekend. 

The project is expected to conclude on Thursday, September 30.

KYTC asks motorists to be aware of the work zone, expect delays, and to utilize safe driving habits when traveling through the area.

The date, time, and duration of work may be adjusted if inclement weather or other unforeseen delays occur. Motorists can access travel and traffic conditions at http://goky.ky.gov or contribute their reports at www.waze.com or via the Waze mobile application. You can also get traffic information for District 11 counties at www.facebook.com/KYTCDistrict11 or by following us on Twitter at www.twitter.com/KYTCDistrict11