Bridge Inspections Scheduled on U.S. 119 in Harlan County for Monday, November 8 and Tuesday, November 9 

MANCHESTER, Ky. (November 3, 2021) – The Kentucky Transportation Cabinet advises motorists that bridge inspections will take place on U.S. 119 in Harlan County on Monday, November 8 and Tuesday November 9.

The work schedule is listed below:

  • On Monday, November 8, traffic on U.S. 119 at mile point 22.4 will be reduced to one lane, and maintained by a flagger from 9 a.m. to 11 a.m.

 

  • On Monday, November 8, traffic on U.S. 119 at mile point 27.2 will be reduced to one lane, and maintained by a flagger from 12 p.m. to 2 p.m.

     
  • On Monday, November 8, traffic on U.S. 119 at mile point 27.7 will be reduced to one lane, and maintained by a flagger from 2:30 p.m. to 4:30 p.m.

     
  • On Tuesday, November 9, traffic on U.S. 119 at mile point 35.6 will be reduced to one lane, and one northbound lane will be open from 9 a.m. to 12 p.m.

     
  • On Tuesday, November 9, traffic on U.S. 119 at mile point 35.6 will be reduced to one lane, and one southbound lane will be open from 1 p.m. to 4 p.m.

The lane restrictions will allow crews to perform a detailed inspection of the bridge structure. Engineers will be using a Snooper Truck to access the deck substructure on the bridge.

Motorists are advised to use caution during this period and be aware of signage, road crews and other drivers. The work is dependent on weather conditions.

The date, time, and duration of work may be adjusted if inclement weather or other unforeseen delays occur. Motorists can access travel and traffic conditions at http://goky.ky.gov or contribute their own reports at www.waze.com or via the Waze mobile application. You can also get traffic information for District 11 counties at www.facebook.com/KYTCDistrict11 or by following us on Twitter at www.twitter.com/KYTCDistrict11


35111/10/2021Bridge Inspections Scheduled on U.S. 119 in Harlan County for Monday, November 8 and Tuesday, November 9 /DistrictEleven/Pages/PressReleasePage.aspx?&FilterField1=ID&FilterValue1=?
 

Cross Drain Operations Start Wednesday, November 3 on KY 904 in Whitley County 

MANCHESTER, Ky. (November 2, 2021) The Kentucky Transportation Cabinet (KYTC) advises motorists that cross drain operations start Wednesday, November 3 on KY 904 (mile point 10.5) in Whitley County.

The roadway will be closed to through traffic on Wednesday, November 3 from 7 a.m. to 6 p.m. each day.

KYTC asks motorists to be aware of the work zone, expect delays, and to utilize safe driving habits when traveling through the area.

The date, time, and duration of work may be adjusted if inclement weather or other unforeseen delays occur. Motorists can access travel and traffic conditions at http://goky.ky.gov or contribute their reports at www.waze.com or via the Waze mobile application. You can also get traffic information for District 11 counties at www.facebook.com/KYTCDistrict11 or by following us on Twitter at www.twitter.com/KYTCDistrict11


35011/3/2021Cross Drain Operations Start Wednesday, November 3 on KY 904 in Whitley County /DistrictEleven/Pages/PressReleasePage.aspx?&FilterField1=ID&FilterValue1=?
 

Bridge construction to begin Monday, November 1 on Dog Branch School Road in Laurel County


MANCHESTER, Ky. (October 29, 2021) The Kentucky Transportation Cabinet (KYTC) advises motorists that Dog Branch School Road (CR 1341) in Laurel County between the intersection with White Oak Road and intersection with Dog Branch Road will be closed to through traffic starting at 8 a.m. Monday, November 1 until Friday, January 14.   

The road closure is necessary for bridge construction.

KYTC asks motorists to be aware of the work zone, expect delays, and to utilize safe driving habits when traveling through the area.

The date, time, and duration of work may be adjusted if inclement weather or other unforeseen delays occur. Motorists can access travel and traffic conditions at http://goky.ky.gov or contribute their reports at www.waze.com or via the Waze mobile application. You can also get traffic information for District 11 counties at www.facebook.com/KYTCDistrict11 or by following us on Twitter at www.twitter.com/KYTCDistrict11


3491/15/2022Bridge construction to begin Monday, November 1 on Dog Branch School Road in Laurel County/DistrictEleven/Pages/PressReleasePage.aspx?&FilterField1=ID&FilterValue1=?
 

Slide Repair Operations Start Friday, October 29 on a Portion of KY 1277 in Whitley County 

MANCHESTER, Ky. (October 28, 2021) The Kentucky Transportation Cabinet (KYTC) advises motorists that slide repair operations start Friday, October 29 on a portion of KY 1277 at mile points 0.000-1.907 in Whitley County. 

A completion date for the slide operations is tentatively set for Friday, November 5.

The roadway will be closed beginning Friday, October 29 with work hours set for 7 a.m. to 6 p.m. each day.

KYTC asks motorists to be aware of the work zone, expect delays, and to utilize safe driving habits when traveling through the area. The date, time, and duration of work may be adjusted if inclement weather or other unforeseen delays occur. Motorists can access travel and traffic conditions at http://goky.ky.gov or contribute their reports at www.waze.com or via the Waze mobile application. You can also get traffic information for District 11 counties at www.facebook.com/KYTCDistrict11 or by following us on Twitter at www.twitter.com/KYTCDistrict11


34811/6/2021Slide Repair Operations Start Friday, October 29 on a Portion of KY 1277 in Whitley County /DistrictEleven/Pages/PressReleasePage.aspx?&FilterField1=ID&FilterValue1=?
 

Cross Drain Operations Start Wednesday, October 27 on Tidal Wave Road at the junction of U.S. 25W in Whitley County 

MANCHESTER, Ky. (October 26, 2021) The Kentucky Transportation Cabinet (KYTC) advises motorists that cross drain operations start Wednesday, October 27 on Tidal Wave Road at the junction of U.S. 25W (mile point 24.8) in Whitley County.

The roadway will be closed to through traffic on Wednesday, October 27 from 7:00 a.m. to 5:00 p.m.

KYTC asks motorists to be aware of the work zone, expect delays, and to utilize safe driving habits when traveling through the area.

The date, time, and duration of work may be adjusted if inclement weather or other unforeseen delays occur. Motorists can access travel and traffic conditions at http://goky.ky.gov or contribute their reports at www.waze.com or via the Waze mobile application. You can also get traffic information for District 11 counties at www.facebook.com/KYTCDistrict11 or by following us on Twitter at www.twitter.com/KYTCDistrict11


34710/28/2021Cross Drain Operations Start Wednesday, October 27 on Tidal Wave Road at the junction of U.S. 25W in Whitley County /DistrictEleven/Pages/PressReleasePage.aspx?&FilterField1=ID&FilterValue1=?
 

Cross Drain Operations Start Tuesday, October 5 on a Portion of KY 577 in Jackson County 

MANCHESTER, Ky. (October 4, 2021) The Kentucky Transportation Cabinet (KYTC) advises motorists that cross drain operations start Tuesday, October 5 on a portion of KY 577 in Jackson County between the intersection with KY 30 (mile point 3.156) and intersection with Moores Creek Green Hill Road (mile point 4.831).

The roadway will be closed to through traffic on Tuesday, October 5, Wednesday, October 6, Thursday, October 7 and Friday, October 8 from 8:00 a.m. to 6:00 p.m. each day.

KYTC asks motorists to be aware of the work zone, expect delays, and to utilize safe driving habits when traveling through the area.

The date, time, and duration of work may be adjusted if inclement weather or other unforeseen delays occur. Motorists can access travel and traffic conditions at http://goky.ky.gov or contribute their reports at www.waze.com or via the Waze mobile application. You can also get traffic information for District 11 counties at www.facebook.com/KYTCDistrict11 or by following us on Twitter at www.twitter.com/KYTCDistrict11


34610/9/2021Cross Drain Operations Start Tuesday, October 5 on a Portion of KY 577 in Jackson County /DistrictEleven/Pages/PressReleasePage.aspx?&FilterField1=ID&FilterValue1=?
 

​Pavement Operations Start Tuesday, October 5 on a Portion of I-75 in Whitley County 

MANCHESTER, Ky. (October 4, 2021) The Kentucky Transportation Cabinet (KYTC) advises motorists that pavement operations start Tuesday, October 5 on a portion of I-75 (mile points 11.2 to Kentucky/Tennessee state line) in Whitley County.

As part of the asphalt rehab project on I-75, motorists traveling I-75 southbound can expect intermittent lane closures from mile point 11.2 to the Kentucky/Tennessee state line until the evening of Friday, October 8 due to the pavement operations.

Work hours are from 7 a.m. to 7 p.m. each day.

KYTC asks motorists to be aware of the work zone, expect delays, and to utilize safe driving habits when traveling through the area.

The date, time, and duration of work may be adjusted if inclement weather or other unforeseen delays occur. Motorists can access travel and traffic conditions at http://goky.ky.gov or contribute their reports at www.waze.com or via the Waze mobile application. You can also get traffic information for District 11 counties at www.facebook.com/KYTCDistrict11 or by following us on Twitter at www.twitter.com/KYTCDistrict11


34510/9/2021Pavement Operations Start Tuesday, October 5 on a Portion of I-75 in Whitley County /DistrictEleven/Pages/PressReleasePage.aspx?&FilterField1=ID&FilterValue1=?
 

Tree Cutting and Tree Removal Operations to Continue on Monday, October 4 on I-75 northbound in Whitley County

MANCHESTER, Ky. (October 1, 2021) The Kentucky Transportation Cabinet (KYTC) advises motorists intermittent right lane closures will continue Monday, October 4 until Friday, October 8 on I-75 northbound (mile points 15.0 – 27.9) in Whitley County from 7 a.m. to 6 p.m. each day due to tree cutting and tree removal operations.

KYTC asks motorists to be aware of the work zone, expect delays, and to utilize safe driving habits when traveling through the area.

The date, time, and duration of work may be adjusted if inclement weather or other unforeseen delays occur. Motorists can access travel and traffic conditions at http://goky.ky.gov or contribute their reports at www.waze.com or via the Waze mobile application. You can also get traffic information for District 11 counties at www.facebook.com/KYTCDistrict11 or by following us on Twitter at www.twitter.com/KYTCDistrict11


34410/9/2021Tree Cutting and Tree Removal Operations to Continue on Monday, October 4 on I-75 northbound in Whitley County/DistrictEleven/Pages/PressReleasePage.aspx?&FilterField1=ID&FilterValue1=?
 

Slide Repair Operations Start Monday, October 4 on a Portion of U.S. 421 in Harlan County 

MANCHESTER, Ky. (September 29, 2021) The Kentucky Transportation Cabinet (KYTC) advises motorists that slide repair operations start Monday, October 4 on a portion of U.S. 421 at mile point 22.8 (0.30 miles south of KY 221) in Harlan County.

The roadway will be reduced to one lane with temporary traffic signals beginning Sunday, October 3. Traffic shifts will be necessary with traffic running on gravel surface.

The contractor plans to work extended shifts, including 24-hour shifts during some of the slide repair operations. Weekend work is also possible.

A completion date for the slide operations is tentatively set for Sunday, July 31, 2022.

KYTC asks motorists to be aware of the work zone, expect delays, and to utilize safe driving habits when traveling through the area. The date, time, and duration of work may be adjusted if inclement weather or other unforeseen delays occur. Motorists can access travel and traffic conditions at http://goky.ky.gov or contribute their reports at www.waze.com or via the Waze mobile application. You can also get traffic information for District 11 counties at www.facebook.com/KYTCDistrict11 or by following us on Twitter at www.twitter.com/KYTCDistrict11


3438/1/2022Slide Repair Operations Start Monday, October 4 on a Portion of U.S. 421 in Harlan County /DistrictEleven/Pages/PressReleasePage.aspx?&FilterField1=ID&FilterValue1=?
 

Cross Drain Operations Start Wednesday, September 29 on a Portion of KY 577 in Jackson County 

MANCHESTER, Ky. (September 28, 2021) The Kentucky Transportation Cabinet (KYTC) advises motorists that cross drain operations start Wednesday, September 29 on a portion of KY 577 in Jackson County between the intersection with Moores Creek Green Hill Road (mile point 4.831) and the intersection with KY 578 (mile point 5.916).

The roadway will be closed to through traffic on Wednesday, September 29, Thursday, September 30 and Friday, October 1 beginning at 8:00 a.m. and ending at 6:00 p.m. each day.

KYTC asks motorists to be aware of the work zone, expect delays, and to utilize safe driving habits when traveling through the area.

The date, time, and duration of work may be adjusted if inclement weather or other unforeseen delays occur. Motorists can access travel and traffic conditions at http://goky.ky.gov or contribute their reports at www.waze.com or via the Waze mobile application. You can also get traffic information for District 11 counties at www.facebook.com/KYTCDistrict11 or by following us on Twitter at www.twitter.com/KYTCDistrict11


34210/2/2021Cross Drain Operations Start Wednesday, September 29 on a Portion of KY 577 in Jackson County /DistrictEleven/Pages/PressReleasePage.aspx?&FilterField1=ID&FilterValue1=?
 

Tree Cutting and Tree Removal Operations to Continue on Monday, September 27 on I-75 northbound in Whitley County

MANCHESTER, Ky. (September 24, 2021) The Kentucky Transportation Cabinet (KYTC) advises motorists intermittent right lane closures will occur beginning Monday, September 27 until Friday, October 1 on I-75 northbound (mile points 15.0 – 27.9) in Whitley County from 7 a.m. to 6 p.m. each day due to tree cutting and tree removal operations.

KYTC asks motorists to be aware of the work zone, expect delays, and to utilize safe driving habits when traveling through the area.

The date, time, and duration of work may be adjusted if inclement weather or other unforeseen delays occur. Motorists can access travel and traffic conditions at http://goky.ky.gov or contribute their reports at www.waze.com or via the Waze mobile application. You can also get traffic information for District 11 counties at www.facebook.com/KYTCDistrict11 or by following us on Twitter at www.twitter.com/KYTCDistrict11


34110/2/2021Tree Cutting and Tree Removal Operations to Continue on Monday, September 27 on I-75 northbound in Whitley County/DistrictEleven/Pages/PressReleasePage.aspx?&FilterField1=ID&FilterValue1=?
 

Cross Drain Operations Start Thursday, September 23 on a Portion of KY 577 in Jackson County 

MANCHESTER, Ky. (September 20, 2021) The Kentucky Transportation Cabinet (KYTC) advises motorists that cross drain operations start Thursday, September 23 on a portion of KY 577 in Jackson County between the intersection with Moores Creek Green Hill Road (mile point 4.831) and the intersection with KY 578 (mile point 5.916).

The roadway will be closed to through traffic on Thursday, September 23 and Friday, September 24 beginning at 8:00 a.m. and ending at 6:00 p.m. each day.

KYTC asks motorists to be aware of the work zone, expect delays, and to utilize safe driving habits when traveling through the area.

The date, time, and duration of work may be adjusted if inclement weather or other unforeseen delays occur. Motorists can access travel and traffic conditions at http://goky.ky.gov or contribute their reports at www.waze.com or via the Waze mobile application. You can also get traffic information for District 11 counties at www.facebook.com/KYTCDistrict11 or by following us on Twitter at www.twitter.com/KYTCDistrict11


3409/25/2021Cross Drain Operations Start Thursday, September 23 on a Portion of KY 577 in Jackson County /DistrictEleven/Pages/PressReleasePage.aspx?&FilterField1=ID&FilterValue1=?
 

Slide Repair Operations Start Friday, September 17 on a Portion of KY 225 in Bell County 

MANCHESTER, Ky. (September 16, 2021) The Kentucky Transportation Cabinet (KYTC) advises motorists that slide repair operations start Friday, September 17 on a portion of KY 225 at mile point 0.97 (Kay Jay Mountain Road) in Bell County.

The roadway will be closed to through traffic Monday through Friday from 7 a.m. to 7 p.m. until Friday, October 15.

KYTC asks motorists to be aware of the work zone, expect delays, and to utilize safe driving habits when traveling through the area.

The date, time, and duration of work may be adjusted if inclement weather or other unforeseen delays occur. Motorists can access travel and traffic conditions at http://goky.ky.gov or contribute their reports at www.waze.com or via the Waze mobile application. You can also get traffic information for District 11 counties at www.facebook.com/KYTCDistrict11 or by following us on Twitter at www.twitter.com/KYTCDistrict11


33910/16/2021Slide Repair Operations Start Friday, September 17 on a Portion of KY 225 in Bell County /DistrictEleven/Pages/PressReleasePage.aspx?&FilterField1=ID&FilterValue1=?
 

Bridge Maintenance Operations continue on a Portion of I-75 Southbound (Right Lane) in Whitley County

MANCHESTER, Ky. (September 15, 2021) The Kentucky Transportation Cabinet (KYTC) advises motorists that a portion of I-75 southbound (right lane) at mile point 2.5 will remain closed until further notice.

The lane closure is necessary to allow crews to perform bridge repair operations.

KYTC asks motorists to be aware of the work zone, expect delays, and to utilize safe driving habits when traveling through the area.

The date, time, and duration of work may be adjusted if inclement weather or other unforeseen delays occur. Motorists can access travel and traffic conditions at http://goky.ky.gov or contribute their reports at www.waze.com or via the Waze mobile application. You can also get traffic information for District 11 counties at www.facebook.com/KYTCDistrict11 or by following us on Twitter at www.twitter.com/KYTCDistrict11


3389/17/2021Bridge Maintenance Operations continue on a Portion of I-75 Southbound (Right Lane) in Whitley County/DistrictEleven/Pages/PressReleasePage.aspx?&FilterField1=ID&FilterValue1=?
 

Tree Cutting and Tree Removal Operations to Occur beginning Thursday, September 16 on I-75 northbound in Whitley County

MANCHESTER, Ky. (September 15, 2021) The Kentucky Transportation Cabinet (KYTC) advises motorists intermittent right lane closures will occur beginning Thursday, September 16 until Friday, September 24 on I-75 northbound (mile points 15.0 – 27.9) in Whitley County from 7 a.m. to 6 p.m. each day due to tree cutting and tree removal operations.

KYTC asks motorists to be aware of the work zone, expect delays, and to utilize safe driving habits when traveling through the area.

The date, time, and duration of work may be adjusted if inclement weather or other unforeseen delays occur. Motorists can access travel and traffic conditions at http://goky.ky.gov or contribute their reports at www.waze.com or via the Waze mobile application. You can also get traffic information for District 11 counties at www.facebook.com/KYTCDistrict11 or by following us on Twitter at www.twitter.com/KYTCDistrict11


3379/25/2021Tree Cutting and Tree Removal Operations to Occur beginning Thursday, September 16 on I-75 northbound in Whitley County/DistrictEleven/Pages/PressReleasePage.aspx?&FilterField1=ID&FilterValue1=?
 

Tree Cutting and Tree Removal Operations to Occur Wednesday, September 15 on I-75 northbound in Whitley County

MANCHESTER, Ky. (September 14, 2021) The Kentucky Transportation Cabinet (KYTC) advises motorists a right lane closure will occur Wednesday, September 15 on I-75 northbound (mile points 15.0 – 17.0) in Whitley County from 7 a.m. to 6 p.m. due to tree cutting and tree removal operations.

KYTC asks motorists to be aware of the work zone, expect delays, and to utilize safe driving habits when traveling through the area.

The date, time, and duration of work may be adjusted if inclement weather or other unforeseen delays occur. Motorists can access travel and traffic conditions at http://goky.ky.gov or contribute their reports at www.waze.com or via the Waze mobile application. You can also get traffic information for District 11 counties at www.facebook.com/KYTCDistrict11 or by following us on Twitter at www.twitter.com/KYTCDistrict11


3369/16/2021Tree Cutting and Tree Removal Operations to Occur Wednesday, September 15 on I-75 northbound in Whitley County/DistrictEleven/Pages/PressReleasePage.aspx?&FilterField1=ID&FilterValue1=?
 

Bridge Maintenance Operations Start Monday, September 13 on a Portion of I-75 Southbound (Right Lane) in Whitley County

MANCHESTER, Ky. (September 10, 2021) The Kentucky Transportation Cabinet (KYTC) advises motorists that a portion of I-75 southbound (right lane) at mile point 2.5 will be closed overnight beginning Monday, September 13 at 9 a.m. until Tuesday, September 14 at noon.

The overnight lane closure is necessary to allow crews to perform bridge repair operations.

KYTC asks motorists to be aware of the work zone, expect delays, and to utilize safe driving habits when traveling through the area.

The date, time, and duration of work may be adjusted if inclement weather or other unforeseen delays occur. Motorists can access travel and traffic conditions at http://goky.ky.gov or contribute their reports at www.waze.com or via the Waze mobile application. You can also get traffic information for District 11 counties at www.facebook.com/KYTCDistrict11 or by following us on Twitter at www.twitter.com/KYTCDistrict11


3359/15/2021​Bridge Maintenance Operations Start Monday, September 13 on a Portion of I-75 Southbound (Right Lane) in Whitley County/DistrictEleven/Pages/PressReleasePage.aspx?&FilterField1=ID&FilterValue1=?
 

Slide Repair Operations Start Wednesday, September 8 on a Portion of KY 2007 in Harlan County 

MANCHESTER, Ky. (September 7, 2021) The Kentucky Transportation Cabinet (KYTC) advises motorists that slide repair operations start Wednesday, September 8 and is expected to end Thursday, September 9 on a portion of KY 2007 at mile point 1.70 (Happy Top Community) in Harlan County.

A road closure at mile point 1.70 will be in effect from 7 a.m. to 6 p.m. on both Wednesday and Thursday. Alternate routes are KY 219 and KY 2007.

KYTC asks motorists to be aware of the work zone, expect delays, and to utilize safe driving habits when traveling through the area.

The date, time, and duration of work may be adjusted if inclement weather or other unforeseen delays occur. Motorists can access travel and traffic conditions at http://goky.ky.gov or contribute their reports at www.waze.com or via the Waze mobile application. You can also get traffic information for District 11 counties at www.facebook.com/KYTCDistrict11 or by following us on Twitter at www.twitter.com/KYTCDistrict11


3349/10/2021Slide Repair Operations Start Wednesday, September 8 on a Portion of KY 2007 in Harlan County /DistrictEleven/Pages/PressReleasePage.aspx?&FilterField1=ID&FilterValue1=?
 

Bridging Kentucky Project Starts on Tuesday, September 7 in Knox County

MANCHESTER, Ky. (September 2, 2021) - The Kentucky Transportation Cabinet (KYTC) District 11 Office advises motorists that a bridge replacement project in Knox County starts on Tuesday, September 7, pending relocation of a water line.

This project will replace the East Bennett Branch Road bridge over Little Poplar Creek and will utilize a temporary onsite diversion during construction. The traffic impact time is up to 60 days, and the new bridge is expected to open to traffic by Saturday, November 6, 2021.

Bridging Kentucky is a program to improve the safety and soundness of the Commonwealth's bridges by rehabilitating, repairing, or replacing critical bridges throughout the state. For more information on Bridging Kentucky and other bridge projects, please visit http://BridgingKentucky.com.

The Kentucky Transportation Cabinet asks motorists to be aware of the work zone, expect delays, and to utilize safe driving habits when traveling through the area.

The date and time could be adjusted if inclement weather or other unforeseen delays occur. Motorists can access travel and traffic conditions at http://goky.ky.gov or contribute their reports at www.waze.com or via the Waze mobile application. You can also get traffic information for District 11 counties at www.facebook.com/KYTCDistrict11 or by following us on Twitter at www.twitter.com/KYTCDistrict11


33311/7/2021Bridging Kentucky Project Starts on Tuesday, September 7 in Knox County/DistrictEleven/Pages/PressReleasePage.aspx?&FilterField1=ID&FilterValue1=?
 

Bridge Repair Operations Start Thursday, September 2 on a Portion of I-75 Southbound (Right Lane) in Whitley County

MANCHESTER, Ky. (September 1, 2021) The Kentucky Transportation Cabinet (KYTC) advises motorists that a portion of I-75 southbound (right lane) at mile points 27.9 (Lynn Camp Creek Bridge) will be closed beginning Thursday, September 2 from 9 a.m. until 12 p.m.

The lane closure is necessary to allow crews to perform bridge repair operations.

KYTC asks motorists to be aware of the work zone, expect delays, and to utilize safe driving habits when traveling through the area.

The date, time, and duration of work may be adjusted if inclement weather or other unforeseen delays occur. Motorists can access travel and traffic conditions at http://goky.ky.gov or contribute their reports at www.waze.com or via the Waze mobile application. You can also get traffic information for District 11 counties at www.facebook.com/KYTCDistrict11 or by following us on Twitter at www.twitter.com/KYTCDistrict11


3329/3/2021Bridge Repair Operations Start Thursday, September 2 on a Portion of I-75 Southbound (Right Lane) in Whitley County/DistrictEleven/Pages/PressReleasePage.aspx?&FilterField1=ID&FilterValue1=?
 

Tree Cutting and Tree Removal Operations Set to Begin Today on I-75 Exit 15 On and Off Ramps in Whitley County

MANCHESTER, Ky. (August 30, 2021) The Kentucky Transportation Cabinet (KYTC) advises motorists to expect delays beginning today until Friday, September 3 on I-75 Exit 15 on and off ramps in Whitley County from 7 a.m. to 5:30 p.m. each day due to tree cutting and tree removal operations.

KYTC asks motorists to be aware of the work zone, expect delays, and to utilize safe driving habits when traveling through the area.

The date, time, and duration of work may be adjusted if inclement weather or other unforeseen delays occur. Motorists can access travel and traffic conditions at http://goky.ky.gov or contribute their reports at www.waze.com or via the Waze mobile application. You can also get traffic information for District 11 counties at www.facebook.com/KYTCDistrict11 or by following us on Twitter at www.twitter.com/KYTCDistrict11


3319/4/2021Tree Cutting and Tree Removal Operations Set to Begin Today on I-75 Exit 15 On and Off Ramps in Whitley County/DistrictEleven/Pages/PressReleasePage.aspx?&FilterField1=ID&FilterValue1=?
 

Slide Repair Operations Continue on a Portion of KY 1556 in Harlan County    

MANCHESTER, Ky. (August 10, 2021) The Kentucky Transportation Cabinet (KYTC) advises motorists that slide repair operations will continue Thursday, August 12 on a portion of KY 1556 from mile points 0.18-0.95 (Bobs Creek) in Harlan County. The work is tentatively scheduled to be completed on Friday, August 20.

The road closure will be in effect beginning from 7 a.m. to 5 p.m. each day with traffic released intermittently during work hours.

KYTC asks motorists to be aware of the work zone, expect long delays, and to utilize safe driving habits when traveling through the area.

The date, time, and duration of work may be adjusted if inclement weather or other unforeseen delays occur. Motorists can access travel and traffic conditions at http://goky.ky.gov or contribute their reports at www.waze.com or via the Waze mobile application. You can also get traffic information for District 11 counties at www.facebook.com/KYTCDistrict11 or by following us on Twitter at www.twitter.com/KYTCDistrict11


3308/21/2021Slide Repair Operations Continue on a Portion of KY 1556 in Harlan County /DistrictEleven/Pages/PressReleasePage.aspx?&FilterField1=ID&FilterValue1=?
 

Slide Repair Operations Start Today on a Portion of KY 2007 in Harlan County    

MANCHESTER, Ky. (August 10, 2021) The Kentucky Transportation Cabinet (KYTC) advises motorists that slide repair operations start today and is expected to end Tuesday, August 24 on a portion of KY 2007 at mile point 1.70 (Happy Top Community) in Harlan County.

The road closure will be in effect beginning today, and 7 a.m. to 7 p.m. each day beginning Wednesday, August 11. Alternate routes are KY 219 and KY 2007.

KYTC asks motorists to be aware of the work zone, expect delays, and to utilize safe driving habits when traveling through the area.

The date, time, and duration of work may be adjusted if inclement weather or other unforeseen delays occur. Motorists can access travel and traffic conditions at http://goky.ky.gov or contribute their reports at www.waze.com or via the Waze mobile application. You can also get traffic information for District 11 counties at www.facebook.com/KYTCDistrict11 or by following us on Twitter at www.twitter.com/KYTCDistrict11


3298/25/2021Slide Repair Operations Start Today on a Portion of KY 2007 in Harlan County /DistrictEleven/Pages/PressReleasePage.aspx?&FilterField1=ID&FilterValue1=?
 

Bridging Kentucky Project Starts on Thursday, August 12 in Harlan County

MANCHESTER, Ky. (August 9, 2021) - The Kentucky Transportation Cabinet (KYTC) District 11 Office advises motorists that a bridge replacement project in Harlan County starts on Thursday, August 12.

This project will replace the Wilson Road Bridge over Martins Fork Creek and will include a realignment for the new bridge. Traffic will continue to utilize the current structure until the new bridge is in place. Construction will take up to 90 days, and the new bridge is expected to open to traffic by Wednesday, November 10.

Bridging Kentucky is a program to improve the safety and soundness of the Commonwealth's bridges by rehabilitating, repairing, or replacing critical bridges throughout the state. For more information on Bridging Kentucky and other bridge projects, please visit http://BridgingKentucky.com.

The Kentucky Transportation Cabinet asks motorists to be aware of the work zone, expect delays, and to utilize safe driving habits when traveling through the area.

The date and time could be adjusted if inclement weather or other unforeseen delays occur. Motorists can access travel and traffic conditions at http://goky.ky.gov or contribute their reports at www.waze.com or via the Waze mobile application. You can also get traffic information for District 11 counties at www.facebook.com/KYTCDistrict11 or by following us on Twitter at www.twitter.com/KYTCDistrict11


32811/11/2021Bridging Kentucky Project Starts on Thursday, August 12 in Harlan County/DistrictEleven/Pages/PressReleasePage.aspx?&FilterField1=ID&FilterValue1=?
 

REVISED: Bridging Kentucky Project Starts on Monday, September 13 in Harlan County

MANCHESTER, Ky. (September 2, 2021) - The Kentucky Transportation Cabinet (KYTC) District 11 Office advises motorists that a bridge replacement project in Harlan County starts on Monday, September 13.

This project will replace the Breedens Creek Road Bridge over Breedens Creek. The bridge will be closed during construction and traffic will utilize a temporary onsite diversion. Construction will take up to 45 days. The new bridge is expected to open to traffic by Friday, November 12.

Bridging Kentucky is a program to improve the safety and soundness of the Commonwealth's bridges by rehabilitating, repairing, or replacing critical bridges throughout the state. For more information on Bridging Kentucky and other bridge projects, please visit http://BridgingKentucky.com.

The Kentucky Transportation Cabinet asks motorists to be aware of the work zone, expect delays, and to utilize safe driving habits when traveling through the area.

The date and time could be adjusted if inclement weather or other unforeseen delays occur. Motorists can access travel and traffic conditions at http://goky.ky.gov or contribute their reports at www.waze.com or via the Waze mobile application. You can also get traffic information for District 11 counties at www.facebook.com/KYTCDistrict11 or by following us on Twitter at www.twitter.com/KYTCDistrict11

32711/13/2021REVISED: Bridging Kentucky Project Starts on Monday, September 13 in Harlan County/DistrictEleven/Pages/PressReleasePage.aspx?&FilterField1=ID&FilterValue1=?
 

Bridging Kentucky Project Starts on Monday, August 16 in Clay County

MANCHESTER, Ky. (August 9, 2021) - The Kentucky Transportation Cabinet (KYTC) District 11 Office advises motorists that a bridge replacement project in Clay County starts on Monday, August 16.

This project will replace the Eriline Road Bridge over Red Bird River and the bridge will be completely closed during construction and traffic will be detoured utilizing Eriline Road and KY 66. This bridge will be closed for up 75 days with an expected open to traffic date of Saturday, October 2.

Bridging Kentucky is a program to improve the safety and soundness of the Commonwealth's bridges by rehabilitating, repairing, or replacing critical bridges throughout the state. For more information on Bridging Kentucky and other bridge projects, please visit http://BridgingKentucky.com.

The Kentucky Transportation Cabinet asks motorists to be aware of the work zone, expect delays, and to utilize safe driving habits when traveling through the area.

The date and time could be adjusted if inclement weather or other unforeseen delays occur. Motorists can access travel and traffic conditions at http://goky.ky.gov or contribute their reports at www.waze.com or via the Waze mobile application. You can also get traffic information for District 11 counties at www.facebook.com/KYTCDistrict11 or by following us on Twitter at www.twitter.com/KYTCDistrict11


32610/3/2021​Bridging Kentucky Project Starts on Monday, August 16 in Clay County/DistrictEleven/Pages/PressReleasePage.aspx?&FilterField1=ID&FilterValue1=?
 

Paving and railroad track repair Operations Set to Begin on U.S. 25E in Knox County on Tuesday, August 10

MANCHESTER, Ky. (August 4, 2020) – The Kentucky Transportation Cabinet (KYTC) advises motorists that paving and railroad track repair operations on U.S. 25E (mile point 11.858) in Knox County will begin Tuesday, August 10 at 8 a.m., and is expected to end Wednesday, August 11 at 6 p.m.

Southbound traffic will be diverted onto the northbound lane on Tuesday, August 10 while northbound traffic will be diverted onto the southbound lane on Wednesday, August 11.

KYTC District 11 crews will perform the paving operations while CSX will perform the railroad track repair operations.

KYTC asks motorists to be aware of the work zone, expect delays, and to utilize safe driving habits when traveling through the area.

The date, time, and duration of work may be adjusted if inclement weather or other unforeseen delays occur. Motorists can access travel and traffic conditions at http://goky.ky.gov or contribute their reports at www.waze.com or via the Waze mobile application. You can also get traffic information for District 11 counties at www.facebook.com/KYTCDistrict11 or by following us on Twitter at www.twitter.com/KYTCDistrict11


3258/12/2021Paving and railroad track repair Operations Set to Begin on U.S. 25E in Knox County on Tuesday, August 10/DistrictEleven/Pages/PressReleasePage.aspx?&FilterField1=ID&FilterValue1=?
 

Slide Repair Operations Continue on a Portion of KY 1556 in Harlan County    

MANCHESTER, Ky. (July 30, 2021) The Kentucky Transportation Cabinet (KYTC) advises motorists that slide repair operations continue and is expected to end Friday, August 6 at 6 p.m. on a portion of KY 1556 from mile points 0.80-0.95 (Bobs Creek) in Harlan County.

The road closure will be in effect beginning from 8 a.m. to 6 p.m. each day with traffic released intermittently during work hours.

KYTC asks motorists to be aware of the work zone, expect delays, and to utilize safe driving habits when traveling through the area.

The date, time, and duration of work may be adjusted if inclement weather or other unforeseen delays occur. Motorists can access travel and traffic conditions at http://goky.ky.gov or contribute their reports at www.waze.com or via the Waze mobile application. You can also get traffic information for District 11 counties at www.facebook.com/KYTCDistrict11 or by following us on Twitter at www.twitter.com/KYTCDistrict11


3248/7/2021Slide Repair Operations Continue on a Portion of KY 1556 in Harlan County /DistrictEleven/Pages/PressReleasePage.aspx?&FilterField1=ID&FilterValue1=?
 

Slide Repair Operations Start Monday, July 26 on a Portion of KY 2004 in Jackson County    

MANCHESTER, Ky. (July 22, 2021) The Kentucky Transportation Cabinet (KYTC) advises motorists that a portion of KY 2004 in Jackson County between the intersection with Azbill Road (mile point 2.133) and intersection with Chestnut Flat Road (mile point 4.006) will be closed to through traffic on Monday, July 26 at 8 a.m., and reopening on Wednesday, August 4 at 6 p.m.

The closure is necessary for slide repair operations.  

KYTC asks motorists to be aware of the work zone, expect delays, and to utilize safe driving habits when traveling through the area.

The date, time, and duration of work may be adjusted if inclement weather or other unforeseen delays occur. Motorists can access travel and traffic conditions at http://goky.ky.gov or contribute their reports at www.waze.com or via the Waze mobile application. You can also get traffic information for District 11 counties at www.facebook.com/KYTCDistrict11 or by following us on Twitter at www.twitter.com/KYTCDistrict11


3238/5/2021​Slide Repair Operations Start Monday, July 26 on a Portion of KY 2004 in Jackson County /DistrictEleven/Pages/PressReleasePage.aspx?&FilterField1=ID&FilterValue1=?
 

Bridging Kentucky Project Starts on Monday, July 26 in Clay County

MANCHESTER, Ky. (July 21, 2021) - The Kentucky Transportation Cabinet (KYTC) District 11 Office advises motorists that a bridge replacement project in Clay County starts on Monday, July 26.

This project will replace the Wiles Branch Road bridge over Wiles Branch and include a temporary onsite diversion, so no detour of traffic is required. The new bridge is scheduled to reopen to traffic by Friday, September 24.

Bridging Kentucky is a program to improve the safety and soundness of the Commonwealth's bridges by rehabilitating, repairing, or replacing critical bridges throughout the state. For more information on Bridging Kentucky and other bridge projects, please visit http://BridgingKentucky.com.

The Kentucky Transportation Cabinet asks motorists to be aware of the work zone, expect delays, and to utilize safe driving habits when traveling through the area.

The date and time could be adjusted if inclement weather or other unforeseen delays occur. Motorists can access travel and traffic conditions at http://goky.ky.gov or contribute their reports at www.waze.com or via the Waze mobile application. You can also get traffic information for District 11 counties at www.facebook.com/KYTCDistrict11 or by following us on Twitter at www.twitter.com/KYTCDistrict11


3229/25/2021Bridging Kentucky Project Starts on Monday, July 26 in Clay County/DistrictEleven/Pages/PressReleasePage.aspx?&FilterField1=ID&FilterValue1=?
1 - 30Next