ContID   243087   EST NO  0001

Date:04/23/2025

COMMONWEALTH OF KENTUCKY

TRANSPORTATION CABINET


Contract ID 243087 Estimate Number 0001 Estimate Type DRAFT_PROGRESS
District Office PADUCAH (01340)  Benifield, Bruce E.

Contractor MURRAY PAVING INC MARS ADDR SN 0
1161 STATE ROUTE 94 E
MURRAY , KY , 42071-9477
Pay Period 11/20/2024  TO  04/17/2025
Date Approved 04/22/2025
Primary Proj Number 0103801252502
Project No. CB06 038 0125 000-001, CB06 038 1463 000-002
Primary County FULTON
Name of Road VARIOUS COUNTY ROADS
Description FROM TENNESSEE / KENTUCKY STATE LINE, EXTENDING NORTH PAST K Y 2140.
     
     
Date Let 09/26/2024 Formal Acceptance
Date Awarded 10/08/2024 Date Work Began 04/07/2025
Date Contract Executed 11/20/2024 Open To Traffic
Date NTP Issued 11/20/2024 Actual Completion Date

Current Contract Amount

$263,100.00

Total to Date

Prev to Date

This Estimate

Original Amount

$263,100.00

Total Earnings

$235,753.80

$0.00

$235,753.80

Percent Complete

89.61

Stockpiled Materials

$0.00

$0.00

$0.00

Funds Available

$27,346.20

Gross Earnings

$235,753.80

$0.00

$0.00

Total Change Orders

$0.00

Other Adjustments

$0.00

$0.00

$0.00

TOTAL

$235,753.80

$0.00

235,753.80

Contract Id 243087

Change Order Summary

County FULTON
Estimate Nbr 0001 Project Number CB06 038 0125 000-001, CB06 038 1463 000-002
Contractor MURRAY PAVING INC Period 11/20/2024  TO  04/17/2025
 
 
CHANGE ORDERS HISTORY  
CHANGE ORDER NBR DESCRIPTION STATUS APPROVAL DATE TOTAL CO AMOUNT CONTRACT TIME ADJUSTED
 
 
 
 

CONTRACT ADJUSTMENTS HISTORY

Contract Adjustments

 

 

Adjustment Description

Est No

Adjustment Amount

Line Item Adjustments History
PROJECT ITEM NBR DESCRPITION TYPE EST NO

ADJ QUANTITY

UNIT PRICE

ADJUSTED AMOUNT

Contract Id 243087

COMMONWEALTH OF KENTUCKY

County FULTON
Contract Type ASRS   ASPHALT RESURFACING

TRANSPORTATION CABINET

Primary Project Number 0103801252502
Estimate Nbr 0001 Period 11/20/2024  TO  04/17/2025
Contractor MURRAY PAVING INC
 
Project 0103801252502 Fed/State Project Number CB06 038 0125 000-001 Category 0001 ROADWAY
LINE ITEM NUMBER ITEM DESCRIPTION ITEM NO. UNIT PLAN QTY CURRENT QUANTITY QUANTITY PAID THIS EST QUANTITY PAID PREV. EST QUANTITY PAID TO DATE UNIT PRICE AMOUNT PAID THIS EST AMOUNT PAID TO DATE
0060 DGA BASE 00001 TON 75.00 75.000 0.000 0.000 40.00 0.00
0065 LEVELING & WEDGING PG64-22 00190 TON 100.00 100.000 0.000 0.000 110.00 0.00
0070 CL2 ASPH SURF 0.38D PG64-22 00301 TON 350.00 350.000 130.000 0.000 130.000 110.00 14,300.00 14,300.00
0075 ASPHALT MATERIAL FOR TACK 00356 TON 3.00 3.000 3.000 0.000 3.000 650.00 1,950.00 1,950.00
0080 TEMPORARY SIGNS 02562 SQFT 300.00 300.000 300.000 0.000 300.000 0.50 150.00 150.00
0085 MAINTAIN & CONTROL TRAFFIC (KY 125) 02650 LS 1.00 1.000 0.500 0.000 0.500 1,500.00 750.00 750.00
0090 MOBILIZATION FOR MILL & TEXT (KY 125) 02676 LS 1.00 1.000 0.000 0.000 1,500.00 0.00
0095 ASPHALT PAVE MILLING & TEXTURING 02677 TON 30.00 30.000 0.000 0.000 50.00 0.00
0100 PAVE STRIPING-TEMP PAINT-4 IN 06510 LF 6,000.00 6,000.000 0.000 0.000 0.14 0.00
0105 PAVE STRIPING-PERM PAINT-4 IN 06514 LF 6,000.00 6,000.000 10,465.000 0.000 10,465.000 0.20 2,093.00 2,093.00
Project 0103801252502 Fed/State Project Number CB06 038 0125 000-001 Category 0002 DEMOBILIZATION
0110 DEMOBILIZATION 02569 LS 1.00 1.000 0.000 0.000 1,950.00 0.00
SUBTOT

$19,243.00

$19,243.000

LNNBR STOCKPILE ADJUSTMENTS

UNIT

ADJ. QUANTITY

EST NBR

UNIT PRICE

ADJUSTED AMOUNT

SUBTOT

0.00

$0.000

 

 

 

Project 0103814632501 Fed/State Project Number CB06 038 1463 000-002 Category 0001 ROADWAY
LINE ITEM NUMBER ITEM DESCRIPTION ITEM NO. UNIT PLAN QTY CURRENT QUANTITY QUANTITY PAID THIS EST QUANTITY PAID PREV. EST QUANTITY PAID TO DATE UNIT PRICE AMOUNT PAID THIS EST AMOUNT PAID TO DATE
0005 DGA BASE 00001 TON 250.00 250.000 0.000 0.000 40.00 0.00
0010 LEVELING & WEDGING PG64-22 00190 TON 200.00 200.000 200.000 0.000 200.000 110.00 22,000.00 22,000.00
0015 CL2 ASPH SURF 0.38D PG64-22 00301 TON 1,350.00 1,350.000 1,649.600 0.000 1,649.600 110.00 181,456.00 181,456.00
0020 ASPHALT MATERIAL FOR TACK 00356 TON 9.00 9.000 9.000 0.000 9.000 650.00 5,850.00 5,850.00
0025 TEMPORARY SIGNS 02562 SQFT 300.00 300.000 300.000 0.000 300.000 0.50 150.00 150.00
0030 MAINTAIN & CONTROL TRAFFIC (KY 1463) 02650 LS 1.00 1.000 0.500 0.000 0.500 1,500.00 750.00 750.00
0035 MOBILIZATION FOR MILL & TEXT (KY 1463) 02676 LS 1.00 1.000 1.000 0.000 1.000 1,500.00 1,500.00 1,500.00
0040 ASPHALT PAVE MILLING & TEXTURING 02677 TON 25.00 25.000 25.000 0.000 25.000 50.00 1,250.00 1,250.00
0045 PAVE STRIPING-TEMP PAINT-4 IN 06510 LF 21,500.00 21,500.000 0.000 0.000 0.14 0.00
0050 PAVE STRIPING-PERM PAINT-4 IN 06514 LF 21,500.00 21,500.000 17,774.000 0.000 17,774.000 0.20 3,554.80 3,554.80
Project 0103814632501 Fed/State Project Number CB06 038 1463 000-002 Category 0002 DEMOBILIZATION
0055 DEMOBILIZATION 02569 LS 1.00 1.000 0.000 0.000 1,950.00 0.00
SUBTOT

$216,510.80

$216,510.800

LNNBR STOCKPILE ADJUSTMENTS

UNIT

ADJ. QUANTITY

EST NBR

UNIT PRICE

ADJUSTED AMOUNT

SUBTOT

0.00

$0.000