Report_Id: 243038 Est NO 0001 |
Date:10/28/2024 |
COMMONWEALTH OF KENTUCKY
TRANSPORTATION CABINET
Contract ID | 243038 | Estimate Number | 0001 | Estimate Type | PROGRESS | ||
District Office | ELIZABETHTOWN (04340) Smith, Jared D | ||||||
Contractor | BLUEGRASS CONTRACTING CORPORATION | ADDR SN 0 VC Code KY0035742 | |||||
PO BOX 11638 | |||||||
1051 RED MILE RD STE 1A | |||||||
LEXINGTON , KY , 40576-1638 | |||||||
Pay Period | 08/07/2024 TO 10/18/2024 | ||||||
Date Approved | 10/28/2024 | ||||||
Primary Proj Number | 0408202282401 | ||||||
Project No. | CB06 082 0228 021-022 | ||||||
Primary County | MEADE | ||||||
Name of Road | BATTLETOWN RD (KY 228) | ||||||
Description | FROM 400 FEET WEST OF KY 313, EXTENDING EASTERLY TO KY 313 I NTERSECTION. | ||||||
Date Let | 07/18/2024 | Formal Acceptance | |||||
Date Awarded | 07/30/2024 | Date Work Began | 10/04/2024 | ||||
Date Contract Executed | 08/07/2024 | Open To Traffic | |||||
Date NTP Issued | 08/07/2024 | Actual Completion Date | 10/06/2024 | ||||
Current Contract Amount | $294,852.00 |
Total to Date |
Prev to Date |
This Estimate |
||
Original Amount | $294,852.00 |
Total Earnings | $285,845.46 |
$0.00 |
$285,845.46 |
|
Percent Complete | 96.95 |
Stockpiled Materials | $0.00 |
$0.00 |
$0.00 |
|
Funds Available | $9,006.54 |
Gross Earnings | $285,845.46 |
$0.00 |
$285,845.46 |
|
Total Change Orders | $0.00 |
Other Adjustments | $0.00 |
$0.00 |
$0.00 |
|
TOTAL | $285,845.46 |
$0.00 |
$285,845.46 |
|||
Contract Id | 243038 | Change Order Summary |
County | MEADE | ||||||
Estimate Nbr | 0001 | Project Number | CB06 082 0228 021-022 | |||||||
Contractor | BLUEGRASS CONTRACTING CORPORATION | Period | 08/07/2024 TO 10/18/2024 | |||||||
CHANGE ORDERS HISTORY | ||||||||||
CHANGE ORDER NBR | DESCRIPTION | STATUS | APPROVAL DATE | TOTAL CO AMOUNT | CONTRACT TIME ADJUSTED | |||||
CONTRACT ADJUSTMENTS HISTORY
Contract Adjustments |
|
|
Adjustment Description | Est No |
Adjustment Amount |
Line Item Adjustments History | |||||||||
PROJECT | ITEM NBR | DESCRPITION | TYPE | EST NO | ADJ QUANTITY |
UNIT PRICE |
ADJUSTED AMOUNT |
Contract Id | 243038 | COMMONWEALTH OF KENTUCKY |
County | MEADE | ||||||
Contract Type | JPC JPC PAVEMENT | TRANSPORTATION CABINET |
Primary Project Number | 0408202282401 | ||||||
Estimate Nbr | 0001 | Period | 08/07/2024 TO 10/18/2024 | |||||||
Contractor | BLUEGRASS CONTRACTING CORPORATION | |||||||||
Project | 0408202282401 | Fed/State Project Number | CB06 082 0228 021-022 | Category | ||||||||
LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
Project | 0408202282401 | Fed/State Project Number | CB06 082 0228 021-022 | Category | 0001 ROADWAY | |||||||
0005 | DGA BASE | 00001 | TON | 25.00 | 25.000 | 72.440 | 0.000 | 72.440 | 109.00 | 7,895.96 | 7,895.96 | |
0010 | CRUSHED AGGREGATE SIZE NO 57 | 00071 | TON | 50.00 | 50.000 | 0.000 | 0.000 | 109.00 | 0.00 | |||
0015 | CL3 ASPH BASE 0.75D PG64-22 (REVISED 7/16/2024) | 00223 | TON | 20.00 | 20.000 | 20.000 | 0.000 | 20.000 | 242.00 | 4,840.00 | 4,840.00 | |
0020 | CL2 ASPH SURF 0.38D PG64-22 | 00301 | TON | 4.00 | 4.000 | 4.000 | 0.000 | 4.000 | 534.00 | 2,136.00 | 2,136.00 | |
0025 | BARRICADE-TYPE III | 02014 | EACH | 2.00 | 2.000 | 2.000 | 0.000 | 2.000 | 222.00 | 444.00 | 444.00 | |
0030 | JPC PAVEMENT-8 IN | 02084 | SQYD | 1,000.00 | 1,000.000 | 1,000.000 | 0.000 | 1,000.000 | 154.00 | 154,000.00 | 154,000.00 | |
0035 | REMOVE PAVEMENT | 02091 | SQYD | 1,000.00 | 1,000.000 | 1,000.000 | 0.000 | 1,000.000 | 57.25 | 57,250.00 | 57,250.00 | |
0040 | TEMPORARY SIGNS | 02562 | SQFT | 190.00 | 190.000 | 188.000 | 0.000 | 188.000 | 9.00 | 1,692.00 | 1,692.00 | |
0045 | FABRIC-GEOTEXTILE CLASS 2 | 02603 | SQYD | 1,000.00 | 1,000.000 | 0.000 | 0.000 | 1.95 | 0.00 | |||
0050 | MAINTAIN & CONTROL TRAFFIC (KY 228) | 02650 | LS | 1.00 | 1.000 | 1.000 | 0.000 | 1.000 | 34,750.00 | 34,750.00 | 34,750.00 | |
0055 | PAVE STRIPING-DUR TY 1-4 IN W | 06554 | LF | 220.00 | 220.000 | 121.000 | 0.000 | 121.000 | 17.00 | 2,057.00 | 2,057.00 | |
0060 | PAVE STRIPING-DUR TY 1-4 IN Y | 06555 | LF | 800.00 | 800.000 | 708.000 | 0.000 | 708.000 | 17.00 | 12,036.00 | 12,036.00 | |
0065 | SAWCUT PAVEMENT | 20550ND | LF | 470.00 | 470.000 | 425.000 | 0.000 | 425.000 | 4.80 | 2,040.00 | 2,040.00 | |
0070 | PAVE MARK TY 1 TAPE STOP BAR-24 IN | 23265ES717 | LF | 33.00 | 33.000 | 32.000 | 0.000 | 32.000 | 28.00 | 896.00 | 896.00 | |
0075 | PAVE MARK TY 1 TAPE-COMBO ARROW | 23269ES717 | EACH | 2.00 | 2.000 | 2.000 | 0.000 | 2.000 | 678.00 | 1,356.00 | 1,356.00 | |
0080 | PAVE MARK TY 1 TAPE-CURV ARROW | 23270ES717 | EACH | 2.00 | 2.000 | 2.000 | 0.000 | 2.000 | 339.00 | 678.00 | 678.00 | |
0090 | PORTABLE CHANGEABLE MESSAGE SIGN (ADDED 7/15/2024) | 02671 | EACH | 3.00 | 3.000 | 3.000 | 0.000 | 3.000 | 895.00 | 2,685.00 | 2,685.00 | |
8000 | JPC PAVEMENT-10 IN | 02069 | SQYD | 0.00 | 0.000 | 0.000 | 0.000 | 171.50 | 0.00 | |||
Project | 0408202282401 | Fed/State Project Number | CB06 082 0228 021-022 | Category | 0002 DEMOBILIZATION | |||||||
0085 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.250 | 0.000 | 0.250 | 4,358.00 | 1,089.50 | 1,089.50 | |
SUBTOT | $285,845.46 |
$285,845.46 |
||||||||||
LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
SUBTOT | $0.00 |