Report_Id:   242297   Est NO  0001

Date:06/23/2025

COMMONWEALTH OF KENTUCKY

TRANSPORTATION CABINET


Contract ID 242297 Estimate Number 0001 Estimate Type PROGRESS
District Office COVINGTON (06320)  Keith, Jerry F.

Contractor MAGO CONSTRUCTION COMPANY LLC ADDR SN 0 VC Code KY0028714
PO BOX 669
BARDSTOWN , KY , 40004
Pay Period 10/17/2024  TO  05/30/2025
Date Approved 06/09/2025
Primary Proj Number MP04100222401
Project No. FD05 041 0022 000-006
Primary County GRANT
Name of Road TAFT HIGHWAY (KY 22)
Description BEGIN AT GRANT/OWEN COUNTY LINE EXTENDING EAST TO EXISTING P AVEMENT JOINT 465 FEET WEST OF KY 36
     
     
Date Let 09/26/2024 Formal Acceptance
Date Awarded 10/08/2024 Date Work Began 05/29/2025
Date Contract Executed 10/17/2024 Open To Traffic
Date NTP Issued 10/17/2024 Actual Completion Date

Current Contract Amount

$762,726.60

Total to Date

Prev to Date

This Estimate

Original Amount

$762,726.60

Total Earnings

$40,375.00

$0.00

$40,375.00

Percent Complete

5.29

Stockpiled Materials

$0.00

$0.00

$0.00

Funds Available

$722,351.60

Gross Earnings

$40,375.00

$0.00

$40,375.00

Total Change Orders

$0.00

Other Adjustments

$0.00

$0.00

$0.00

TOTAL

$40,375.00

$0.00

$40,375.00

Contract Id 242297

Change Order Summary

County GRANT
Estimate Nbr 0001 Project Number FD05 041 0022 000-006
Contractor MAGO CONSTRUCTION COMPANY LLC Period 10/17/2024  TO  05/30/2025
 
 
CHANGE ORDERS HISTORY  
CHANGE ORDER NBR DESCRIPTION STATUS APPROVAL DATE TOTAL CO AMOUNT CONTRACT TIME ADJUSTED
 
 
 
 

CONTRACT ADJUSTMENTS HISTORY

Contract Adjustments

 

 

Adjustment Description

Est No

Adjustment Amount

Line Item Adjustments History
PROJECT ITEM NBR DESCRPITION TYPE EST NO

ADJ QUANTITY

UNIT PRICE

ADJUSTED AMOUNT

Contract Id 242297

COMMONWEALTH OF KENTUCKY

County GRANT
Contract Type ASRS   ASPHALT RESURFACING

TRANSPORTATION CABINET

Primary Project Number MP04100222401
Estimate Nbr 0001 Period 10/17/2024  TO  05/30/2025
Contractor MAGO CONSTRUCTION COMPANY LLC
 
Project MP04100222401 Fed/State Project Number FD05 041 0022 000-006 Category
LINE ITEM NUMBER ITEM DESCRIPTION ITEM NO. UNIT PLAN QTY CURRENT QUANTITY QUANTITY PAID THIS EST QUANTITY PAID PREV. EST QUANTITY PAID TO DATE UNIT PRICE AMOUNT PAID THIS EST AMOUNT PAID TO DATE
Project MP04100222401 Fed/State Project Number FD05 041 0022 000-006 Category 0001 PAVING
0005 DGA BASE 00001 TON 875.00 875.000 0.000 0.000 45.00 0.00
0010 LEVELING & WEDGING PG64-22 00190 TON 314.00 314.000 0.000 0.000 95.00 0.00
0015 CL2 ASPH SURF 0.38D PG64-22 00301 TON 4,575.00 4,575.000 0.000 0.000 95.00 0.00
0020 ASPHALT MATERIAL FOR TACK 00356 TON 39.00 39.000 0.000 0.000 1.00 0.00
0025 TEMPORARY SIGNS 02562 SQFT 271.00 271.000 0.000 0.000 0.01 0.00
0030 MAINTAIN & CONTROL TRAFFIC 02650 LS 1.00 1.000 0.250 0.000 0.250 17,500.00 4,375.00 4,375.00
0035 MOBILIZATION FOR MILL & TEXT 02676 LS 1.00 1.000 0.500 0.000 0.500 4,000.00 2,000.00 2,000.00
0040 ASPHALT PAVE MILLING & TEXTURING 02677 TON 100.00 100.000 0.000 0.000 16.00 0.00
0045 EDGELINE RUMBLE STRIPS 02697 LF 59,900.00 59,900.000 0.000 0.000 0.21 0.00
0050 BASE FAILURE REPAIR 03240 SQYD 1,170.00 1,170.000 680.000 0.000 680.000 50.00 34,000.00 34,000.00
0055 PAVE STRIPING-TEMP PAINT-4 IN 06510 LF 57,400.00 57,400.000 0.000 0.000 0.01 0.00
0060 PAVE STRIPING-THERMO-6 IN W 06542 LF 60,000.00 60,000.000 0.000 0.000 1.10 0.00
0065 PAVE STRIPING-THERMO-6 IN Y 06543 LF 55,000.00 55,000.000 0.000 0.000 1.10 0.00
0070 FUEL ADJUSTMENT 10020NS DOLL 7,610.00 7,610.000 0.000 0.000 1.00 0.00
0075 ASPHALT ADJUSTMENT 10030NS DOLL 19,114.00 19,114.000 0.000 0.000 1.00 0.00
0080 ELECTRONIC DELIVERY MGMT SYSTEM 26228EC LS 1.00 1.000 0.000 0.000 1.00 0.00
Project MP04100222401 Fed/State Project Number FD05 041 0022 000-006 Category 0002 DEMOBILIZATION
0085 DEMOBILIZATION 02569 LS 1.00 1.000 0.000 0.000 10,876.89 0.00

SUBTOT

$40,375.00

$40,375.00

LNNBR STOCKPILE ADJUSTMENTS

UNIT

ADJ. QUANTITY

EST NBR

UNIT PRICE

ADJUSTED AMOUNT

SUBTOT

$0.00