Report_Id:   239003   Est NO  0022

Date:02/16/2026

COMMONWEALTH OF KENTUCKY

TRANSPORTATION CABINET


Contract ID 239003 Estimate Number 0022 Estimate Type PROGRESS
District Office (99460)   Drury, Erika B. P.E.

Contractor STANSELL ELECTRIC COMPANY INCORPORATED ADDR SN 0 VC Code KS0020305
1630 CHURCH STREET ALLEY
NASHVILLE , TN , 37203
Pay Period 01/13/2026  TO  02/02/2026
Date Approved 02/15/2026
Primary Proj Number DE03400752301
Project No. FD52 034 0075 110-121
Primary County FAYETTE
Name of Road WRONG WAY DRIVING PREVENTION PROJECT
Description DEPLOYMENT OF WRONG WAY DRIVING PREVENTION TECHNOLOGIES
     
     
Date Let 04/10/2023 Formal Acceptance
Date Awarded 12/13/2023 Date Work Began 12/12/2023
Date Contract Executed 12/12/2023 Open To Traffic
Date NTP Issued 12/12/2023 Actual Completion Date

Current Contract Amount

$2,394,529.89

Total to Date

Prev to Date

This Estimate

Original Amount

$270,693.58

Total Earnings

$2,350,511.01

$2,322,050.32

$28,460.69

Percent Complete

98.16

Stockpiled Materials

$0.00

$0.00

$0.00

Funds Available

$44,018.88

Gross Earnings

$2,350,511.01

$2,322,050.32

$28,460.69

Total Change Orders

$2,123,836.31

Other Adjustments

$0.00

$0.00

$0.00

TOTAL

$2,350,511.01

$2,322,050.32

$28,460.69

Contract Id 239003

Change Order Summary

County FAYETTE
Estimate Nbr 0022 Project Number FD52 034 0075 110-121
Contractor STANSELL ELECTRIC COMPANY INCORPORATED Period 01/13/2026  TO  02/02/2026
 
 
CHANGE ORDERS HISTORY  
CHANGE ORDER NBR DESCRIPTION STATUS APPROVAL DATE TOTAL CO AMOUNT CONTRACT TIME ADJUSTED
001 Preconstruction Phase Amendment #2 & #3 Approved 07/12/2024 $1,290,136.71 0.0
002 Preconstruction Phase Amendment #4 Approved 04/01/2025 $833,699.60 0.0
 
 
 
 

CONTRACT ADJUSTMENTS HISTORY

Contract Adjustments

 

 

Adjustment Description

Est No

Adjustment Amount

Line Item Adjustments History
PROJECT ITEM NBR DESCRPITION TYPE EST NO

ADJ QUANTITY

UNIT PRICE

ADJUSTED AMOUNT

Contract Id 239003

COMMONWEALTH OF KENTUCKY

County FAYETTE
Contract Type ITS   INTELLIGENT TRANSPORTATION SYSTEMS

TRANSPORTATION CABINET

Primary Project Number DE03400752301
Estimate Nbr 0022 Period 01/13/2026  TO  02/02/2026
Contractor STANSELL ELECTRIC COMPANY INCORPORATED
 
Project DE03400752301 Fed/State Project Number FD52 034 0075 110-121 Category
LINE ITEM NUMBER ITEM DESCRIPTION ITEM NO. UNIT PLAN QTY CURRENT QUANTITY QUANTITY PAID THIS EST QUANTITY PAID PREV. EST QUANTITY PAID TO DATE UNIT PRICE AMOUNT PAID THIS EST AMOUNT PAID TO DATE
Project DE03400752301 Fed/State Project Number FD52 034 0075 110-121 Category 0001 WRONG WAY DRIVING
0005 D/B CONTRACT PAYMENT 25083EN DOLL 270,693.58 270,693.580 28,460.690 2,322,050.320 2,350,511.010 1.00 28,460.69 2,350,511.01
8001 D/B CONTRACT PAYMENT 25083EN DOLL 0.00 2,123,836.310 0.000 0.000 1.00 0.00

SUBTOT

$28,460.69

$2,350,511.01

LNNBR STOCKPILE ADJUSTMENTS

UNIT

ADJ. QUANTITY

EST NBR

UNIT PRICE

ADJUSTED AMOUNT

SUBTOT

$0.00