Report_Id:   232473   Est NO  0001

Date:07/22/2024

COMMONWEALTH OF KENTUCKY

TRANSPORTATION CABINET


Contract ID 232473 Estimate Number 0001 Estimate Type PROGRESS
District Office MANCHESTER (11300)  Nicholson, Robert C

Contractor GEORGE B STONE CO LLC ADDR SN 0 VC Code KY0035959
PO BOX 219
34 N HWY #11
SHARPSBURG , KY , 40374
Pay Period 12/13/2023  TO  06/30/2024
Date Approved 07/10/2024
Primary Proj Number MP06301922302
Project No. FD04 063 0192 017-018, FD04 063 0312 004-005, FD04 063 0472 001-002, FD04 063 0472 008-009
Primary County LAUREL
Name of Road VARIOUS GUARDRAIL PROJECTS
Description FROM 0.348 MILES EAST OF CLUB VALLEY ESTATES ROAD EXTENDING EAST TO DOGWOOD TRAIL
     
     
Date Let 11/16/2023 Formal Acceptance
Date Awarded 11/29/2023 Date Work Began 06/18/2024
Date Contract Executed 12/13/2023 Open To Traffic
Date NTP Issued 12/13/2023 Actual Completion Date 06/28/2024

Current Contract Amount

$434,453.31

Total to Date

Prev to Date

This Estimate

Original Amount

$434,453.31

Total Earnings

$350,412.75

$0.00

$350,412.75

Percent Complete

80.66

Stockpiled Materials

$0.00

$0.00

$0.00

Funds Available

$84,040.56

Gross Earnings

$350,412.75

$0.00

$350,412.75

Total Change Orders

$0.00

Other Adjustments

$0.00

$0.00

$0.00

TOTAL

$350,412.75

$0.00

$350,412.75

Contract Id 232473

Change Order Summary

County LAUREL
Estimate Nbr 0001 Project Number FD04 063 0192 017-018, FD04 063 0312 004-005, FD04 063 0472 001-002, FD04 063 0472 008-009
Contractor GEORGE B STONE CO LLC Period 12/13/2023  TO  06/30/2024
 
 
CHANGE ORDERS HISTORY  
CHANGE ORDER NBR DESCRIPTION STATUS APPROVAL DATE TOTAL CO AMOUNT CONTRACT TIME ADJUSTED
 
 
 
 

CONTRACT ADJUSTMENTS HISTORY

Contract Adjustments

 

 

Adjustment Description

Est No

Adjustment Amount

Line Item Adjustments History
PROJECT ITEM NBR DESCRPITION TYPE EST NO

ADJ QUANTITY

UNIT PRICE

ADJUSTED AMOUNT

Contract Id 232473

COMMONWEALTH OF KENTUCKY

County LAUREL
Contract Type GUAR   GUARDRAIL

TRANSPORTATION CABINET

Primary Project Number MP06301922302
Estimate Nbr 0001 Period 12/13/2023  TO  06/30/2024
Contractor GEORGE B STONE CO LLC
 
Project MP06301922302 Fed/State Project Number FD04 063 0192 017-018 Category 0010 GUARDRAIL
LINE ITEM NUMBER ITEM DESCRIPTION ITEM NO. UNIT PLAN QTY CURRENT QUANTITY QUANTITY PAID THIS EST QUANTITY PAID PREV. EST QUANTITY PAID TO DATE UNIT PRICE AMOUNT PAID THIS EST AMOUNT PAID TO DATE
0005 DGA BASE 00001 TON 250.00 250.000 24.700 0.000 24.700 60.00 1,482.00 1,482.00
0010 CULVERT PIPE-24 IN 00464 LF 300.00 300.000 300.000 0.000 300.000 100.00 30,000.00 30,000.00
0015 METAL END SECTION TY 1-24 IN 01373 EACH 2.00 2.000 2.000 0.000 2.000 6,500.00 13,000.00 13,000.00
0020 DELINEATOR FOR GUARDRAIL BI DIRECTIONAL WHITE 01987 EACH 22.00 22.000 19.000 0.000 19.000 20.00 380.00 380.00
0025 GUARDRAIL-STEEL W BEAM-S FACE 02351 LF 1,000.00 1,000.000 1,250.000 0.000 1,250.000 39.00 48,750.00 48,750.00
0030 GUARDRAIL TERMINAL SECTION NO 1 02360 EACH 1.00 1.000 1.000 0.000 1.000 100.00 100.00 100.00
0035 GUARDRAIL END TREATMENT TYPE 1 02367 EACH 1.00 1.000 1.000 0.000 1.000 5,000.00 5,000.00 5,000.00
0040 GUARDRAIL END TREATMENT TYPE 3 02373 EACH 2.00 2.000 2.000 0.000 2.000 3,000.00 6,000.00 6,000.00
0045 EXTRA LENGTH GUARDRAIL POST (9 FOOT) 02399 EACH 22.00 22.000 0.000 0.000 100.00 0.00
0050 TEMPORARY SIGNS 02562 SQFT 137.00 137.000 0.000 0.000 0.01 0.00
0055 MAINTAIN & CONTROL TRAFFIC (KY 192) 02650 LS 1.00 1.000 1.000 0.000 1.000 2,500.00 2,500.00 2,500.00
Project MP06301922302 Fed/State Project Number FD04 063 0192 017-018 Category 0020 DEMOBILIZATION
0060 DEMOBILIZATION 02569 LS 1.00 1.000 0.000 0.000 1,650.00 0.00

SUBTOT

$107,212.00

$107,212.00

LNNBR STOCKPILE ADJUSTMENTS

UNIT

ADJ. QUANTITY

EST NBR

UNIT PRICE

ADJUSTED AMOUNT

SUBTOT

$0.00

 

 

 

Project MP06303122302 Fed/State Project Number FD04 063 0312 004-005 Category 0010 GUARDRAIL
LINE ITEM NUMBER ITEM DESCRIPTION ITEM NO. UNIT PLAN QTY CURRENT QUANTITY QUANTITY PAID THIS EST QUANTITY PAID PREV. EST QUANTITY PAID TO DATE UNIT PRICE AMOUNT PAID THIS EST AMOUNT PAID TO DATE
0065 DGA BASE 00001 TON 75.00 75.000 0.000 0.000 60.00 0.00
0070 DELINEATOR FOR GUARDRAIL BI DIRECTIONAL WHITE 01987 EACH 7.00 7.000 5.000 0.000 5.000 20.00 100.00 100.00
0075 GUARDRAIL-STEEL W BEAM-S FACE 02351 LF 250.00 250.000 243.000 0.000 243.000 39.00 9,477.00 9,477.00
0080 GUARDRAIL END TREATMENT TYPE 1 02367 EACH 2.00 2.000 2.000 0.000 2.000 5,000.00 10,000.00 10,000.00
0085 TEMPORARY SIGNS 02562 SQFT 137.00 137.000 0.000 0.000 0.01 0.00
0090 MAINTAIN & CONTROL TRAFFIC (KY 312) 02650 LS 1.00 1.000 1.000 0.000 1.000 2,500.00 2,500.00 2,500.00
Project MP06303122302 Fed/State Project Number FD04 063 0312 004-005 Category 0020 DEMOBILIZATION
0095 DEMOBILIZATION 02569 LS 1.00 1.000 0.000 0.000 1,650.00 0.00

SUBTOT

$22,077.00

$129,289.00

LNNBR STOCKPILE ADJUSTMENTS

UNIT

ADJ. QUANTITY

EST NBR

UNIT PRICE

ADJUSTED AMOUNT

SUBTOT

$0.00

 

 

 

Project MP06304722302 Fed/State Project Number FD04 063 0472 001-002 Category 0010 GUARDRAIL
LINE ITEM NUMBER ITEM DESCRIPTION ITEM NO. UNIT PLAN QTY CURRENT QUANTITY QUANTITY PAID THIS EST QUANTITY PAID PREV. EST QUANTITY PAID TO DATE UNIT PRICE AMOUNT PAID THIS EST AMOUNT PAID TO DATE
0100 DGA BASE 00001 TON 900.00 900.000 100.490 0.000 100.490 60.00 6,029.40 6,029.40
0105 DELINEATOR FOR GUARDRAIL BI DIRECTIONAL WHITE 01987 EACH 80.00 80.000 80.000 0.000 80.000 20.00 1,600.00 1,600.00
0110 GUARDRAIL-STEEL W BEAM-S FACE 02351 LF 3,862.50 3,862.500 3,862.500 0.000 3,862.500 39.00 150,637.50 150,637.50
0115 GUARDRAIL TERMINAL SECTION NO 1 02360 EACH 1.00 1.000 1.000 0.000 1.000 100.00 100.00 100.00
0120 GUARDRAIL END TREATMENT TYPE 7 02371 EACH 2.00 2.000 2.000 0.000 2.000 1,500.00 3,000.00 3,000.00
0125 TEMPORARY SIGNS 02562 SQFT 170.00 170.000 85.000 0.000 85.000 0.01 0.85 0.85
0130 MAINTAIN & CONTROL TRAFFIC (KY 472 MILEPOINT 001-002) 02650 LS 1.00 1.000 1.000 0.000 1.000 2,500.00 2,500.00 2,500.00
Project MP06304722302 Fed/State Project Number FD04 063 0472 001-002 Category 0020 DEMOBILIZATION
0135 DEMOBILIZATION 02569 LS 1.00 1.000 0.000 0.000 1,650.00 0.00

SUBTOT

$163,867.75

$293,156.75

LNNBR STOCKPILE ADJUSTMENTS

UNIT

ADJ. QUANTITY

EST NBR

UNIT PRICE

ADJUSTED AMOUNT

SUBTOT

$0.00

 

 

 

Project MP06304722303 Fed/State Project Number FD04 063 0472 008-009 Category 0010 GUARDRAIL
LINE ITEM NUMBER ITEM DESCRIPTION ITEM NO. UNIT PLAN QTY CURRENT QUANTITY QUANTITY PAID THIS EST QUANTITY PAID PREV. EST QUANTITY PAID TO DATE UNIT PRICE AMOUNT PAID THIS EST AMOUNT PAID TO DATE
0140 DGA BASE 00001 TON 300.00 300.000 0.000 0.000 60.00 0.00
0145 DELINEATOR FOR GUARDRAIL BI DIRECTIONAL WHITE 01987 EACH 29.00 29.000 29.000 0.000 29.000 20.00 580.00 580.00
0150 GUARDRAIL-STEEL W BEAM-S FACE 02351 LF 1,400.00 1,400.000 1,384.000 0.000 1,384.000 39.00 53,976.00 53,976.00
0155 GUARDRAIL TERMINAL SECTION NO 1 02360 EACH 2.00 2.000 2.000 0.000 2.000 100.00 200.00 200.00
0160 TEMPORARY SIGNS 02562 SQFT 137.00 137.000 0.000 0.000 0.01 0.00
0165 MAINTAIN & CONTROL TRAFFIC (KY 472 MILEPOINT 008-009) 02650 LS 1.00 1.000 1.000 0.000 1.000 2,500.00 2,500.00 2,500.00
Project MP06304722303 Fed/State Project Number FD04 063 0472 008-009 Category 0020 DEMOBILIZATION
0170 DEMOBILIZATION 02569 LS 1.00 1.000 0.000 0.000 1,650.00 0.00

SUBTOT

$57,256.00

$350,412.75

LNNBR STOCKPILE ADJUSTMENTS

UNIT

ADJ. QUANTITY

EST NBR

UNIT PRICE

ADJUSTED AMOUNT

SUBTOT

$0.00