Report_Id:   232080   Est NO  0004

Date:10/02/2023

COMMONWEALTH OF KENTUCKY

TRANSPORTATION CABINET


Contract ID 232080 Estimate Number 0004 Estimate Type PROGRESS
District Office FLEMINGSBURG (09360)  Tuel, Christopher L.

Contractor STRAWSER CONSTRUCTION INC ADDR SN 0 VC Code KY0036495
1392 DUBLIN ROAD
COLUMBUS , OH , 43215
Pay Period 08/26/2023  TO  09/08/2023
Date Approved 09/18/2023
Primary Proj Number MP04500102301
Project No. FD05 045 0010 008-013
Primary County GREENUP
Name of Road AA HIGHWAY - GREENUP SPUR (KY 10)
Description FROM KY 7, EXTENDING EAST TO GREENUP DAM & LOCKS
     
     
Date Let 01/26/2023 Formal Acceptance
Date Awarded 02/06/2023 Date Work Began 07/18/2023
Date Contract Executed 02/16/2023 Open To Traffic
Date NTP Issued 02/16/2023 Actual Completion Date

Current Contract Amount

$710,034.90

Total to Date

Prev to Date

This Estimate

Original Amount

$710,034.90

Total Earnings

$424,147.63

$291,884.87

$132,262.76

Percent Complete

59.74

Stockpiled Materials

$0.00

$0.00

$0.00

Funds Available

$285,887.27

Gross Earnings

$424,147.63

$291,884.87

$132,262.76

Total Change Orders

$0.00

Other Adjustments

$0.00

$0.00

$0.00

TOTAL

$424,147.63

$291,884.87

$132,262.76

Contract Id 232080

Change Order Summary

County GREENUP
Estimate Nbr 0004 Project Number FD05 045 0010 008-013
Contractor STRAWSER CONSTRUCTION INC Period 08/26/2023  TO  09/08/2023
 
 
CHANGE ORDERS HISTORY  
CHANGE ORDER NBR DESCRIPTION STATUS APPROVAL DATE TOTAL CO AMOUNT CONTRACT TIME ADJUSTED
 
 
 
 

CONTRACT ADJUSTMENTS HISTORY

Contract Adjustments

 

 

Adjustment Description

Est No

Adjustment Amount

Line Item Adjustments History
PROJECT ITEM NBR DESCRPITION TYPE EST NO

ADJ QUANTITY

UNIT PRICE

ADJUSTED AMOUNT

Contract Id 232080

COMMONWEALTH OF KENTUCKY

County GREENUP
Contract Type PALT   PAVEMENT (WITH ALTERNATES)

TRANSPORTATION CABINET

Primary Project Number MP04500102301
Estimate Nbr 0004 Period 08/26/2023  TO  09/08/2023
Contractor STRAWSER CONSTRUCTION INC
 
Project MP04500102301 Fed/State Project Number FD05 045 0010 008-013 Category
LINE ITEM NUMBER ITEM DESCRIPTION ITEM NO. UNIT PLAN QTY CURRENT QUANTITY QUANTITY PAID THIS EST QUANTITY PAID PREV. EST QUANTITY PAID TO DATE UNIT PRICE AMOUNT PAID THIS EST AMOUNT PAID TO DATE
Project MP04500102301 Fed/State Project Number FD05 045 0010 008-013 Category 0001 ROADWAY
0005 TEMPORARY SIGNS 02562 SQFT 230.00 230.000 200.000 200.000 20.00 4,000.00
0010 MAINTAIN & CONTROL TRAFFIC 02650 LS 1.00 1.000 0.500 0.500 19,900.00 9,950.00
0015 PORTABLE CHANGEABLE MESSAGE SIGN 02671 EACH 2.00 2.000 2.000 2.000 835.00 1,670.00
0020 ARROW PANEL 02775 EACH 1.00 1.000 0.000 0.000 565.00 0.00
0025 PAVE STRIPING-THERMO-6 IN W 06542 LF 56,000.00 56,000.000 0.000 0.000 1.29 0.00
0030 PAVE STRIPING-THERMO-6 IN Y 06543 LF 41,000.00 41,000.000 0.000 0.000 1.29 0.00
0035 PAVE MARKING-THERMO STOP BAR-24IN 06568 LF 84.00 84.000 0.000 0.000 15.00 0.00
0040 PAVE MARKING-THERMO CROSS-HATCH 06569 SQFT 938.00 938.000 0.000 0.000 5.00 0.00
0045 PAVE MARKING-THERMO STR ARROW 06573 EACH 5.00 5.000 0.000 0.000 130.00 0.00
0050 PAVE MARKING-THERMO CURV ARROW 06574 EACH 20.00 20.000 0.000 0.000 150.00 0.00
0055 PAVE MARKING-THERMO COMB ARROW 06575 EACH 5.00 5.000 0.000 0.000 175.00 0.00
0060 REMOVE PAVEMENT MARKER TYPE V 06600 EACH 795.00 795.000 650.000 650.000 8.50 5,525.00
0065 CENTERLINE RUMBLE STRIPS 20458ES403 LF 21,000.00 21,000.000 0.000 0.000 0.30 0.00
0070 OVERBAND CRACK SEALING 23071EN LB 18,000.00 18,000.000 0.000 0.000 1.80 0.00
0075 INSTALL RADAR PRESENCE DETECTOR TYPE A 26119EC EACH 4.00 4.000 4.000 4.000 1,410.00 5,640.00
0080 INSTALL RADAR ADVANCE DETECTOR TYPE B 26120EC EACH 2.00 2.000 2.000 2.000 1,410.00 2,820.00
8000 PAVE STRIPING REMOVAL-6 IN 06531 LF 0.00 0.000 0.000 0.000 0.61 0.00
Project MP04500102301 Fed/State Project Number FD05 045 0010 008-013 Category 0003 MICROSURFACE
0115 PAVE STRIPING-TEMP PAINT-4 IN (MICROSURFACE) 06510 LF 100,000.00 100,000.000 3,444.000 140,337.000 143,781.000 0.19 654.36 27,318.39
0120 MICROSURFACING-LEVELING COURSE 21652EN SQYD 113,630.00 113,630.000 86,349.000 86,349.000 1.96 169,244.04
0125 MICROSURFACING-SURFACE COURSE - TYPE D 24958EC SQYD 100,483.00 100,483.000 59,822.000 30,169.000 89,991.000 2.20 131,608.40 197,980.20
8001 PAVE MARK-PAINT ARROWS ( MICROSURFACE ) 20208NC EACH 0.00 0.000 0.000 0.000 50.00 0.00
8002 PAVE MARK TEMP PAINT STOP BAR-24 IN ( MICROSURFACE ) 23010EN LF 0.00 0.000 0.000 0.000 5.25 0.00
8003 EW~ ( Microsurface RAP EXPERIMENTAL ) 10090NX LS 0.00 0.000 0.000 0.000 3,420.00 0.00
Project MP04500102301 Fed/State Project Number FD05 045 0010 008-013 Category 0004 DEMOBILIZATION
0130 DEMOBILIZATION 02569 LS 1.00 1.000 0.000 0.000 31,000.00 0.00

SUBTOT

$132,262.76

$424,147.63

LNNBR STOCKPILE ADJUSTMENTS

UNIT

ADJ. QUANTITY

EST NBR

UNIT PRICE

ADJUSTED AMOUNT

SUBTOT

$0.00