Report_Id: 222436 Est NO 0003 |
Date:06/26/2023 |
COMMONWEALTH OF KENTUCKY
TRANSPORTATION CABINET
Contract ID | 222436 | Estimate Number | 0003 | Estimate Type | PROGRESS | ||
District Office | COVINGTON (06340) Griggs, Anthony D. | ||||||
Contractor | EATON ASPHALT PAVING CO INC | ADDR SN 0 VC Code KY0028332 | |||||
AND SUBSIDIARY | |||||||
136 EAST FROGTOWN ROAD | |||||||
WALTON , KY , 41094 | |||||||
Pay Period | 06/03/2023 TO 06/16/2023 | ||||||
Date Approved | 06/26/2023 | ||||||
Primary Proj Number | MP00800252201 | ||||||
Project No. | FD05 008 0025 009-011 | ||||||
Primary County | BOONE | ||||||
Name of Road | DIXIE HIGHWAY (US 25) | ||||||
Description | BEGINNING 0.082 MILES NORTH OF KY 2847 EXTENDING NORTH TO US 42/MAIN STREET. | ||||||
Date Let | 06/23/2022 | Formal Acceptance | |||||
Date Awarded | 07/06/2022 | Date Work Began | 10/17/2022 | ||||
Date Contract Executed | 07/22/2022 | Open To Traffic | |||||
Date NTP Issued | 07/22/2022 | Actual Completion Date | |||||
Current Contract Amount | $625,796.50 |
Total to Date |
Prev to Date |
This Estimate |
||
Original Amount | $625,796.50 |
Total Earnings | $391,816.01 |
$61,352.65 |
$330,463.36 |
|
Percent Complete | 62.61 |
Stockpiled Materials | $0.00 |
$0.00 |
$0.00 |
|
Funds Available | $233,980.49 |
Gross Earnings | $391,816.01 |
$61,352.65 |
$330,463.36 |
|
Total Change Orders | $0.00 |
Other Adjustments | $0.00 |
$0.00 |
$0.00 |
|
TOTAL | $391,816.01 |
$61,352.65 |
$330,463.36 |
|||
Contract Id | 222436 | Change Order Summary |
County | BOONE | ||||||
Estimate Nbr | 0003 | Project Number | FD05 008 0025 009-011 | |||||||
Contractor | EATON ASPHALT PAVING CO INC | Period | 06/03/2023 TO 06/16/2023 | |||||||
CHANGE ORDERS HISTORY | ||||||||||
CHANGE ORDER NBR | DESCRIPTION | STATUS | APPROVAL DATE | TOTAL CO AMOUNT | CONTRACT TIME ADJUSTED | |||||
001 | Time Extension | Pending | 0 | $0.00 | 227.0 | |||||
002 | Liquidated Damage Override | Approved | 06/19/2023 | $0.00 | 0.0 | |||||
CONTRACT ADJUSTMENTS HISTORY
Contract Adjustments |
|
|
Adjustment Description | Est No |
Adjustment Amount |
Line Item Adjustments History | |||||||||
PROJECT | ITEM NBR | DESCRPITION | TYPE | EST NO | ADJ QUANTITY |
UNIT PRICE |
ADJUSTED AMOUNT |
Contract Id | 222436 | COMMONWEALTH OF KENTUCKY |
County | BOONE | ||||||
Contract Type | ASRS ASPHALT RESURFACING | TRANSPORTATION CABINET |
Primary Project Number | MP00800252201 | ||||||
Estimate Nbr | 0003 | Period | 06/03/2023 TO 06/16/2023 | |||||||
Contractor | EATON ASPHALT PAVING CO INC | |||||||||
Project | MP00800252201 | Fed/State Project Number | FD05 008 0025 009-011 | Category | ||||||||
LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
Project | MP00800252201 | Fed/State Project Number | FD05 008 0025 009-011 | Category | 0001 PAVING | |||||||
0005 | ASPHALT MATERIAL FOR TACK | 00356 | TON | 19.00 | 19.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
0010 | CL3 ASPH SURF 0.38B PG64-22 | 00388 | TON | 3,025.00 | 3,025.000 | 1,990.820 | 0.000 | 1,990.820 | 113.00 | 224,962.66 | 224,962.66 | |
0015 | TEMPORARY SIGNS | 02562 | SQFT | 510.00 | 510.000 | 0.000 | 0.000 | 4.50 | 0.00 | |||
0020 | MAINTAIN & CONTROL TRAFFIC | 02650 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 15,515.00 | 0.00 | |||
0025 | PORTABLE CHANGEABLE MESSAGE SIGN | 02671 | EACH | 2.00 | 2.000 | 0.000 | 0.000 | 1,950.00 | 0.00 | |||
0030 | MOBILIZATION FOR MILL & TEXT | 02676 | LS | 1.00 | 1.000 | 1.000 | 1.000 | 3,225.00 | 3,225.00 | |||
0035 | ASPHALT PAVE MILLING & TEXTURING | 02677 | TON | 3,025.00 | 3,025.000 | 1,047.980 | 1,210.470 | 2,258.450 | 18.00 | 18,863.64 | 40,652.10 | |
0040 | SIDEWALK-4 IN CONCRETE | 02720 | SQYD | 68.00 | 68.000 | 80.750 | 80.750 | 215.00 | 17,361.25 | |||
0045 | ARROW PANEL | 02775 | EACH | 1.00 | 1.000 | 1.000 | 0.000 | 1.000 | 225.00 | 225.00 | 225.00 | |
0050 | CONDUIT-1 1/4 IN | 04793 | LF | 200.00 | 200.000 | 15.000 | 15.000 | 17.00 | 255.00 | |||
0055 | ELECTRICAL JUNCTION BOX TYPE B | 04811 | EACH | 4.00 | 4.000 | 0.000 | 0.000 | 1,050.00 | 0.00 | |||
0060 | LOOP WIRE | 04830 | LF | 3,204.00 | 3,204.000 | 356.000 | 356.000 | 2.00 | 712.00 | |||
0065 | CABLE-NO. 14/1 PAIR | 04850 | LF | 200.00 | 200.000 | 0.000 | 0.000 | 4.00 | 0.00 | |||
0070 | LOOP SAW SLOT AND FILL | 04895 | LF | 1,268.00 | 1,268.000 | 133.000 | 133.000 | 15.00 | 1,995.00 | |||
0075 | PAVE STRIPING-TEMP PAINT-4 IN | 06510 | LF | 48,500.00 | 48,500.000 | 16,823.000 | 16,277.000 | 33,100.000 | 0.22 | 3,701.06 | 7,282.00 | |
0080 | PAVE STRIPING-THERMO-6 IN W | 06542 | LF | 27,000.00 | 27,000.000 | 15,822.000 | 0.000 | 15,822.000 | 1.50 | 23,733.00 | 23,733.00 | |
0085 | PAVE STRIPING-THERMO-6 IN Y | 06543 | LF | 21,500.00 | 21,500.000 | 19,286.000 | 0.000 | 19,286.000 | 1.50 | 28,929.00 | 28,929.00 | |
0090 | PAVE MARKING-THERMO R 6 FT | 06562 | EACH | 4.00 | 4.000 | 4.000 | 0.000 | 4.000 | 5.00 | 20.00 | 20.00 | |
0095 | PAVE MARKING-R/R XBUCKS 16 IN | 06563 | LF | 80.00 | 80.000 | 80.000 | 0.000 | 80.000 | 20.00 | 1,600.00 | 1,600.00 | |
0100 | PAVE MARKING-THERMO X-WALK-6 IN | 06565 | LF | 682.00 | 682.000 | 264.000 | 0.000 | 264.000 | 5.00 | 1,320.00 | 1,320.00 | |
0105 | PAVE MARKING-THERMO STOP BAR-24IN | 06568 | LF | 473.00 | 473.000 | 332.000 | 0.000 | 332.000 | 14.50 | 4,814.00 | 4,814.00 | |
0110 | PAVE MARKING-THERMO CROSS-HATCH | 06569 | SQFT | 2,208.00 | 2,208.000 | 4,222.000 | 0.000 | 4,222.000 | 5.00 | 21,110.00 | 21,110.00 | |
0115 | PAVE MARKING-THERMO STR ARROW | 06573 | EACH | 2.00 | 2.000 | 5.000 | 0.000 | 5.000 | 125.00 | 625.00 | 625.00 | |
0120 | PAVE MARKING-THERMO CURV ARROW | 06574 | EACH | 55.00 | 55.000 | 38.000 | 0.000 | 38.000 | 145.00 | 5,510.00 | 5,510.00 | |
0125 | PAVE MARKING-THERMO ONLY | 06576 | EACH | 3.00 | 3.000 | 0.000 | 0.000 | 335.00 | 0.00 | |||
0130 | REMOVE PAVEMENT MARKER TYPE V | 06600 | EACH | 430.00 | 430.000 | 430.000 | 430.000 | 6.50 | 2,795.00 | |||
0135 | FUEL ADJUSTMENT | 10020NS | DOLL | 4,709.00 | 4,709.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
0140 | ASPHALT ADJUSTMENT | 10030NS | DOLL | 11,827.00 | 11,827.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
0145 | DETECTABLE WARNINGS (NEW) | 23158ES505 | SQFT | 64.00 | 64.000 | 56.000 | 56.000 | 85.00 | 4,760.00 | |||
0150 | PAVE MARK THERMO-6 IN W CAT TRAXX | 23625EC | LF | 160.00 | 160.000 | 0.000 | 0.000 | 5.50 | 0.00 | |||
0155 | LOOP TEST | 24963ED | EACH | 9.00 | 9.000 | 8.000 | 8.000 | 610.00 | 4,880.00 | |||
8002 | LIQUIDATED DAMAGES Failure to Maintain & Control Traffic-Intersection Markings | 10111NS | DOLL | 0.00 | 0.001 | -4,950.000 | 0.000 | -4,950.000 | 1.00 | -4,950.00 | -4,950.00 | |
Project | MP00800252201 | Fed/State Project Number | FD05 008 0025 009-011 | Category | 0002 DEMOBILIZATION | |||||||
0160 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 9,175.00 | 0.00 | |||
SUBTOT | $330,463.36 |
$391,816.01 |
||||||||||
LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
SUBTOT | $0.00 |