Report_Id:   214213   Est NO  0005

Date:03/29/2022

COMMONWEALTH OF KENTUCKY

TRANSPORTATION CABINET


Contract ID 214213 Estimate Number 0005 Estimate Type PROGRESS
District Office PADUCAH (01340)  Wilson, Everett L.

Contractor HARPER CONSTRUCTION LLC ADDR SN 0 VC Code KY0035937
P O BOX 7605
PADUCAH , KY , 42002
Pay Period 02/12/2022  TO  02/25/2022
Date Approved 03/04/2022
Primary Proj Number 0104200802001
Project No. HSIP 5007(008)
Primary County GRAVES
Name of Road KY HIGHWAY 80 (KY 80)
Description EXTEND FOUR REINFORCED CONCRETE BOX CULVERTS ALONG KY 80
     
     
Date Let 09/24/2021 Formal Acceptance
Date Awarded 10/06/2021 Date Work Began 12/09/2021
Date Contract Executed 10/19/2021 Open To Traffic
Date NTP Issued 10/19/2021 Actual Completion Date

Current Contract Amount

$548,855.00

Total to Date

Prev to Date

This Estimate

Original Amount

$548,855.00

Total Earnings

$84,659.55

$79,234.55

$5,425.00

Percent Complete

15.42

Stockpiled Materials

$0.00

$0.00

$0.00

Funds Available

$464,195.45

Gross Earnings

$84,659.55

$79,234.55

$5,425.00

Total Change Orders

$0.00

Other Adjustments

$0.00

$0.00

$0.00

TOTAL

$84,659.55

$79,234.55

$5,425.00

Contract Id 214213

Change Order Summary

County GRAVES
Estimate Nbr 0005 Project Number HSIP 5007(008)
Contractor HARPER CONSTRUCTION LLC Period 02/12/2022  TO  02/25/2022
 
 
CHANGE ORDERS HISTORY  
CHANGE ORDER NBR DESCRIPTION STATUS APPROVAL DATE TOTAL CO AMOUNT CONTRACT TIME ADJUSTED
 
 
 
 

CONTRACT ADJUSTMENTS HISTORY

Contract Adjustments

 

 

Adjustment Description

Est No

Adjustment Amount

Line Item Adjustments History
PROJECT ITEM NBR DESCRPITION TYPE EST NO

ADJ QUANTITY

UNIT PRICE

ADJUSTED AMOUNT

Contract Id 214213

COMMONWEALTH OF KENTUCKY

County GRAVES
Contract Type ASGD   ASPHALT SURFACE WITH GRADE & DRAIN

TRANSPORTATION CABINET

Primary Project Number 0104200802001
Estimate Nbr 0005 Period 02/12/2022  TO  02/25/2022
Contractor HARPER CONSTRUCTION LLC
 
Project 0104200802001 Fed/State Project Number HSIP 5007(008) Category
LINE ITEM NUMBER ITEM DESCRIPTION ITEM NO. UNIT PLAN QTY CURRENT QUANTITY QUANTITY PAID THIS EST QUANTITY PAID PREV. EST QUANTITY PAID TO DATE UNIT PRICE AMOUNT PAID THIS EST AMOUNT PAID TO DATE
Project 0104200802001 Fed/State Project Number HSIP 5007(008) Category 0001 PAVING
0005 CRUSHED STONE BASE 00003 TON 28.00 28.000 0.000 0.000 90.00 0.00
0010 CL2 ASPH BASE 1.00D PG64-22 00212 TON 26.00 26.000 0.000 0.000 250.00 0.00
0015 CL2 ASPH SURF 0.50D PG64-22 00309 TON 7.00 7.000 0.000 0.000 450.00 0.00
0020 ASPHALT MATERIAL FOR TACK NON-TRACKING 24970EC TON 0.04 0.040 0.000 0.000 600.00 0.00
Project 0104200802001 Fed/State Project Number HSIP 5007(008) Category 0002 ROADWAY
0025 BARRICADE-TYPE III 02014 EACH 8.00 8.000 0.000 0.000 250.00 0.00
0030 EMBANKMENT IN PLACE 02230 CUYD 179.00 179.000 0.000 0.000 66.00 0.00
0035 DITCHING 02237 LF 12.00 12.000 0.000 0.000 45.00 0.00
0040 CHANNEL LINING CLASS II 02483 TON 186.00 186.000 0.000 0.000 50.00 0.00
0045 CLEARING AND GRUBBING (APPROX 0.15 ACRES) 02545 LS 1.00 1.000 0.000 0.000 15,500.00 0.00
0050 TEMPORARY SIGNS 02562 SQFT 200.00 200.000 176.000 176.000 15.00 2,640.00
0055 EDGE KEY 02585 LF 40.00 40.000 0.000 0.000 80.00 0.00
0060 MAINTAIN & CONTROL TRAFFIC (GRAVES CO KY 80) 02650 LS 1.00 1.000 0.000 0.000 75,275.05 0.00
0065 STAKING (GRAVES CO KY 80) 02726 LS 1.00 1.000 0.000 0.000 13,749.00 0.00
0070 MAINTENANCE FERTILIZER 05964 TON 0.03 0.030 0.000 0.000 5,000.00 0.00
0075 SEEDING AND PROTECTION 05985 SQYD 453.00 453.000 0.000 0.000 8.50 0.00
0080 AGRICULTURAL LIMESTONE 05992 TON 0.30 0.300 0.000 0.000 1,500.00 0.00
0085 EROSION CONTROL (GRAVES CO KY 80) 21415ND LS 1.00 1.000 0.000 0.000 15,000.00 0.00
Project 0104200802001 Fed/State Project Number HSIP 5007(008) Category 0003 BRIDGE
0090 REMOVE CONCRETE MASONRY 02403 CUYD 9.80 9.800 3.600 3.600 975.00 3,510.00
0095 REMOVE STRUCTURE (RCBC @ MP 2.85) 02731 LS 1.00 1.000 0.000 0.000 22,500.00 0.00
0100 FOUNDATION PREPARATION (RCBC @ MP 2.85) 08003 LS 1.00 1.000 0.000 0.000 27,500.00 0.00
0105 FOUNDATION PREPARATION (RCBC @ MP 8.31) 08003 LS 1.00 1.000 0.000 0.000 16,500.00 0.00
0110 FOUNDATION PREPARATION (RCBC @ MP 8.45) 08003 LS 1.00 1.000 1.000 1.000 25,500.00 25,500.00
0115 FOUNDATION PREPARATION (RCBC 2 MP 2.38) 08003 LS 1.00 1.000 0.000 0.000 33,500.00 0.00
0120 CONCRETE-CLASS A 08100 CUYD 185.10 185.100 5.000 42.000 47.000 1,085.00 5,425.00 50,995.00
0125 STEEL REINFORCEMENT 08150 LB 18,053.00 18,053.000 937.000 937.000 2.15 2,014.55
Project 0104200802001 Fed/State Project Number HSIP 5007(008) Category 0004 DEMOBILIZATION
0130 DEMOBILIZATION 02569 LS 1.00 1.000 0.000 0.000 8,130.00 0.00

SUBTOT

$5,425.00

$84,659.55

LNNBR STOCKPILE ADJUSTMENTS

UNIT

ADJ. QUANTITY

EST NBR

UNIT PRICE

ADJUSTED AMOUNT

SUBTOT

$0.00