Report_Id: 213118 Est NO 0004 |
Date:05/01/2023 |
COMMONWEALTH OF KENTUCKY
TRANSPORTATION CABINET
Contract ID | 213118 | Estimate Number | 0004 | Estimate Type | PROGRESS | ||
District Office | SOMERSET (08360) Foster, Mark A. | ||||||
Contractor | HINKLE CONTRACTING COMPANY LLC | ADDR SN 0 VC Code KY0028986 | |||||
PO BOX 200 | |||||||
PARIS , KY , 40362 | |||||||
Pay Period | 07/16/2022 TO 04/07/2023 | ||||||
Date Approved | 05/01/2023 | ||||||
Primary Proj Number | 0807414702101 | ||||||
Project No. | CB06 074 1470 000-003, CB06 074 3251 000-002 | ||||||
Primary County | MCCREARY | ||||||
Name of Road | VARIOUS ROUTES IN MCCREARY COUNTY | ||||||
Description | FROM THE BEGINNING OF STATE MAINTENANCE EXTENDING EAST TO 0. 119 MILES EAST OF SILERVILLE CEMETERY CIR | ||||||
Date Let | 07/23/2021 | Formal Acceptance | |||||
Date Awarded | 08/04/2021 | Date Work Began | 06/09/2022 | ||||
Date Contract Executed | 08/20/2021 | Open To Traffic | |||||
Date NTP Issued | 08/20/2021 | Actual Completion Date | 07/01/2022 | ||||
Current Contract Amount | $380,803.15 |
Total to Date |
Prev to Date |
This Estimate |
||
Original Amount | $375,609.90 |
Total Earnings | $372,840.45 |
$364,048.03 |
$8,792.42 |
|
Percent Complete | 97.91 |
Stockpiled Materials | $0.00 |
$0.00 |
$0.00 |
|
Funds Available | $7,962.70 |
Gross Earnings | $372,840.45 |
$364,048.03 |
$8,792.42 |
|
Total Change Orders | $5,193.25 |
Other Adjustments | $0.00 |
$0.00 |
$0.00 |
|
TOTAL | $372,840.45 |
$364,048.03 |
$8,792.42 |
|||
Contract Id | 213118 | Change Order Summary |
County | MCCREARY | ||||||
Estimate Nbr | 0004 | Project Number | CB06 074 1470 000-003, CB06 074 3251 000-002 | |||||||
Contractor | HINKLE CONTRACTING COMPANY LLC | Period | 07/16/2022 TO 04/07/2023 | |||||||
CHANGE ORDERS HISTORY | ||||||||||
CHANGE ORDER NBR | DESCRIPTION | STATUS | APPROVAL DATE | TOTAL CO AMOUNT | CONTRACT TIME ADJUSTED | |||||
001 | Overruns, Lot Pay and Non-Spec Material | Approved | 04/21/2023 | $5,193.25 | 3.0 | |||||
CONTRACT ADJUSTMENTS HISTORY
Contract Adjustments |
|
|
Adjustment Description | Est No |
Adjustment Amount |
Line Item Adjustments History | |||||||||
PROJECT | ITEM NBR | DESCRPITION | TYPE | EST NO | ADJ QUANTITY |
UNIT PRICE |
ADJUSTED AMOUNT |
Contract Id | 213118 | COMMONWEALTH OF KENTUCKY |
County | MCCREARY | ||||||
Contract Type | ASRS ASPHALT RESURFACING | TRANSPORTATION CABINET |
Primary Project Number | 0807414702101 | ||||||
Estimate Nbr | 0004 | Period | 07/16/2022 TO 04/07/2023 | |||||||
Contractor | HINKLE CONTRACTING COMPANY LLC | |||||||||
Project | 0807414702101 | Fed/State Project Number | CB06 074 1470 000-003 | Category | 0001 ROADWAY | |||||||
LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
0005 | LEVELING & WEDGING PG64-22 | 00190 | TON | 159.00 | 159.000 | 150.180 | 150.180 | 87.75 | 13,178.29 | |||
0010 | CL2 ASPH SURF 0.38D PG64-22 | 00301 | TON | 1,715.00 | 1,715.000 | 1,707.850 | 1,707.850 | 87.75 | 149,863.83 | |||
0015 | ASPHALT MATERIAL FOR TACK | 00356 | TON | 15.00 | 15.000 | 0.000 | 0.000 | 10.00 | 0.00 | |||
0020 | TEMPORARY SIGNS | 02562 | SQFT | 370.00 | 370.000 | 96.000 | 96.000 | 0.01 | 0.96 | |||
0025 | EDGE KEY | 02585 | LF | 21.00 | 21.000 | 40.000 | 40.000 | 60.00 | 2,400.00 | |||
0030 | MAINTAIN & CONTROL TRAFFIC (KY 1470) | 02650 | LS | 1.00 | 1.000 | 1.000 | 0.000 | 1.000 | 2,000.00 | 2,000.00 | 2,000.00 | |
0035 | BASE FAILURE REPAIR | 03240 | SQYD | 870.00 | 895.000 | 892.000 | 892.000 | 72.00 | 64,224.00 | |||
0040 | PAVE STRIPING-TEMP PAINT-4 IN | 06510 | LF | 4,000.00 | 4,000.000 | 1,738.000 | 1,738.000 | 0.01 | 17.38 | |||
0045 | PAVE STRIPING-PERM PAINT-4 IN | 06514 | LF | 25,000.00 | 25,000.000 | 23,246.000 | 23,246.000 | 0.17 | 3,951.82 | |||
0050 | PAVE MARKING-THERMO R 6 FT | 06562 | EACH | 2.00 | 2.000 | 2.000 | 0.000 | 2.000 | 105.00 | 210.00 | 210.00 | |
0055 | PAVE MARKING-R/R XBUCKS 16 IN | 06563 | LF | 44.00 | 44.000 | 42.000 | 0.000 | 42.000 | 15.00 | 630.00 | 630.00 | |
0060 | PAVE MARKING-THERMO STOP BAR-24IN | 06568 | LF | 30.00 | 30.000 | 21.400 | 0.000 | 21.400 | 12.50 | 267.50 | 267.50 | |
8001 | LOT PAY ADJUSTMENT | 10000NS | DOLL | 0.00 | 1,150.000 | 1,138.560 | 0.000 | 1,138.560 | 1.00 | 1,138.56 | 1,138.56 | |
8002 | NON-SPEC MATERIAL Stiping Retroreflectivity | 10070NS | DOLL | 0.00 | 1.000 | -2,174.980 | 0.000 | -2,174.980 | 1.00 | -2,174.98 | -2,174.98 | |
Project | 0807414702101 | Fed/State Project Number | CB06 074 1470 000-003 | Category | 0002 DEMOBILIZATION | |||||||
0065 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.500 | 0.000 | 0.500 | 5,555.00 | 2,777.50 | 2,777.50 | |
SUBTOT | $4,848.58 |
$238,484.87 |
||||||||||
LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
SUBTOT | $0.00 |
Project | 0807432512102 | Fed/State Project Number | CB06 074 3251 000-002 | Category | 0001 ROADWAY | |||||||
LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
0070 | LEVELING & WEDGING PG64-22 | 00190 | TON | 70.00 | 70.000 | 75.600 | 75.600 | 87.75 | 6,633.90 | |||
0075 | CL2 ASPH SURF 0.38D PG64-22 | 00301 | TON | 770.00 | 785.000 | 783.340 | 783.340 | 87.75 | 68,738.08 | |||
0080 | ASPHALT MATERIAL FOR TACK | 00356 | TON | 7.00 | 7.000 | 0.000 | 0.000 | 10.00 | 0.00 | |||
0085 | TEMPORARY SIGNS | 02562 | SQFT | 270.00 | 270.000 | 96.000 | 96.000 | 0.01 | 0.96 | |||
0090 | EDGE KEY | 02585 | LF | 60.00 | 60.000 | 74.000 | 74.000 | 60.00 | 4,440.00 | |||
0095 | MAINTAIN & CONTROL TRAFFIC (KY 3251) | 02650 | LS | 1.00 | 1.000 | 1.000 | 0.000 | 1.000 | 2,000.00 | 2,000.00 | 2,000.00 | |
0100 | BASE FAILURE REPAIR | 03240 | SQYD | 695.00 | 695.000 | 676.000 | 676.000 | 72.00 | 48,672.00 | |||
0105 | PAVE STRIPING-TEMP PAINT-4 IN | 06510 | LF | 2,000.00 | 2,000.000 | 0.000 | 0.000 | 0.01 | 0.00 | |||
0110 | PAVE STRIPING-PERM PAINT-4 IN | 06514 | LF | 12,000.00 | 12,000.000 | 11,334.000 | 11,334.000 | 0.17 | 1,926.78 | |||
0115 | PAVE MARKING-THERMO R 6 FT | 06562 | EACH | 4.00 | 4.000 | 4.000 | 0.000 | 4.000 | 105.00 | 420.00 | 420.00 | |
0120 | PAVE MARKING-R/R XBUCKS 16 IN | 06563 | LF | 88.00 | 88.000 | 86.000 | 0.000 | 86.000 | 15.00 | 1,290.00 | 1,290.00 | |
0125 | PAVE MARKING-THERMO STOP BAR-24IN | 06568 | LF | 64.00 | 64.000 | 54.000 | 0.000 | 54.000 | 12.50 | 675.00 | 675.00 | |
8004 | LOT PAY ADJUSTMENT | 10000NS | DOLL | 0.00 | 925.000 | 522.230 | 0.000 | 522.230 | 1.00 | 522.23 | 522.23 | |
8005 | NON-SPEC MATERIAL Stiping Retroreflectivity | 10070NS | DOLL | 0.00 | 1.000 | -963.390 | 0.000 | -963.390 | 1.00 | -963.39 | -963.39 | |
Project | 0807432512102 | Fed/State Project Number | CB06 074 3251 000-002 | Category | 0002 DEMOBILIZATION | |||||||
0130 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.500 | 0.000 | 0.500 | 0.00 | 0.00 | ||
SUBTOT | $3,943.84 |
$372,840.43 |
||||||||||
LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
SUBTOT | $0.00 |