Report_Id: 203303 Est NO 0002 |
Date:06/28/2021 |
COMMONWEALTH OF KENTUCKY
TRANSPORTATION CABINET
Contract ID | 203303 | Estimate Number | 0002 | Estimate Type | PROGRESS | ||
District Office | MADISONVILLE (02320) Deason, Emily A. | ||||||
Contractor | RB PAVING AND CONSTRUCTION LLC | ADDR SN 0 VC Code KY0053249 | |||||
, , | |||||||
Pay Period | 05/21/2021 TO 06/03/2021 | ||||||
Date Approved | 06/11/2021 | ||||||
Primary Proj Number | 0205102661902 | ||||||
Project No. | CB06 051 0266 001-005, CB06 051 0283 000-003, CB06 051 0812 000-004 | ||||||
Primary County | HENDERSON | ||||||
Name of Road | VARIOUS ROUTES IN HENDERSON COUNTY | ||||||
Description | FROM MIDWAY RD EXTENDING EAST TO US 60 | ||||||
Date Let | 12/11/2020 | Formal Acceptance | |||||
Date Awarded | 12/18/2020 | Date Work Began | 05/17/2021 | ||||
Date Contract Executed | 01/13/2021 | Open To Traffic | |||||
Date NTP Issued | 01/13/2021 | Actual Completion Date | |||||
Current Contract Amount | $599,941.15 |
Total to Date |
Prev to Date |
This Estimate |
||
Original Amount | $599,941.15 |
Total Earnings | $163,564.14 |
$3,095.00 |
$160,469.14 |
|
Percent Complete | 27.26 |
Stockpiled Materials | $0.00 |
$0.00 |
$0.00 |
|
Funds Available | $436,377.01 |
Gross Earnings | $163,564.14 |
$3,095.00 |
$160,469.14 |
|
Total Change Orders | $0.00 |
Other Adjustments | $0.00 |
$0.00 |
$0.00 |
|
TOTAL | $163,564.14 |
$3,095.00 |
$160,469.14 |
|||
Contract Id | 203303 | Change Order Summary |
County | HENDERSON | ||||||
Estimate Nbr | 0002 | Project Number | CB06 051 0266 001-005, CB06 051 0283 000-003, CB06 051 0812 000-004 | |||||||
Contractor | RB PAVING AND CONSTRUCTION LLC | Period | 05/21/2021 TO 06/03/2021 | |||||||
CHANGE ORDERS HISTORY | ||||||||||
CHANGE ORDER NBR | DESCRIPTION | STATUS | APPROVAL DATE | TOTAL CO AMOUNT | CONTRACT TIME ADJUSTED | |||||
CONTRACT ADJUSTMENTS HISTORY
Contract Adjustments |
|
|
Adjustment Description | Est No |
Adjustment Amount |
Line Item Adjustments History | |||||||||
PROJECT | ITEM NBR | DESCRPITION | TYPE | EST NO | ADJ QUANTITY |
UNIT PRICE |
ADJUSTED AMOUNT |
Contract Id | 203303 | COMMONWEALTH OF KENTUCKY |
County | HENDERSON | ||||||
Contract Type | ASRS ASPHALT RESURFACING | TRANSPORTATION CABINET |
Primary Project Number | 0205102661902 | ||||||
Estimate Nbr | 0002 | Period | 05/21/2021 TO 06/03/2021 | |||||||
Contractor | RB PAVING AND CONSTRUCTION LLC | |||||||||
Project | 0205102661902 | Fed/State Project Number | CB06 051 0266 001-005 | Category | 0001 ROADWAY | |||||||
LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
0075 | DGA BASE | 00001 | TON | 600.00 | 600.000 | 0.000 | 0.000 | 28.58 | 0.00 | |||
0080 | LEVELING & WEDGING PG64-22 | 00190 | TON | 213.00 | 213.000 | 0.000 | 0.000 | 58.16 | 0.00 | |||
0085 | CL2 ASPH SURF 0.38D PG64-22 | 00301 | TON | 2,075.00 | 2,075.000 | 0.000 | 0.000 | 58.16 | 0.00 | |||
0090 | TEMPORARY SIGNS | 02562 | SQFT | 310.00 | 310.000 | 197.000 | 197.000 | 5.00 | 985.00 | |||
0095 | MAINTAIN & CONTROL TRAFFIC (KY 266) | 02650 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 2,050.00 | 0.00 | |||
0100 | MOBILIZATION FOR MILL & TEXT (KY 266) | 02676 | LS | 1.00 | 1.000 | 1.000 | 0.000 | 1.000 | 2,500.00 | 2,500.00 | 2,500.00 | |
0105 | ASPHALT PAVE MILLING & TEXTURING | 02677 | TON | 30.00 | 30.000 | 22.350 | 0.000 | 22.350 | 31.12 | 695.53 | 695.53 | |
0110 | PAVE STRIPING-TEMP PAINT-4 IN | 06510 | LF | 16,000.00 | 16,000.000 | 0.000 | 0.000 | 0.27 | 0.00 | |||
0115 | PAVE STRIPING-PERM PAINT-4 IN | 06514 | LF | 28,000.00 | 28,000.000 | 0.000 | 0.000 | 0.29 | 0.00 | |||
0120 | FUEL ADJUSTMENT | 10020NS | DOLL | 3,561.00 | 3,561.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
0125 | ASPHALT ADJUSTMENT | 10030NS | DOLL | 8,945.00 | 8,945.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
0130 | ASPHALT MATERIAL FOR TACK NON-TRACKING | 24970EC | TON | 10.00 | 10.000 | 0.000 | 0.000 | 464.00 | 0.00 | |||
Project | 0205102661902 | Fed/State Project Number | CB06 051 0266 001-005 | Category | 0002 DEMOBILIZATION | |||||||
0135 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 2,955.37 | 0.00 | |||
SUBTOT | $3,195.53 |
$4,180.53 |
||||||||||
LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
SUBTOT | $0.00 |
Project | 0205102831901 | Fed/State Project Number | CB06 051 0283 000-003 | Category | 0001 ROADWAY | |||||||
LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
0005 | DGA BASE | 00001 | TON | 475.00 | 475.000 | 344.970 | 0.000 | 344.970 | 28.58 | 9,859.24 | 9,859.24 | |
0010 | LEVELING & WEDGING PG64-22 | 00190 | TON | 189.00 | 189.000 | 174.330 | 0.000 | 174.330 | 58.16 | 10,139.03 | 10,139.03 | |
0015 | CL2 ASPH SURF 0.38D PG64-22 | 00301 | TON | 1,840.00 | 1,840.000 | 1,848.480 | 0.000 | 1,848.480 | 58.16 | 107,507.59 | 107,507.59 | |
0020 | TEMPORARY SIGNS | 02562 | SQFT | 310.00 | 310.000 | 225.000 | 225.000 | 5.00 | 1,125.00 | |||
0025 | MAINTAIN & CONTROL TRAFFIC (KY 283) | 02650 | LS | 1.00 | 1.000 | 0.250 | 0.000 | 0.250 | 2,050.00 | 512.50 | 512.50 | |
0030 | MOBILIZATION FOR MILL & TEXT (KY 283) | 02676 | LS | 1.00 | 1.000 | 1.000 | 0.000 | 1.000 | 2,500.00 | 2,500.00 | 2,500.00 | |
0035 | ASPHALT PAVE MILLING & TEXTURING | 02677 | TON | 35.00 | 35.000 | 15.280 | 0.000 | 15.280 | 31.12 | 475.51 | 475.51 | |
0040 | EDGELINE RUMBLE STRIPS | 02697 | LF | 25,000.00 | 25,000.000 | 0.000 | 0.000 | 0.33 | 0.00 | |||
0045 | PAVE STRIPING-TEMP PAINT-4 IN | 06510 | LF | 12,500.00 | 12,500.000 | 4,126.000 | 0.000 | 4,126.000 | 0.27 | 1,114.02 | 1,114.02 | |
0050 | PAVE STRIPING-PERM PAINT-4 IN | 06514 | LF | 22,000.00 | 22,000.000 | 12,720.000 | 0.000 | 12,720.000 | 0.29 | 3,688.80 | 3,688.80 | |
0055 | FUEL ADJUSTMENT | 10020NS | DOLL | 3,158.00 | 3,158.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
0060 | ASPHALT ADJUSTMENT | 10030NS | DOLL | 7,933.00 | 7,933.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
0065 | ASPHALT MATERIAL FOR TACK NON-TRACKING | 24970EC | TON | 9.00 | 9.000 | 10.580 | 0.000 | 10.580 | 464.00 | 4,909.12 | 4,909.12 | |
Project | 0205102831901 | Fed/State Project Number | CB06 051 0283 000-003 | Category | 0002 DEMOBILIZATION | |||||||
0070 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 2,955.38 | 0.00 | |||
SUBTOT | $140,705.82 |
$146,011.35 |
||||||||||
LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
SUBTOT | $0.00 |
Project | 0205108121903 | Fed/State Project Number | CB06 051 0812 000-004 | Category | 0001 ROADWAY | |||||||
LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
0140 | DGA BASE | 00001 | TON | 700.00 | 700.000 | 0.000 | 0.000 | 28.58 | 0.00 | |||
0145 | LEVELING & WEDGING PG64-22 | 00190 | TON | 850.00 | 850.000 | 223.970 | 0.000 | 223.970 | 58.16 | 13,026.09 | 13,026.09 | |
0150 | CL2 ASPH SURF 0.38D PG64-22 | 00301 | TON | 2,075.00 | 2,075.000 | 0.000 | 0.000 | 58.16 | 0.00 | |||
0155 | TEMPORARY SIGNS | 02562 | SQFT | 310.00 | 310.000 | 197.000 | 197.000 | 5.00 | 985.00 | |||
0160 | MAINTAIN & CONTROL TRAFFIC (KY 812) | 02650 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 2,050.00 | 0.00 | |||
0165 | MOBILIZATION FOR MILL & TEXT (KY 812) | 02676 | LS | 1.00 | 1.000 | 1.000 | 0.000 | 1.000 | 2,500.00 | 2,500.00 | 2,500.00 | |
0170 | ASPHALT PAVE MILLING & TEXTURING | 02677 | TON | 75.00 | 75.000 | 22.440 | 0.000 | 22.440 | 31.12 | 698.33 | 698.33 | |
0175 | WATERPROOFING MEMBRANE KY 812 | 03250 | SQYD | 150.00 | 150.000 | 0.000 | 0.000 | 27.00 | 0.00 | |||
0180 | PAVE STRIPING-TEMP PAINT-4 IN | 06510 | LF | 16,000.00 | 16,000.000 | 0.000 | 0.000 | 0.27 | 0.00 | |||
0185 | PAVE STRIPING-PERM PAINT-4 IN | 06514 | LF | 28,000.00 | 28,000.000 | 0.000 | 0.000 | 0.29 | 0.00 | |||
0190 | FUEL ADJUSTMENT | 10020NS | DOLL | 3,561.00 | 3,561.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
0195 | ASPHALT ADJUSTMENT | 10030NS | DOLL | 8,945.00 | 8,945.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
0200 | ASPHALT MATERIAL FOR TACK NON-TRACKING | 24970EC | TON | 10.00 | 10.000 | 0.740 | 0.000 | 0.740 | 464.00 | 343.36 | 343.36 | |
Project | 0205108121903 | Fed/State Project Number | CB06 051 0812 000-004 | Category | 0002 DEMOBILIZATION | |||||||
0205 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 2,955.38 | 0.00 | |||
SUBTOT | $16,567.78 |
$163,564.14 |
||||||||||
LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
SUBTOT | $0.00 |