Report_Id: 202257 Est NO 0001 |
Date:03/08/2021 |
COMMONWEALTH OF KENTUCKY
TRANSPORTATION CABINET
Contract ID | 202257 | Estimate Number | 0001 | Estimate Type | PROGRESS | ||
District Office | COVINGTON (06320) Keith, Jerry F. | ||||||
Contractor | MAGO CONSTRUCTION COMPANY LLC | ADDR SN 0 VC Code KY0028714 | |||||
PO BOX 669 | |||||||
BARDSTOWN , KY , 40004 | |||||||
Pay Period | 10/14/2020 TO 02/01/2021 | ||||||
Date Approved | 02/05/2021 | ||||||
Primary Proj Number | MP04100362001 | ||||||
Project No. | FD05 041 0036 014-015 | ||||||
Primary County | GRANT | ||||||
Name of Road | STUARTSVILLE ROAD (KY 36) | ||||||
Description | BEGINNING AT THE EAST END OF THE I-75 OVERPASS EXTENDING EAS T TO US 25. | ||||||
Date Let | 09/25/2020 | Formal Acceptance | |||||
Date Awarded | 10/05/2020 | Date Work Began | 11/04/2020 | ||||
Date Contract Executed | 10/13/2020 | Open To Traffic | |||||
Date NTP Issued | 10/14/2020 | Actual Completion Date | 11/12/2020 | ||||
Current Contract Amount | $49,362.00 |
Total to Date |
Prev to Date |
This Estimate |
||
Original Amount | $49,362.00 |
Total Earnings | $47,000.01 |
$0.00 |
$47,000.01 |
|
Percent Complete | 95.22 |
Stockpiled Materials | $0.00 |
$0.00 |
$0.00 |
|
Funds Available | $2,361.99 |
Gross Earnings | $47,000.01 |
$0.00 |
$47,000.01 |
|
Total Change Orders | $0.00 |
Other Adjustments | $0.00 |
$0.00 |
$0.00 |
|
TOTAL | $47,000.01 |
$0.00 |
$47,000.01 |
|||
Contract Id | 202257 | Change Order Summary |
County | GRANT | ||||||
Estimate Nbr | 0001 | Project Number | FD05 041 0036 014-015 | |||||||
Contractor | MAGO CONSTRUCTION COMPANY LLC | Period | 10/14/2020 TO 02/01/2021 | |||||||
CHANGE ORDERS HISTORY | ||||||||||
CHANGE ORDER NBR | DESCRIPTION | STATUS | APPROVAL DATE | TOTAL CO AMOUNT | CONTRACT TIME ADJUSTED | |||||
CONTRACT ADJUSTMENTS HISTORY
Contract Adjustments |
|
|
Adjustment Description | Est No |
Adjustment Amount |
Line Item Adjustments History | |||||||||
PROJECT | ITEM NBR | DESCRPITION | TYPE | EST NO | ADJ QUANTITY |
UNIT PRICE |
ADJUSTED AMOUNT |
Contract Id | 202257 | COMMONWEALTH OF KENTUCKY |
County | GRANT | ||||||
Contract Type | ASRS ASPHALT RESURFACING | TRANSPORTATION CABINET |
Primary Project Number | MP04100362001 | ||||||
Estimate Nbr | 0001 | Period | 10/14/2020 TO 02/01/2021 | |||||||
Contractor | MAGO CONSTRUCTION COMPANY LLC | |||||||||
Project | MP04100362001 | Fed/State Project Number | FD05 041 0036 014-015 | Category | ||||||||
LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
Project | MP04100362001 | Fed/State Project Number | FD05 041 0036 014-015 | Category | 0001 PAVING | |||||||
0005 | DGA BASE | 00001 | TON | 125.00 | 125.000 | 124.120 | 0.000 | 124.120 | 50.00 | 6,206.00 | 6,206.00 | |
0010 | LEVELING & WEDGING PG64-22 | 00190 | TON | 8.00 | 8.000 | 0.000 | 0.000 | 72.00 | 0.00 | |||
0015 | CL3 ASPH SURF 0.38B PG64-22 | 00388 | TON | 275.00 | 275.000 | 275.710 | 0.000 | 275.710 | 72.00 | 19,851.12 | 19,851.12 | |
0020 | TEMPORARY SIGNS | 02562 | SQFT | 150.00 | 150.000 | 128.830 | 0.000 | 128.830 | 3.00 | 386.49 | 386.49 | |
0025 | MAINTAIN & CONTROL TRAFFIC | 02650 | LS | 1.00 | 1.000 | 1.000 | 0.000 | 1.000 | 3,500.00 | 3,500.00 | 3,500.00 | |
0030 | MOBILIZATION FOR MILL & TEXT | 02676 | LS | 1.00 | 1.000 | 1.000 | 0.000 | 1.000 | 6,500.00 | 6,500.00 | 6,500.00 | |
0035 | ASPHALT PAVE MILLING & TEXTURING | 02677 | TON | 275.00 | 275.000 | 191.900 | 0.000 | 191.900 | 11.00 | 2,110.90 | 2,110.90 | |
0040 | BASE FAILURE REPAIR | 03240 | SQYD | 70.00 | 70.000 | 70.000 | 0.000 | 70.000 | 100.00 | 7,000.00 | 7,000.00 | |
0045 | PAVE STRIPING-TEMP PAINT-4 IN | 06510 | LF | 4,850.00 | 4,850.000 | 0.000 | 0.000 | 0.01 | 0.00 | |||
0050 | PAVE STRIPING-PERM PAINT-4 IN | 06514 | LF | 4,850.00 | 4,850.000 | 4,782.000 | 0.000 | 4,782.000 | 0.25 | 1,195.50 | 1,195.50 | |
Project | MP04100362001 | Fed/State Project Number | FD05 041 0036 014-015 | Category | 0002 DEMOBILIZATION | |||||||
0055 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.250 | 0.000 | 0.250 | 1,000.00 | 250.00 | 250.00 | |
SUBTOT | $47,000.01 |
$47,000.01 |
||||||||||
LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
SUBTOT | $0.00 |