Report_Id: 192309 Est NO 0001 |
Date:12/04/2019 |
COMMONWEALTH OF KENTUCKY
TRANSPORTATION CABINET
Contract ID | 192309 | Estimate Number | 0001 | Estimate Type | PROGRESS | ||
District Office | MADISONVILLE (02340) Gilliam, Lucas J. | ||||||
Contractor | ROGERS GROUP INC | ADDR SN 0 VC Code KY0029875 | |||||
PO BOX 1045 | |||||||
HOPKINSVILLE , KY , 42241 | |||||||
Pay Period | 10/15/2019 TO 10/31/2019 | ||||||
Date Approved | 11/08/2019 | ||||||
Primary Proj Number | MP02410271901 | ||||||
Project No. | FD05 024 1027 008-012 | ||||||
Primary County | CHRISTIAN | ||||||
Name of Road | ROSETOWN ROAD (KY 1027) | ||||||
Description | BEGINNING 0.304 MILES WEST OF HAMMACK ROAD EXTENDING EAST TO US 68 | ||||||
Date Let | 09/20/2019 | Formal Acceptance | |||||
Date Awarded | 10/02/2019 | Date Work Began | 10/25/2019 | ||||
Date Contract Executed | 10/15/2019 | Open To Traffic | |||||
Date NTP Issued | 10/15/2019 | Actual Completion Date | 11/11/2019 | ||||
Current Contract Amount | $269,666.80 |
Total to Date |
Prev to Date |
This Estimate |
||
Original Amount | $269,666.80 |
Total Earnings | $7,583.62 |
$0.00 |
$7,583.62 |
|
Percent Complete | 2.81 |
Stockpiled Materials | $0.00 |
$0.00 |
$0.00 |
|
Funds Available | $262,083.18 |
Gross Earnings | $7,583.62 |
$0.00 |
$7,583.62 |
|
Total Change Orders | $0.00 |
Other Adjustments | $0.00 |
$0.00 |
$0.00 |
|
TOTAL | $7,583.62 |
$0.00 |
$7,583.62 |
|||
Contract Id | 192309 | Change Order Summary |
County | CHRISTIAN | ||||||
Estimate Nbr | 0001 | Project Number | FD05 024 1027 008-012 | |||||||
Contractor | ROGERS GROUP INC | Period | 10/15/2019 TO 10/31/2019 | |||||||
CHANGE ORDERS HISTORY | ||||||||||
CHANGE ORDER NBR | DESCRIPTION | STATUS | APPROVAL DATE | TOTAL CO AMOUNT | CONTRACT TIME ADJUSTED | |||||
CONTRACT ADJUSTMENTS HISTORY
Contract Adjustments |
|
|
Adjustment Description | Est No |
Adjustment Amount |
Line Item Adjustments History | |||||||||
PROJECT | ITEM NBR | DESCRPITION | TYPE | EST NO | ADJ QUANTITY |
UNIT PRICE |
ADJUSTED AMOUNT |
Contract Id | 192309 | COMMONWEALTH OF KENTUCKY |
County | CHRISTIAN | ||||||
Contract Type | ASRS ASPHALT RESURFACING | TRANSPORTATION CABINET |
Primary Project Number | MP02410271901 | ||||||
Estimate Nbr | 0001 | Period | 10/15/2019 TO 10/31/2019 | |||||||
Contractor | ROGERS GROUP INC | |||||||||
Project | MP02410271901 | Fed/State Project Number | FD05 024 1027 008-012 | Category | ||||||||
LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
Project | MP02410271901 | Fed/State Project Number | FD05 024 1027 008-012 | Category | 0001 PAVING | |||||||
0005 | DGA BASE | 00001 | TON | 500.00 | 500.000 | 0.000 | 0.000 | 25.60 | 0.00 | |||
0010 | LEVELING & WEDGING PG64-22 | 00190 | TON | 359.00 | 359.000 | 0.000 | 0.000 | 65.58 | 0.00 | |||
0015 | CL2 ASPH SURF 0.38D PG64-22 | 00301 | TON | 2,870.00 | 2,870.000 | 0.000 | 0.000 | 63.26 | 0.00 | |||
0020 | TEMPORARY SIGNS | 02562 | SQFT | 230.00 | 230.000 | 144.000 | 0.000 | 144.000 | 0.50 | 72.00 | 72.00 | |
0025 | MAINTAIN & CONTROL TRAFFIC | 02650 | LS | 1.00 | 1.000 | 0.500 | 0.000 | 0.500 | 1,698.59 | 849.29 | 849.29 | |
0030 | MOBILIZATION FOR MILL & TEXT | 02676 | LS | 1.00 | 1.000 | 1.000 | 0.000 | 1.000 | 2,500.00 | 2,500.00 | 2,500.00 | |
0035 | ASPHALT PAVE MILLING & TEXTURING | 02677 | TON | 55.00 | 55.000 | 38.540 | 0.000 | 38.540 | 108.00 | 4,162.32 | 4,162.32 | |
0040 | PAVE STRIPING-TEMP PAINT-4 IN | 06510 | LF | 8,000.00 | 8,000.000 | 0.000 | 0.000 | 0.15 | 0.00 | |||
0045 | PAVE STRIPING-PERM PAINT-4 IN | 06514 | LF | 40,000.00 | 40,000.000 | 0.000 | 0.000 | 0.20 | 0.00 | |||
0050 | FUEL ADJUSTMENT | 10020NS | DOLL | 5,026.00 | 5,026.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
0055 | ASPHALT ADJUSTMENT | 10030NS | DOLL | 12,624.00 | 12,624.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
0060 | ASPHALT MATERIAL FOR TACK NON-TRACKING | 24970EC | TON | 15.00 | 15.000 | 0.000 | 0.000 | 695.93 | 0.00 | |||
Project | MP02410271901 | Fed/State Project Number | FD05 024 1027 008-012 | Category | 0002 DEMOBILIZATION | |||||||
0065 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 4,224.84 | 0.00 | |||
SUBTOT | $7,583.61 |
$7,583.61 |
||||||||||
LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
SUBTOT | $0.00 |