Report_Id: 182277 Est NO 0001 |
Date:10/16/2018 |
COMMONWEALTH OF KENTUCKY
TRANSPORTATION CABINET
Contract ID | 182277 | Estimate Number | 0001 | Estimate Type | PROGRESS | ||
District Office | COVINGTON (06360) Moore, Craig A. | ||||||
Contractor | MAGO CONSTRUCTION COMPANY LLC | ADDR SN 0 VC Code KY0028714 | |||||
PO BOX 669 | |||||||
BARDSTOWN , KY , 40004 | |||||||
Pay Period | 07/26/2018 TO 09/20/2018 | ||||||
Date Approved | 10/02/2018 | ||||||
Primary Proj Number | MP09601591801 | ||||||
Project No. | FD05 096 0159 000-003 | ||||||
Primary County | PENDLETON | ||||||
Name of Road | FALMOUTH-MT. AUBURN ROAD (KY 159) | ||||||
Description | FROM KY 22 EXTENDING NORTH TO GRIMES ROAD-NORTH | ||||||
Date Let | 06/22/2018 | Formal Acceptance | |||||
Date Awarded | 06/28/2018 | Date Work Began | 09/13/2018 | ||||
Date Contract Executed | 07/26/2018 | Open To Traffic | |||||
Date NTP Issued | 07/26/2018 | Actual Completion Date | |||||
Current Contract Amount | $185,417.67 |
Total to Date |
Prev to Date |
This Estimate |
||
Original Amount | $185,417.67 |
Total Earnings | $64,923.98 |
$0.00 |
$64,923.98 |
|
Percent Complete | 35.02 |
Stockpiled Materials | $0.00 |
$0.00 |
$0.00 |
|
Funds Available | $120,493.69 |
Gross Earnings | $64,923.98 |
$0.00 |
$64,923.98 |
|
Total Change Orders | $0.00 |
Other Adjustments | $0.00 |
$0.00 |
$0.00 |
|
TOTAL | $64,923.98 |
$0.00 |
$64,923.98 |
|||
Contract Id | 182277 | Change Order Summary |
County | PENDLETON | ||||||
Estimate Nbr | 0001 | Project Number | FD05 096 0159 000-003 | |||||||
Contractor | MAGO CONSTRUCTION COMPANY LLC | Period | 07/26/2018 TO 09/20/2018 | |||||||
CHANGE ORDERS HISTORY | ||||||||||
CHANGE ORDER NBR | DESCRIPTION | STATUS | APPROVAL DATE | TOTAL CO AMOUNT | CONTRACT TIME ADJUSTED | |||||
CONTRACT ADJUSTMENTS HISTORY
Contract Adjustments |
|
|
Adjustment Description | Est No |
Adjustment Amount |
Line Item Adjustments History | |||||||||
PROJECT | ITEM NBR | DESCRPITION | TYPE | EST NO | ADJ QUANTITY |
UNIT PRICE |
ADJUSTED AMOUNT |
Contract Id | 182277 | COMMONWEALTH OF KENTUCKY |
County | PENDLETON | ||||||
Contract Type | PALT PAVEMENT (WITH ALTERNATES) | TRANSPORTATION CABINET |
Primary Project Number | MP09601591801 | ||||||
Estimate Nbr | 0001 | Period | 07/26/2018 TO 09/20/2018 | |||||||
Contractor | MAGO CONSTRUCTION COMPANY LLC | |||||||||
Project | MP09601591801 | Fed/State Project Number | FD05 096 0159 000-003 | Category | ||||||||
LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
Project | MP09601591801 | Fed/State Project Number | FD05 096 0159 000-003 | Category | 0001 ROADWAY | |||||||
0005 | TEMPORARY SIGNS | 02562 | SQFT | 300.00 | 300.000 | 231.000 | 0.000 | 231.000 | 3.00 | 693.00 | 693.00 | |
0010 | MAINTAIN & CONTROL TRAFFIC | 02650 | LS | 1.00 | 1.000 | 0.500 | 0.000 | 0.500 | 2,000.00 | 1,000.00 | 1,000.00 | |
0015 | PAVE STRIPING-TEMP PAINT-4 IN | 06510 | LF | 30,000.00 | 30,000.000 | 26,296.000 | 0.000 | 26,296.000 | 0.13 | 3,418.48 | 3,418.48 | |
0020 | PAVE STRIPING-PERM PAINT-4 IN | 06514 | LF | 60,000.00 | 60,000.000 | 0.000 | 0.000 | 0.14 | 0.00 | |||
0025 | PAVE MARKING-THERMO STOP BAR-24IN | 06568 | LF | 80.00 | 80.000 | 0.000 | 0.000 | 9.00 | 0.00 | |||
Project | MP09601591801 | Fed/State Project Number | FD05 096 0159 000-003 | Category | 0002 SCRUB SEAL | |||||||
0030 | POLYMER ASPHALT EMULSION FOR SCRUB SEAL | 24858EC | TON | 57.43 | 57.430 | 45.850 | 0.000 | 45.850 | 750.00 | 34,387.50 | 34,387.50 | |
0035 | ASPHALT SEAL AGGREGATE - TYPE D (SEAL COAT NO. 9M) | 24961EC | SQYD | 42,375.00 | 42,375.000 | 42,375.000 | 0.000 | 42,375.000 | 0.60 | 25,425.00 | 25,425.00 | |
Project | MP09601591801 | Fed/State Project Number | FD05 096 0159 000-003 | Category | 0004 THINLAY | |||||||
0045 | ASPHALT MATERIAL FOR TACK | 00356 | TON | 11.12 | 11.120 | 0.000 | 0.000 | 500.00 | 0.00 | |||
0050 | MOBILIZATION FOR MILL & TEXT | 02676 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 1,400.00 | 0.00 | |||
0055 | ASPHALT PAVE MILLING & TEXTURING | 02677 | TON | 10.00 | 10.000 | 0.000 | 0.000 | 5.00 | 0.00 | |||
0060 | CL2 ASPH SURF NO.4D PG64-22 | 21653ES403 | TON | 1,460.00 | 1,460.000 | 0.000 | 0.000 | 62.50 | 0.00 | |||
Project | MP09601591801 | Fed/State Project Number | FD05 096 0159 000-003 | Category | 0005 DEMOBILIZATION | |||||||
0065 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 2,740.17 | 0.00 | |||
SUBTOT | $64,923.98 |
$64,923.98 |
||||||||||
LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
SUBTOT | $0.00 |