Report_Id:ESTIMATE FINAL updated 6-26-09 |
Date:05/13/2019 |
COMMONWEALTH OF KENTUCKY
TRANSPORTATION CABINET
Contract ID | 182248 | Estimate Number | 0003 | Estimate Type FINAL | |||
District Office | ELIZABETHTOWN (04320) Jewell, William C. | ||||||
Contractor | HAYDON MATERIALS LLC | ADDR SN 0 VC Code KY0017940 | |||||
40 LUCKNOW COURT | |||||||
BARDSTOWN , KY , 40004-2113 | |||||||
Pay Period | 12/12/2018 TO 02/05/2019 | ||||||
Date Approved | 04/16/2019 | ||||||
Primary Proj Number | MP04402181801 | ||||||
Project No. | FD05 044 0218 005-010 | ||||||
Primary County | GREEN | ||||||
Name of Road | PIERCE TO EXIE ROAD (KY 218) | ||||||
Description | BEGIN AT KY 1464 EXTENDING EAST TO US 68 | ||||||
Date Let | 05/25/2018 | Formal Acceptance | 07/24/2018 | ||||
Date Awarded | 06/07/2018 | Date Work Began | 07/16/2018 | ||||
Date Contract Executed | 07/02/2018 | Open To Traffic | 07/24/2018 | ||||
Date NTP Issued | 07/02/2018 | Actual Completion Date | 07/24/2018 | ||||
Current Contract Amount | $381,208.65 |
Total to Date |
Prev to Date |
This Estimate |
||
Original Amount | $381,208.65 |
Total Earnings | $343,453.39 |
$337,819.74 |
$5,633.65 |
|
Percent Complete | 90.10 |
Stockpiled Materials | $0.00 |
$0.00 |
$0.00 |
|
Funds Available | $37,755.26 |
Gross Earnings | $343,453.39 |
$337,819.74 |
$5,633.65 |
|
Total Change Orders | $0.00 |
Other Adjustments | $0.00 |
$0.00 |
$0.00 |
|
TOTAL | $343,453.39 |
$337,819.74 |
$5,633.65 |
|||
Contract Id | 182248 | Change Order Summary |
County | GREEN | ||||||
Estimate Nbr | 0003 | Project Number | FD05 044 0218 005-010 | |||||||
Contractor | HAYDON MATERIALS LLC | Period | 12/12/2018 TO 02/05/2019 | |||||||
CHANGE ORDERS HISTORY | ||||||||||
CHANGE ORDER NBR | DESCRIPTION | STATUS | APPROVAL DATE | TOTAL CO AMOUNT | CONTRACT TIME ADJUSTED | |||||
CONTRACT ADJUSTMENTS HISTORY
Contract Adjustments |
|
|
Adjustment Description | Est No |
Adjustment Amount |
Line Item Adjustments History | |||||||||
PROJECT | ITEM NBR | DESCRPITION | TYPE | EST NO | ADJ QUANTITY |
UNIT PRICE |
ADJUSTED AMOUNT |
Contract Id | 182248 | COMMONWEALTH OF KENTUCKY |
County | GREEN | ||||||
Contract No | TRANSPORTATION CABINET |
Primary Project Number | MP04402181801 | |||||||
Estimate Nbr | 0003 | Period | 12/12/2018 TO 02/05/2019 | |||||||
Contractor | HAYDON MATERIALS LLC | |||||||||
Project | MP04402181801 | Fed/State Project Number | FD05 044 0218 005-010 | Category | ||||||||
LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
Project | MP04402181801 | Fed/State Project Number | FD05 044 0218 005-010 | Category | 0001 PAVING | |||||||
0005 | LEVELING & WEDGING PG64-22 | 00190 | TON | 327.00 | 327.000 | 326.340 | 326.340 | 69.25 | 22,599.04 | |||
0010 | CL2 ASPH BASE 0.75D PG64-22 | 00221 | TON | 655.00 | 655.000 | 683.980 | 683.980 | 71.75 | 49,075.56 | |||
0015 | CL2 ASPH SURF 0.38D PG64-22 | 00301 | TON | 3,180.00 | 3,180.000 | 3,179.710 | 3,179.710 | 69.25 | 220,194.91 | |||
0020 | TEMPORARY SIGNS | 02562 | SQFT | 330.00 | 330.000 | 208.000 | 208.000 | 3.00 | 624.00 | |||
0025 | MAINTAIN & CONTROL TRAFFIC | 02650 | LS | 1.00 | 1.000 | 1.000 | 1.000 | 7,000.00 | 7,000.00 | |||
0030 | MOBILIZATION FOR MILL & TEXT | 02676 | LS | 1.00 | 1.000 | 1.000 | 1.000 | 3,500.00 | 3,500.00 | |||
0035 | ASPHALT PAVE MILLING & TEXTURING | 02677 | TON | 25.00 | 25.000 | 28.760 | 28.760 | 50.00 | 1,438.00 | |||
0040 | PAVE STRIPING-TEMP PAINT-4 IN | 06510 | LF | 15,000.00 | 15,000.000 | 560.000 | 560.000 | 0.01 | 5.60 | |||
0045 | PAVE STRIPING-PERM PAINT-4 IN | 06514 | LF | 38,500.00 | 38,500.000 | 37,090.000 | 37,090.000 | 0.19 | 7,047.10 | |||
0050 | PAVE MARKING-THERMO STOP BAR-24IN | 06568 | LF | 24.00 | 24.000 | 24.000 | 24.000 | 10.00 | 240.00 | |||
0055 | FUEL ADJUSTMENT | 10020NS | DOLL | 12,950.00 | 12,950.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
0060 | ASPHALT ADJUSTMENT | 10030NS | DOLL | 32,528.00 | 32,528.000 | 12,860.750 | 12,860.750 | 1.00 | 12,860.75 | |||
0065 | THERMO RUMBLE STRIPS TY 2 | 24097EC | LF | 108.00 | 108.000 | 117.000 | 117.000 | 12.00 | 1,404.00 | |||
0070 | ASPHALT MATERIAL FOR TACK NON-TRACKING | 24970EC | TON | 20.00 | 20.000 | 12.790 | 12.790 | 925.00 | 11,830.75 | |||
Project | MP04402181801 | Fed/State Project Number | FD05 044 0218 005-010 | Category | 0002 DEMOBILIZATION | |||||||
0075 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 1.000 | 0.000 | 1.000 | 5,633.65 | 5,633.65 | 5,633.65 | |
SUBTOT | $5,633.65 |
$343,453.37 |
||||||||||
LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
SUBTOT | $0.00 |