Report_Id:ESTIMATE FINAL updated 6-26-09

Date:04/26/2018

COMMONWEALTH OF KENTUCKY

TRANSPORTATION CABINET


Contract ID 162168 Estimate Number 0007 Estimate Type  FINAL
District Office COVINGTON (06380)  Rust, Kevin J.

Contractor MAGO CONSTRUCTION COMPANY LLC ADDR SN 0 VC Code VC0000088019
PO BOX 669
BARDSTOWN , KY , 40004
Pay Period 02/24/2018  TO  03/07/2018
Date Approved 04/03/2018
Primary Proj Number MP09402271602
Project No. FD05 094 0227 000-015
Primary County OWEN
Name of Road HESLER ROAD (KY 227)
Description HESLER ROAD (KY 227)
     
     
Date Let 07/29/2016 Formal Acceptance 09/21/2017
Date Awarded 08/05/2016 Date Work Began 04/03/2017
Date Contract Executed 08/23/2016 Open To Traffic 05/03/2017
Date NTP Issued 08/23/2016 Actual Completion Date 05/03/2017

Current Contract Amount

$823,398.13

Total to Date

Prev to Date

This Estimate

Original Amount

$823,398.13

Total Earnings

$786,050.83

$783,289.91

$2,760.92

Percent Complete

95.46

Stockpiled Materials

$0.00

$0.00

$0.00

Funds Available

$37,347.30

Gross Earnings

$786,050.83

$783,289.91

$2,760.92

Total Change Orders

$0.00

Other Adjustments

$0.00

$0.00

$0.00

TOTAL

$786,050.83

$783,289.91

$2,760.92

Contract Id 162168

Change Order Summary

County OWEN
Estimate Nbr 0007 Project Number FD05 094 0227 000-015
Contractor MAGO CONSTRUCTION COMPANY LLC Period 02/24/2018  TO  03/07/2018
 
 
CHANGE ORDERS HISTORY  
CHANGE ORDER NBR DESCRIPTION STATUS APPROVAL DATE TOTAL CO AMOUNT CONTRACT TIME ADJUSTED
 
 
 
 

CONTRACT ADJUSTMENTS HISTORY

Contract Adjustments

 

 

Adjustment Description

Est No

Adjustment Amount

Line Item Adjustments History
PROJECT ITEM NBR DESCRPITION TYPE EST NO

ADJ QUANTITY

UNIT PRICE

ADJUSTED AMOUNT

Contract Id 162168

COMMONWEALTH OF KENTUCKY

County OWEN
Contract No

TRANSPORTATION CABINET

Primary Project Number MP09402271602
Estimate Nbr 0007 Period 02/24/2018  TO  03/07/2018
Contractor MAGO CONSTRUCTION COMPANY LLC
 
Project MP09402271602 Fed/State Project Number FD05 094 0227 000-015 Category
LINE ITEM NUMBER ITEM DESCRIPTION ITEM NO. UNIT PLAN QTY CURRENT QUANTITY QUANTITY PAID THIS EST QUANTITY PAID PREV. EST QUANTITY PAID TO DATE UNIT PRICE AMOUNT PAID THIS EST AMOUNT PAID TO DATE
Project MP09402271602 Fed/State Project Number FD05 094 0227 000-015 Category 0001 PAVING
0005 LEVELING & WEDGING PG64-22 00190 TON 2,064.00 2,064.000 2,071.730 2,071.730 49.00 101,514.77
0010 ASPHALT MIX FOR PAVEMENT WEDGE 00263 TON 1,825.00 1,825.000 1,824.120 1,824.120 49.00 89,381.88
0015 CL2 ASPH SURF 0.38D PG64-22 00301 TON 10,035.00 10,035.000 10,072.070 10,072.070 49.00 493,531.43
0020 TEMPORARY SIGNS 02562 SQFT 450.00 450.000 408.000 408.000 3.00 1,224.00
0025 EDGE KEY 02585 LF 344.00 344.000 190.000 190.000 10.00 1,900.00
0030 MAINTAIN & CONTROL TRAFFIC 02650 LS 1.00 1.000 1.000 1.000 11,450.00 11,450.00
0035 PAVE STRIPING-TEMP PAINT-4 IN 06510 LF 20,000.00 20,000.000 66,237.000 66,237.000 0.18 11,922.66
0040 PAVE STRIPING-PERM PAINT-4 IN 06514 LF 242,489.00 242,489.000 295,773.000 295,773.000 0.14 41,408.22
0045 PAVE MARKING-THERMO STOP BAR-24IN 06568 LF 12.00 12.000 15.000 15.000 15.00 225.00
0050 FUEL ADJUSTMENT 10020NS DOLL 21,673.00 21,673.000 3,637.920 3,637.920 1.00 3,637.92
0055 ASPHALT ADJUSTMENT 10030NS DOLL 54,437.00 54,437.000 18,811.280 18,811.280 1.00 18,811.28
Project MP09402271602 Fed/State Project Number FD05 094 0227 000-015 Category 0002 DEMOBILIZATION
0060 DEMOBILIZATION 02569 LS 1.00 1.000 0.250 0.750 1.000 11,043.67 2,760.91 11,043.67

SUBTOT

$2,760.91

$786,050.83

LNNBR STOCKPILE ADJUSTMENTS

UNIT

ADJ. QUANTITY

EST NBR

UNIT PRICE

ADJUSTED AMOUNT

SUBTOT

$0.00