Report_Id: 143356 Est NO 0003 |
Date:07/02/2015 |
COMMONWEALTH OF KENTUCKY
TRANSPORTATION CABINET
Contract ID | 143356 | Estimate Number | 0003 | Estimate Type | PROGRESS | ||
District Office | COVINGTON (06340) Mitchell, Laura T. | ||||||
Contractor | EATON ASPHALT PAVING CO INC AND SUBSIDIARY | ADDR SN 1 VC Code VC0000019236 | |||||
AND SUBSIDIARY | |||||||
136 EAST FROGTOWN ROAD | |||||||
WALTON , KY , 41094 | |||||||
Pay Period | 05/08/2015 TO 06/04/2015 | ||||||
Date Approved | 06/15/2015 | ||||||
Primary Proj Number | 0600803381403 | ||||||
Project No. | CB06 008 0338 006-011, CB06 008 1292 000-005 | ||||||
Primary County | BOONE | ||||||
Name of Road | VARIOUS ROUTES IN BOONE COUNTY | ||||||
Description | VARIOUS ROUTES IN BOONE COUNTY | ||||||
Date Let | 08/22/2014 | Formal Acceptance | |||||
Date Awarded | 09/03/2014 | Date Work Began | 11/25/2014 | ||||
Date Contract Executed | 09/18/2014 | Open To Traffic | |||||
Date NTP Issued | 09/18/2014 | Actual Completion Date | |||||
Current Contract Amount | $677,540.00 |
Total to Date |
Prev to Date |
This Estimate |
||
Original Amount | $677,540.00 |
Total Earnings | $612,276.47 |
$330,968.78 |
$281,307.69 |
|
Percent Complete | 90.37 |
Stockpiled Materials | $0.00 |
$0.00 |
$0.00 |
|
Funds Available | $65,263.53 |
Gross Earnings | $612,276.47 |
$330,968.78 |
$281,307.69 |
|
Total Change Orders | $0.00 |
Other Adjustments | $0.00 |
$0.00 |
$0.00 |
|
TOTAL | $612,276.47 |
$330,968.78 |
$281,307.69 |
|||
Contract Id | 143356 | Change Order Summary |
County | BOONE | ||||||
Estimate Nbr | 0003 | Project Number | CB06 008 0338 006-011, CB06 008 1292 000-005 | |||||||
Contractor | EATON ASPHALT PAVING CO INC AND SUBSIDIARY | Period | 05/08/2015 TO 06/04/2015 | |||||||
CHANGE ORDERS HISTORY | ||||||||||
CHANGE ORDER NBR | DESCRIPTION | STATUS | APPROVAL DATE | TOTAL CO AMOUNT | CONTRACT TIME ADJUSTED | |||||
CONTRACT ADJUSTMENTS HISTORY
Contract Adjustments |
|
|
Adjustment Description | Est No |
Adjustment Amount |
Line Item Adjustments History | |||||||||
PROJECT | ITEM NBR | DESCRPITION | TYPE | EST NO | ADJ QUANTITY |
UNIT PRICE |
ADJUSTED AMOUNT |
Contract Id | 143356 | COMMONWEALTH OF KENTUCKY |
County | BOONE | ||||||
Contract Type | ASGD ASPHALT SURFACE WITH GRADE & DRAIN | TRANSPORTATION CABINET |
Primary Project Number | 0600803381403 | ||||||
Estimate Nbr | 0003 | Period | 05/08/2015 TO 06/04/2015 | |||||||
Contractor | EATON ASPHALT PAVING CO INC AND SUBSIDIARY | |||||||||
Project | 0600803381403 | Fed/State Project Number | CB06 008 0338 006-011 | Category | ||||||||
LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
Project | 0600803381403 | Fed/State Project Number | CB06 008 0338 006-011 | Category | 0001 PAVING | |||||||
0001 | LEVELING & WEDGING PG64-22 | 00190 | TON | 467.00 | 467.000 | 395.220 | 395.220 | 62.00 | 24,503.64 | |||
0002 | CL2 ASPH SURF 0.38D PG64-22 | 00301 | TON | 3,250.00 | 3,250.000 | 3,411.790 | 3,411.790 | 62.00 | 211,530.98 | |||
0003 | TEMPORARY SIGNS | 02562 | SQFT | 330.00 | 330.000 | 257.000 | 257.000 | 5.00 | 1,285.00 | |||
0004 | MAINTAIN & CONTROL TRAFFIC KY 338 | 02650 | LS | 1.00 | 1.000 | 0.050 | 0.950 | 1.000 | 12,671.00 | 633.55 | 12,671.00 | |
0005 | MOBILIZATION FOR MILL & TEXT KY 338 | 02676 | LS | 1.00 | 1.000 | 1.000 | 1.000 | 225.00 | 225.00 | |||
0006 | ASPHALT PAVE MILLING & TEXTURING | 02677 | TON | 75.00 | 75.000 | 103.300 | 103.300 | 45.00 | 4,648.50 | |||
0007 | BASE FAILURE REPAIR | 03240 | SQYD | 27.00 | 27.000 | 43.440 | 43.440 | 181.00 | 7,862.64 | |||
0008 | PAVE STRIPING-TEMP PAINT-4 IN | 06510 | LF | 36,369.00 | 36,369.000 | 0.000 | 0.000 | 0.01 | 0.00 | |||
0009 | PAVE STRIPING-PERM PAINT-4 IN | 06514 | LF | 90,922.00 | 90,922.000 | 83,207.000 | 83,207.000 | 0.16 | 13,313.12 | |||
0010 | PAVE MARKING-THERMO CURV ARROW | 06574 | EACH | 2.00 | 2.000 | 2.000 | 0.000 | 2.000 | 140.00 | 280.00 | 280.00 | |
0011 | FUEL ADJUSTMENT | 10020NS | DOLL | 5,080.00 | 5,080.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
0012 | ASPHALT ADJUSTMENT | 10030NS | DOLL | 8,952.00 | 8,952.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
Project | 0600803381403 | Fed/State Project Number | CB06 008 0338 006-011 | Category | 0002 DEMOBILIZATION | |||||||
0013 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 3,930.08 | 0.00 | |||
SUBTOT | $913.55 |
$276,319.88 |
||||||||||
LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
SUBTOT | $0.00 |
Project | 0600812921401 | Fed/State Project Number | CB06 008 1292 000-005 | Category | ||||||||
LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
Project | 0600812921401 | Fed/State Project Number | CB06 008 1292 000-005 | Category | 0001 PAVING | |||||||
0001 | LEVELING & WEDGING PG64-22 | 00190 | TON | 528.00 | 528.000 | 593.240 | 0.000 | 593.240 | 62.00 | 36,780.88 | 36,780.88 | |
0002 | CL2 ASPH SURF 0.38D PG64-22 | 00301 | TON | 3,680.00 | 3,680.000 | 3,563.440 | 0.000 | 3,563.440 | 62.00 | 220,933.28 | 220,933.28 | |
0003 | TEMPORARY SIGNS | 02562 | SQFT | 290.00 | 290.000 | 241.000 | 241.000 | 5.00 | 1,205.00 | |||
0004 | MAINTAIN & CONTROL TRAFFIC KY 1292 | 02650 | LS | 1.00 | 1.000 | 0.750 | 0.250 | 1.000 | 11,803.00 | 8,852.25 | 11,803.00 | |
0005 | MOBILIZATION FOR MILL & TEXT KY 1292 | 02676 | LS | 1.00 | 1.000 | 1.000 | 1.000 | 225.00 | 225.00 | |||
0006 | ASPHALT PAVE MILLING & TEXTURING | 02677 | TON | 85.00 | 85.000 | 43.010 | 77.020 | 120.030 | 45.00 | 1,935.45 | 5,401.35 | |
0007 | PAVE STRIPING-TEMP PAINT-4 IN | 06510 | LF | 31,537.00 | 31,537.000 | 5,132.000 | 0.000 | 5,132.000 | 0.01 | 51.32 | 51.32 | |
0008 | PAVE STRIPING-PERM PAINT-4 IN | 06514 | LF | 78,841.00 | 78,841.000 | 74,006.000 | 0.000 | 74,006.000 | 0.16 | 11,840.96 | 11,840.96 | |
0009 | FUEL ADJUSTMENT | 10020NS | DOLL | 5,753.00 | 5,753.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
0010 | ASPHALT ADJUSTMENT | 10030NS | DOLL | 10,138.00 | 10,138.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
Project | 0600812921401 | Fed/State Project Number | CB06 008 1292 000-005 | Category | 0002 DEMOBILIZATION | |||||||
0011 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 5,669.78 | 0.00 | |||
Project | 0600812921401 | Fed/State Project Number | CB06 008 1292 000-005 | Category | 0003 DRAINAGE | |||||||
0012 | CULVERT PIPE-24 IN | 00464 | LF | 315.00 | 315.000 | 295.000 | 295.000 | 123.00 | 36,285.00 | |||
0013 | CULVERT PIPE-36 IN | 00468 | LF | 70.00 | 70.000 | 0.000 | 0.000 | 132.00 | 0.00 | |||
0014 | CULVERT PIPE-36 IN EQUIV | 00496 | LF | 40.00 | 40.000 | 36.000 | 36.000 | 200.00 | 7,200.00 | |||
0015 | DROP BOX INLET TYPE 1 | 01490 | EACH | 3.00 | 3.000 | 0.000 | 0.000 | 3,000.00 | 0.00 | |||
0016 | CHANNEL LINING CLASS II | 02483 | TON | 220.00 | 220.000 | 34.520 | 34.520 | 40.00 | 1,380.80 | |||
0017 | DITCHING AND SHOULDERING | 02575 | LF | 950.00 | 950.000 | 950.000 | 950.000 | 3.00 | 2,850.00 | |||
0018 | SAFELOADING | 02690 | CUYD | 6.00 | 6.000 | 0.000 | 0.000 | 300.00 | 0.00 | |||
SUBTOT | $280,394.14 |
$612,276.47 |
||||||||||
LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
SUBTOT | $0.00 |