Report_Id: 132029 Est NO 0003 |
Date:09/04/2013 |
COMMONWEALTH OF KENTUCKY
TRANSPORTATION CABINET
| Contract ID | 132029 | Estimate Number | 0003 | Estimate Type | PROGRESS | ||
| District Office | SOMERSET (08300) Gilreath, Stewart B. P.E. | ||||||
| Contractor | HINKLE CONTRACTING COMPANY LLC | ADDR SN 0 VC Code VC0000092418 | |||||
| PO BOX 200 | |||||||
| PARIS , KY , 40362 | |||||||
| Pay Period | 06/18/2013 TO 08/23/2013 | ||||||
| Date Approved | 09/04/2013 | ||||||
| Primary Proj Number | MP10000701301 | ||||||
| Project No. | FD05 100 0070 002-004, FD05 100 0192 000-002 | ||||||
| Primary County | PULASKI | ||||||
| Name of Road | KY 70 AND KY 192 IN PULASKI COUNTY | ||||||
| Description | KY 70 AND KY 192 IN PULASKI COUNTY | ||||||
| Date Let | 03/22/2013 | Formal Acceptance | |||||
| Date Awarded | 04/03/2013 | Date Work Began | 05/30/2013 | ||||
| Date Contract Executed | 04/17/2013 | Open To Traffic | |||||
| Date NTP Issued | 04/17/2013 | Actual Completion Date | 08/26/2013 | ||||
| Current Contract Amount | $204,058.10 |
Total to Date |
Prev to Date |
This Estimate |
||
| Original Amount | $204,058.10 |
Total Earnings | $203,029.40 |
$191,916.43 |
$11,112.97 |
|
| Percent Complete | 99.50 |
Stockpiled Materials | $0.00 |
$0.00 |
$0.00 |
|
| Funds Available | $1,028.70 |
Gross Earnings | $203,029.40 |
$191,916.43 |
$11,112.97 |
|
| Total Change Orders | $0.00 |
Other Adjustments | $0.00 |
$0.00 |
$0.00 |
|
| TOTAL | $203,029.40 |
$191,916.43 |
$11,112.97 |
|||
| Contract Id | 132029 | Change Order Summary |
County | PULASKI | ||||||
| Estimate Nbr | 0003 | Project Number | FD05 100 0070 002-004, FD05 100 0192 000-002 | |||||||
| Contractor | HINKLE CONTRACTING COMPANY LLC | Period | 06/18/2013 TO 08/23/2013 | |||||||
| CHANGE ORDERS HISTORY | ||||||||||
| CHANGE ORDER NBR | DESCRIPTION | STATUS | APPROVAL DATE | TOTAL CO AMOUNT | CONTRACT TIME ADJUSTED | |||||
| 001 | Milling Reimbursement Override | Approved | 06/18/2013 | $0.00 | 0.0 | |||||
CONTRACT ADJUSTMENTS HISTORY
| Contract Adjustments |
|
|
| Adjustment Description | Est No |
Adjustment Amount |
| Line Item Adjustments History | |||||||||
| PROJECT | ITEM NBR | DESCRPITION | TYPE | EST NO | ADJ QUANTITY |
UNIT PRICE |
ADJUSTED AMOUNT |
||
| Contract Id | 132029 | COMMONWEALTH OF KENTUCKY |
County | PULASKI | ||||||
| Contract Type | ASRS ASPHALT RESURFACING | TRANSPORTATION CABINET |
Primary Project Number | MP10000701301 | ||||||
| Estimate Nbr | 0003 | Period | 06/18/2013 TO 08/23/2013 | |||||||
| Contractor | HINKLE CONTRACTING COMPANY LLC | |||||||||
| Project | MP10000701301 | Fed/State Project Number | FD05 100 0070 002-004 | Category | ||||||||
| LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
| Project | MP10000701301 | Fed/State Project Number | FD05 100 0070 002-004 | Category | 0001 ROADWAY | |||||||
| 0010 | LEVELING & WEDGING PG64-22 | 00190 | TON | 99.00 | 99.000 | 102.080 | 102.080 | 80.00 | 8,166.40 | |||
| 0020 | ASPHALT MIX FOR PAVEMENT WEDGE | 00263 | TON | 50.00 | 50.000 | 50.000 | 50.000 | 77.00 | 3,850.00 | |||
| 0030 | CL2 ASPH SURF 0.38D PG64-22 | 00301 | TON | 505.00 | 505.000 | 496.440 | 496.440 | 77.00 | 38,225.88 | |||
| 0040 | TEMPORARY SIGNS | 02562 | SQFT | 290.00 | 290.000 | 192.000 | 192.000 | 8.00 | 1,536.00 | |||
| 0050 | MAINTAIN & CONTROL TRAFFIC (KY 70) | 02650 | LS | 1.00 | 1.000 | 1.000 | 1.000 | 350.00 | 350.00 | |||
| 0060 | MOBILIZATION FOR MILL & TEXT (KY 70) | 02676 | LS | 1.00 | 1.000 | 1.000 | 1.000 | 1,800.00 | 1,800.00 | |||
| 0070 | ASPHALT PAVE MILLING & TEXTURING | 02677 | TON | 15.00 | 15.000 | 14.150 | 14.150 | 165.00 | 2,334.75 | |||
| 0080 | PAVE STRIPING-TEMP PAINT-4 IN | 06510 | LF | 5,000.00 | 5,000.000 | 0.000 | 0.000 | 0.01 | 0.00 | |||
| 0090 | PAVE STRIPING-PERM PAINT-4 IN | 06514 | LF | 12,430.00 | 12,430.000 | 11,273.000 | 11,273.000 | 0.17 | 1,916.41 | |||
| 8000 | MILLING REIMBURSEMENT | 24256EN | DOLL | 0.00 | 0.001 | -106.125 | 0.000 | -106.125 | 1.00 | -106.12 | -106.12 | |
| Project | MP10000701301 | Fed/State Project Number | FD05 100 0070 002-004 | Category | 0002 DEMOBILIZATION | |||||||
| 0100 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 881.98 | 0.00 | |||
| SUBTOT | $-106.12 |
$58,073.31 |
||||||||||
| LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
| SUBTOT | $0.00 |
|||||||||||
| Project | MP10001921301 | Fed/State Project Number | FD05 100 0192 000-002 | Category | ||||||||
| LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
| Project | MP10001921301 | Fed/State Project Number | FD05 100 0192 000-002 | Category | 0001 ROADWAY | |||||||
| 0010 | ASPHALT SEAL AGGREGATE | 00100 | TON | 103.00 | 103.000 | 63.260 | 0.000 | 63.260 | 105.00 | 6,642.30 | 6,642.30 | |
| 0020 | LEVELING & WEDGING PG64-22 | 00190 | TON | 199.00 | 199.000 | 200.900 | 200.900 | 80.00 | 16,072.00 | |||
| 0030 | ASPHALT MIX FOR PAVEMENT WEDGE | 00263 | TON | 130.00 | 130.000 | 130.000 | 130.000 | 77.00 | 10,010.00 | |||
| 0040 | EMULSIFIED ASPHALT RS-2 | 00291 | TON | 12.00 | 12.000 | 7.590 | 0.000 | 7.590 | 700.00 | 5,313.00 | 5,313.00 | |
| 0050 | CL2 ASPH SURF 0.38D PG64-22 | 00301 | TON | 970.00 | 970.000 | 1,036.520 | 1,036.520 | 77.00 | 79,812.04 | |||
| 0060 | TEMPORARY SIGNS | 02562 | SQFT | 250.00 | 250.000 | 224.000 | 224.000 | 8.00 | 1,792.00 | |||
| 0070 | MAINTAIN & CONTROL TRAFFIC (KY 192) | 02650 | LS | 1.00 | 1.000 | -0.100 | 1.000 | 0.900 | 900.00 | -90.00 | 810.00 | |
| 0080 | MOBILIZATION FOR MILL & TEXT (KY 192) | 02676 | LS | 1.00 | 1.000 | 1.000 | 1.000 | 1,800.00 | 1,800.00 | |||
| 0090 | ASPHALT PAVE MILLING & TEXTURING | 02677 | TON | 36.00 | 36.000 | 86.000 | 86.000 | 165.00 | 14,190.00 | |||
| 0100 | LOOP WIRE | 04830 | LF | 1,600.00 | 1,600.000 | 1,440.000 | 1,440.000 | 0.28 | 403.20 | |||
| 0110 | CABLE-NO. 14/1 PAIR | 04850 | LF | 600.00 | 600.000 | 0.000 | 0.000 | 1.12 | 0.00 | |||
| 0120 | LOOP SAW SLOT AND FILL (REVISED: 3-20-13) | 04895 | LF | 600.00 | 600.000 | 502.000 | 502.000 | 6.70 | 3,363.40 | |||
| 0130 | PAVE STRIPING-TEMP PAINT-4 IN | 06510 | LF | 13,000.00 | 13,000.000 | 766.000 | 766.000 | 0.01 | 7.66 | |||
| 0140 | PAVE STRIPING-PERM PAINT-4 IN | 06514 | LF | 25,000.00 | 25,000.000 | 24,157.000 | 24,157.000 | 0.17 | 4,106.69 | |||
| 0150 | PAVE MARKING-THERMO STOP BAR-24IN | 06568 | LF | 60.00 | 60.000 | 60.000 | 60.000 | 15.00 | 900.00 | |||
| 0160 | PAVE MARKING-THERMO CURV ARROW | 06574 | EACH | 4.00 | 4.000 | 4.000 | 4.000 | 95.00 | 380.00 | |||
| 8000 | MILLING REIMBURSEMENT | 24256EN | DOLL | 0.00 | 0.001 | -646.200 | 0.000 | -646.200 | 1.00 | -646.20 | -646.20 | |
| Project | MP10001921301 | Fed/State Project Number | FD05 100 0192 000-002 | Category | 0002 DEMOBILIZATION | |||||||
| 0170 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 2,138.02 | 0.00 | |||
| SUBTOT | $11,219.10 |
$203,029.40 |
||||||||||
| LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
| SUBTOT | $0.00 |
|||||||||||