Report_Id:ESTIMATE FINAL updated 6-26-09

Date:07/17/2013

COMMONWEALTH OF KENTUCKY

TRANSPORTATION CABINET


Contract ID 123323 Estimate Number 0007 Estimate Type  FINAL
District Office COVINGTON (06380)  Hammer, Lee A. PE

Contractor EATON ASPHALT PAVING CO INC AND SUBSIDIARY ADDR SN 1 VC Code VC0000019236
AND SUBSIDIARY
1075 EATON DR
COVINGTON , KY , 41017-9655
Pay Period 03/09/2013  TO  06/10/2013
Date Approved 07/15/2013
Primary Proj Number 0609403681201
Project No. CB06 094 0368 005-007, CB06 094 0845 000-006, CB06 094 3215 001-005
Primary County OWEN
Name of Road VARIOUS ROUTES IN OWEN COUNTY
Description VARIOUS ROUTES IN OWEN COUNTY
     
     
Date Let 07/13/2012 Formal Acceptance 09/24/2012
Date Awarded 07/25/2012 Date Work Began 09/04/2012
Date Contract Executed 08/08/2012 Open To Traffic 09/24/2012
Date NTP Issued 08/08/2012 Actual Completion Date 09/24/2012

Current Contract Amount

$453,377.00

Total to Date

Prev to Date

This Estimate

Original Amount

$453,377.00

Total Earnings

$437,523.88

$435,926.15

$1,597.73

Percent Complete

96.50

Stockpiled Materials

$0.00

$0.00

$0.00

Funds Available

$15,853.12

Gross Earnings

$437,523.88

$435,926.15

$1,597.73

Total Change Orders

$0.00

Other Adjustments

$0.00

$0.00

$0.00

TOTAL

$437,523.88

$435,926.15

$1,597.73

Contract Id 123323

Change Order Summary

County OWEN
Estimate Nbr 0007 Project Number CB06 094 0368 005-007, CB06 094 0845 000-006, CB06 094 3215 001-005
Contractor EATON ASPHALT PAVING CO INC AND SUBSIDIARY Period 03/09/2013  TO  06/10/2013
 
 
CHANGE ORDERS HISTORY  
CHANGE ORDER NBR DESCRIPTION STATUS APPROVAL DATE TOTAL CO AMOUNT CONTRACT TIME ADJUSTED
001 Non Spec Material Override Approved 10/29/2012 $0.00 0.0
 
 
 
 

CONTRACT ADJUSTMENTS HISTORY

Contract Adjustments

 

 

Adjustment Description

Est No

Adjustment Amount

Line Item Adjustments History
PROJECT ITEM NBR DESCRPITION TYPE EST NO

ADJ QUANTITY

UNIT PRICE

ADJUSTED AMOUNT

Contract Id 123323

COMMONWEALTH OF KENTUCKY

County OWEN
Contract No

TRANSPORTATION CABINET

Primary Project Number 0609403681201
Estimate Nbr 0007 Period 03/09/2013  TO  06/10/2013
Contractor EATON ASPHALT PAVING CO INC AND SUBSIDIARY
 
Project 0609403681201 Fed/State Project Number CB06 094 0368 005-007 Category 0001 ROADWAY
LINE ITEM NUMBER ITEM DESCRIPTION ITEM NO. UNIT PLAN QTY CURRENT QUANTITY QUANTITY PAID THIS EST QUANTITY PAID PREV. EST QUANTITY PAID TO DATE UNIT PRICE AMOUNT PAID THIS EST AMOUNT PAID TO DATE
0010 SIGNS 02562 SQFT 190.00 190.000 124.000 124.000 4.00 496.00
0020 MAINTAIN & CONTROL TRAFFIC KY 368 02650 LS 1.00 1.000 1.000 1.000 1,000.00 1,000.00
0030 CL2 ASPH SURF 0.38D PG64-22 00301 TON 960.00 960.000 960.150 960.150 55.85 53,624.37
0040 MOBILIZATION FOR MILL & TEXT KY 368 02676 LS 1.00 1.000 1.000 1.000 500.00 500.00
0050 ASPHALT PAVE MILLING & TEXTURING 02677 TON 53.00 53.000 34.820 34.820 15.00 522.30
0060 LEVELING & WEDGING PG64-22 00190 TON 126.00 126.000 126.290 126.290 56.00 7,072.24
0070 PAVE STRIPING-PERM PAINT-4 IN 06514 LF 15,200.00 15,200.000 14,542.000 14,542.000 0.17 2,472.14
0080 PAVE STRIPING-TEMP PAINT-4 IN 06510 LF 5,000.00 5,000.000 0.000 0.000 0.01 0.00
0090 ASPHALT ADJUSTMENT 10030NS DOLL 2,602.00 2,602.000 0.000 0.000 1.00 0.00
0100 FUEL ADJUSTMENT 10020NS DOLL 1,476.00 1,476.000 981.220 981.220 1.00 981.22
Project 0609403681201 Fed/State Project Number CB06 094 0368 005-007 Category 0002 DEMOBILIZATION
0110 DEMOBILIZATION 02569 LS 1.00 1.000 0.250 0.750 1.000 1,006.98 251.74 1,006.98

SUBTOT

$251.74

$67,675.26

LNNBR STOCKPILE ADJUSTMENTS

UNIT

ADJ. QUANTITY

EST NBR

UNIT PRICE

ADJUSTED AMOUNT

SUBTOT

$0.00

 

 

 

Project 0609408451201 Fed/State Project Number CB06 094 0845 000-006 Category 0001 RDWY
LINE ITEM NUMBER ITEM DESCRIPTION ITEM NO. UNIT PLAN QTY CURRENT QUANTITY QUANTITY PAID THIS EST QUANTITY PAID PREV. EST QUANTITY PAID TO DATE UNIT PRICE AMOUNT PAID THIS EST AMOUNT PAID TO DATE
0010 SIGNS 02562 SQFT 150.00 150.000 108.000 108.000 4.00 432.00
0020 MAINTAIN & CONTROL TRAFFIC KY 845 02650 LS 1.00 1.000 1.000 1.000 1,000.00 1,000.00
0030 CL2 ASPH SURF 0.38D PG64-22 00301 TON 3,475.00 3,475.000 3,867.060 3,867.060 55.85 215,975.30
0040 EDGE KEY 02585 LF 60.00 60.000 60.000 60.000 15.00 900.00
0050 LEVELING & WEDGING PG64-22 00190 TON 228.00 228.000 413.340 413.340 56.00 23,147.04
0060 PAVE STRIPING-PERM PAINT-4 IN 06514 LF 109,812.00 109,812.000 56,154.000 56,154.000 0.17 9,546.18
0070 PAVE STRIPING-TEMP PAINT-4 IN 06510 LF 71,380.00 71,380.000 0.000 0.000 0.01 0.00
0080 ASPHALT ADJUSTMENT 10030NS DOLL 8,921.00 8,921.000 0.000 0.000 1.00 0.00
0090 FUEL ADJUSTMENT 10020NS DOLL 5,062.00 5,062.000 3,865.850 3,865.850 1.00 3,865.85
8000 NON-SPEC MATERIAL - 10070NS DOLL 0.00 0.001 -12,467.980 -12,467.980 1.00 -12,467.98
Project 0609408451201 Fed/State Project Number CB06 094 0845 000-006 Category 0002 ZEMO
0100 DEMOBILIZATION 02569 LS 1.00 1.000 0.250 0.750 1.000 3,477.22 869.30 3,477.22

SUBTOT

$869.30

$313,550.88

LNNBR STOCKPILE ADJUSTMENTS

UNIT

ADJ. QUANTITY

EST NBR

UNIT PRICE

ADJUSTED AMOUNT

SUBTOT

$0.00

 

 

 

Project 0609432151201 Fed/State Project Number CB06 094 3215 001-005 Category 0001 RDWY
LINE ITEM NUMBER ITEM DESCRIPTION ITEM NO. UNIT PLAN QTY CURRENT QUANTITY QUANTITY PAID THIS EST QUANTITY PAID PREV. EST QUANTITY PAID TO DATE UNIT PRICE AMOUNT PAID THIS EST AMOUNT PAID TO DATE
0010 SIGNS 02562 SQFT 150.00 150.000 2.000 150.000 152.000 4.00 8.00 608.00
0020 MAINTAIN & CONTROL TRAFFIC KY 3215 02650 LS 1.00 1.000 1.000 1.000 1,100.00 1,100.00
0030 CL2 ASPH SURF 0.38D PG64-22 00301 TON 1,990.00 1,990.000 1,887.430 1,887.430 55.85 105,412.96
0040 EDGE KEY 02585 LF 45.00 45.000 32.000 32.000 15.00 480.00
0050 LEVELING & WEDGING PG64-22 00190 TON 130.00 130.000 129.710 129.710 56.00 7,263.76
0060 PAVE STRIPING-PERM PAINT-4 IN 06514 LF 31,500.00 31,500.000 31,834.000 31,834.000 0.17 5,411.78
0070 PAVE STRIPING-TEMP PAINT-4 IN 06510 LF 5,000.00 5,000.000 0.000 0.000 0.01 0.00
0080 ASPHALT ADJUSTMENT 10030NS DOLL 4,891.00 4,891.000 0.000 0.000 1.00 0.00
0090 FUEL ADJUSTMENT 10020NS DOLL 2,775.00 2,775.000 1,821.780 1,821.780 1.00 1,821.78
Project 0609432151201 Fed/State Project Number CB06 094 3215 001-005 Category 0002 ZEMO
0100 DEMOBILIZATION 02569 LS 1.00 1.000 0.250 0.750 1.000 1,874.69 468.67 1,874.69

SUBTOT

$476.67

$437,523.86

LNNBR STOCKPILE ADJUSTMENTS

UNIT

ADJ. QUANTITY

EST NBR

UNIT PRICE

ADJUSTED AMOUNT

SUBTOT

$0.00