Report_Id:ESTIMATE FINAL updated 6-26-09

Date:07/17/2013

COMMONWEALTH OF KENTUCKY

TRANSPORTATION CABINET


Contract ID 123213 Estimate Number 0003 Estimate Type  FINAL
District Office FLEMINGSBURG (09340)  Gillum, Brian S., P.E.

Contractor THE WALKER COMPANY OF KENTUCKY INC ADDR SN 2 VC Code VC0000088141
PO BOX 308
MT STERLING , KY , 40353
Pay Period 11/17/2012  TO  06/28/2013
Date Approved 07/15/2013
Primary Proj Number 0900611981201
Project No. CB06 006 0965 003-008, CB06 006 1198 000-001, CB06 091 1198 000-001
Primary County BATH
Name of Road VARIOUS ROUTES IN BATH AND NICHOLAS COUNTY
Description VARIOUS ROUTES IN BATH AND NICHOLAS COUNTY
     
     
Date Let 06/15/2012 Formal Acceptance 01/18/2013
Date Awarded 06/27/2012 Date Work Began 10/19/2012
Date Contract Executed 07/12/2012 Open To Traffic 11/15/2012
Date NTP Issued 07/12/2012 Actual Completion Date 11/15/2012

Current Contract Amount

$469,090.05

Total to Date

Prev to Date

This Estimate

Original Amount

$469,090.05

Total Earnings

$447,637.12

$425,204.69

$22,432.43

Percent Complete

95.43

Stockpiled Materials

$0.00

$0.00

$0.00

Funds Available

$21,452.93

Gross Earnings

$447,637.12

$425,204.69

$22,432.43

Total Change Orders

$0.00

Other Adjustments

$0.00

$0.00

$0.00

TOTAL

$447,637.12

$425,204.69

$22,432.43

Contract Id 123213

Change Order Summary

County BATH
Estimate Nbr 0003 Project Number CB06 006 0965 003-008, CB06 006 1198 000-001, CB06 091 1198 000-001
Contractor THE WALKER COMPANY OF KENTUCKY INC Period 11/17/2012  TO  06/28/2013
 
 
CHANGE ORDERS HISTORY  
CHANGE ORDER NBR DESCRIPTION STATUS APPROVAL DATE TOTAL CO AMOUNT CONTRACT TIME ADJUSTED
 
 
 
 

CONTRACT ADJUSTMENTS HISTORY

Contract Adjustments

 

 

Adjustment Description

Est No

Adjustment Amount

Line Item Adjustments History
PROJECT ITEM NBR DESCRPITION TYPE EST NO

ADJ QUANTITY

UNIT PRICE

ADJUSTED AMOUNT

Contract Id 123213

COMMONWEALTH OF KENTUCKY

County BATH
Contract No

TRANSPORTATION CABINET

Primary Project Number 0900611981201
Estimate Nbr 0003 Period 11/17/2012  TO  06/28/2013
Contractor THE WALKER COMPANY OF KENTUCKY INC
 
Project 0900609651201 Fed/State Project Number CB06 006 0965 003-008 Category 0001 ROADWAY
LINE ITEM NUMBER ITEM DESCRIPTION ITEM NO. UNIT PLAN QTY CURRENT QUANTITY QUANTITY PAID THIS EST QUANTITY PAID PREV. EST QUANTITY PAID TO DATE UNIT PRICE AMOUNT PAID THIS EST AMOUNT PAID TO DATE
0010 DGA BASE 00001 TON 575.00 575.000 608.790 608.790 26.75 16,285.13
0020 LEVELING & WEDGING PG64-22 00190 TON 571.00 571.000 570.640 570.640 83.40 47,591.37
0030 CL2 ASPH SURF 0.38D PG64-22 00301 TON 2,900.00 2,900.000 2,854.560 2,854.560 83.40 238,070.30
0040 SIGNS 02562 SQFT 190.00 190.000 190.000 190.000 9.00 1,710.00
0050 MAINTAIN & CONTROL TRAFFIC KY 965 02650 LS 1.00 1.000 1.000 1.000 3,500.00 3,500.00
0060 MOBILIZATION FOR MILL & TEXT KY 965 02676 LS 1.00 1.000 1.000 1.000 2,000.00 2,000.00
0070 ASPHALT PAVE MILLING & TEXTURING 02677 TON 24.00 24.000 24.000 24.000 190.00 4,560.00
0080 PAVE STRIPING-TEMP PAINT-4 IN 06510 LF 1,000.00 1,000.000 8,268.000 8,268.000 0.25 2,067.00
0090 PAVE STRIPING-PERM PAINT-4 IN 06514 LF 28,100.00 28,100.000 8,933.000 18,759.000 27,692.000 0.25 2,233.25 6,923.00
0100 FUEL ADJUSTMENT 10020NS DOLL 4,745.00 4,745.000 3,531.210 0.000 3,531.210 1.00 3,531.21 3,531.21
0110 ASPHALT ADJUSTMENT 10030NS DOLL 8,362.00 8,362.000 6,550.000 0.000 6,550.000 1.00 6,550.00 6,550.00
Project 0900609651201 Fed/State Project Number CB06 006 0965 003-008 Category 0002 DEMOBOLIZATION
0120 DEMOBILIZATION 02569 LS 1.00 1.000 1.000 0.000 1.000 5,235.62 5,235.62 5,235.62

SUBTOT

$17,550.08

$338,023.65

LNNBR STOCKPILE ADJUSTMENTS

UNIT

ADJ. QUANTITY

EST NBR

UNIT PRICE

ADJUSTED AMOUNT

SUBTOT

$0.00

 

 

 

Project 0900611981201 Fed/State Project Number CB06 006 1198 000-001 Category 0001 ROADWAY
LINE ITEM NUMBER ITEM DESCRIPTION ITEM NO. UNIT PLAN QTY CURRENT QUANTITY QUANTITY PAID THIS EST QUANTITY PAID PREV. EST QUANTITY PAID TO DATE UNIT PRICE AMOUNT PAID THIS EST AMOUNT PAID TO DATE
0010 DGA BASE 00001 TON 105.00 105.000 129.870 129.870 26.75 3,474.02
0020 LEVELING & WEDGING PG64-22 00190 TON 104.00 104.000 104.310 104.310 83.40 8,699.45
0030 CL2 ASPH SURF 0.38D PG64-22 00301 TON 530.00 530.000 490.030 490.030 83.40 40,868.50
0040 SIGNS 02562 SQFT 150.00 150.000 150.000 150.000 9.00 1,350.00
0050 EDGE KEY 02585 LF 20.00 20.000 20.000 20.000 70.00 1,400.00
0060 MAINTAIN & CONTROL TRAFFIC KY 1198 BATH 02650 LS 1.00 1.000 1.000 1.000 1,000.00 1,000.00
0070 PAVE STRIPING-TEMP PAINT-4 IN 06510 LF 2,500.00 2,500.000 0.000 0.000 0.25 0.00
0080 PAVE STRIPING-PERM PAINT-4 IN 06514 LF 7,920.00 7,920.000 6,392.000 6,392.000 0.25 1,598.00
0090 FUEL ADJUSTMENT 10020NS DOLL 867.00 867.000 607.390 0.000 607.390 1.00 607.39 607.39
0100 ASPHALT ADJUSTMENT 10030NS DOLL 1,527.00 1,527.000 1,136.000 0.000 1,136.000 1.00 1,136.00 1,136.00
Project 0900611981201 Fed/State Project Number CB06 006 1198 000-001 Category 0002 DEMOBOLIZATION
0110 DEMOBILIZATION 02569 LS 1.00 1.000 1.000 0.000 1.000 960.67 960.67 960.67

SUBTOT

$2,704.06

$399,117.69

LNNBR STOCKPILE ADJUSTMENTS

UNIT

ADJ. QUANTITY

EST NBR

UNIT PRICE

ADJUSTED AMOUNT

SUBTOT

$0.00

 

 

 

Project 0909111981201 Fed/State Project Number CB06 091 1198 000-001 Category 0001 ROADWAY
LINE ITEM NUMBER ITEM DESCRIPTION ITEM NO. UNIT PLAN QTY CURRENT QUANTITY QUANTITY PAID THIS EST QUANTITY PAID PREV. EST QUANTITY PAID TO DATE UNIT PRICE AMOUNT PAID THIS EST AMOUNT PAID TO DATE
0010 DGA BASE 00001 TON 115.00 115.000 129.440 129.440 26.75 3,462.52
0020 LEVELING & WEDGING PG64-22 00190 TON 117.00 117.000 117.920 117.920 83.40 9,834.52
0030 CL2 ASPH SURF 0.38D PG64-22 00301 TON 490.00 490.000 350.370 350.370 83.40 29,220.85
0040 SIGNS 02562 SQFT 150.00 150.000 150.000 150.000 9.00 1,350.00
0050 MAINTAIN & CONTROL TRAFFIC KY 1198 NICHOLAS 02650 LS 1.00 1.000 1.000 1.000 1,000.00 1,000.00
0080 PAVE STRIPING-TEMP PAINT-4 IN 06510 LF 2,500.00 2,500.000 0.000 0.000 0.25 0.00
0090 PAVE STRIPING-PERM PAINT-4 IN 06514 LF 6,700.00 6,700.000 5,893.000 5,893.000 0.25 1,473.25
0100 FUEL ADJUSTMENT 10020NS DOLL 830.00 830.000 478.570 0.000 478.570 1.00 478.57 478.57
0110 ASPHALT ADJUSTMENT 10030NS DOLL 1,462.00 1,462.000 896.000 0.000 896.000 1.00 896.00 896.00
Project 0909111981201 Fed/State Project Number CB06 091 1198 000-001 Category 0002 DEMOBILIZATION
0120 DEMOBILIZATION 02569 LS 1.00 1.000 1.000 0.000 1.000 803.69 803.69 803.69

SUBTOT

$2,178.26

$447,637.11

LNNBR STOCKPILE ADJUSTMENTS

UNIT

ADJ. QUANTITY

EST NBR

UNIT PRICE

ADJUSTED AMOUNT

SUBTOT

$0.00