Report_Id:ESTIMATE FINAL updated 6-26-09

Date:06/03/2013

COMMONWEALTH OF KENTUCKY

TRANSPORTATION CABINET


Contract ID 113370 Estimate Number 0003 Estimate Type  FINAL
District Office COVINGTON (06360)  Moore, Craig A.

Contractor MAGO CONSTRUCTION COMPANY LLC ADDR SN 1 VC Code VC0000088020
PO BOX 669
BARDSTOWN , KY , 40004
Pay Period 06/01/2012  TO  04/30/2013
Date Approved 06/03/2013
Primary Proj Number 0609603301101
Project No. CB06 096 0330 003-007
Primary County PENDLETON
Name of Road MORGAN CORINTH ROAD (KY 330)
Description FROM 0.300 MILE SE OF HARDIN ROAD SOUTH EXTENDING NE TO KY 1054
     
     
Date Let 09/23/2011 Formal Acceptance 05/22/2012
Date Awarded 10/05/2011 Date Work Began 05/15/2012
Date Contract Executed 10/13/2011 Open To Traffic 05/22/2012
Date NTP Issued 10/13/2011 Actual Completion Date 05/22/2012

Current Contract Amount

$91,677.34

Total to Date

Prev to Date

This Estimate

Original Amount

$91,677.34

Total Earnings

$90,519.94

$89,165.10

$1,354.84

Percent Complete

98.74

Stockpiled Materials

$0.00

$0.00

$0.00

Funds Available

$1,157.40

Gross Earnings

$90,519.94

$89,165.10

$1,354.84

Total Change Orders

$0.00

Other Adjustments

$0.00

$0.00

$0.00

TOTAL

$90,519.94

$89,165.10

$1,354.84

Contract Id 113370

Change Order Summary

County PENDLETON
Estimate Nbr 0003 Project Number CB06 096 0330 003-007
Contractor MAGO CONSTRUCTION COMPANY LLC Period 06/01/2012  TO  04/30/2013
 
 
CHANGE ORDERS HISTORY  
CHANGE ORDER NBR DESCRIPTION STATUS APPROVAL DATE TOTAL CO AMOUNT CONTRACT TIME ADJUSTED
 
 
 
 

CONTRACT ADJUSTMENTS HISTORY

Contract Adjustments

 

 

Adjustment Description

Est No

Adjustment Amount

Line Item Adjustments History
PROJECT ITEM NBR DESCRPITION TYPE EST NO

ADJ QUANTITY

UNIT PRICE

ADJUSTED AMOUNT

Contract Id 113370

COMMONWEALTH OF KENTUCKY

County PENDLETON
Contract No

TRANSPORTATION CABINET

Primary Project Number 0609603301101
Estimate Nbr 0003 Period 06/01/2012  TO  04/30/2013
Contractor MAGO CONSTRUCTION COMPANY LLC
 
Project 0609603301101 Fed/State Project Number CB06 096 0330 003-007 Category 0001 ROADWAY
LINE ITEM NUMBER ITEM DESCRIPTION ITEM NO. UNIT PLAN QTY CURRENT QUANTITY QUANTITY PAID THIS EST QUANTITY PAID PREV. EST QUANTITY PAID TO DATE UNIT PRICE AMOUNT PAID THIS EST AMOUNT PAID TO DATE
0010 SIGNS 02562 SQFT 150.00 150.000 0.000 0.000 3.00 0.00
0020 MAINTAIN & CONTROL TRAFFIC KY 330 02650 LS 1.00 1.000 1.000 1.000 750.00 750.00
0030 CL2 ASPH SURF 0.38D PG64-22 00301 TON 1,465.00 1,465.000 1,455.050 1,455.050 54.00 78,572.70
0040 LEVELING & WEDGING PG64-22 00190 TON 150.00 150.000 146.850 146.850 54.00 7,929.90
0050 ASPHALT PAVE MILLING & TEXTURING 02677 TON 15.00 15.000 15.000 15.000 7.50 112.50
0060 MOBILIZATION FOR MILL & TEXT KY 330 02676 LS 1.00 1.000 1.000 1.000 1,800.00 1,800.00
Project 0609603301101 Fed/State Project Number CB06 096 0330 003-007 Category 0002 DEMOBILIZATION
0090 DEMOBILIZATION 02569 LS 1.00 1.000 1.000 0.000 1.000 1,354.84 1,354.84 1,354.84

SUBTOT

$1,354.84

$90,519.94

LNNBR STOCKPILE ADJUSTMENTS

UNIT

ADJ. QUANTITY

EST NBR

UNIT PRICE

ADJUSTED AMOUNT

SUBTOT

$0.00