Report_Id:ESTIMATE FINAL updated 6-26-09 |
Date:03/29/2013 |
COMMONWEALTH OF KENTUCKY
TRANSPORTATION CABINET
Contract ID | 112222 | Estimate Number | 0003 | Estimate Type FINAL | |||
District Office | MADISIONVILLE (02340) Wyatt, Craig T. | ||||||
Contractor | TODD COUNTY CRUSHED STONE LLC D/B/A PENNYRILE ASPHALT | ADDR SN 0 VC Code VC0000116434 | |||||
4240 WEST JEFFERSON DAVIS HWY | |||||||
ELKTON , KY , 42220 | |||||||
Pay Period | 11/06/2011 TO 05/11/2012 | ||||||
Date Approved | 05/29/2012 | ||||||
Primary Proj Number | MP02401071101 | ||||||
Project No. | FD05 024 0107 019-026 | ||||||
Primary County | CHRISTIAN | ||||||
Name of Road | GREENVILLE ROAD (KY 107) | ||||||
Description | FROM KY 507 EXTENDING NORTH TO WOODBURN HAY ROAD | ||||||
Date Let | 06/17/2011 | Formal Acceptance | 10/17/2011 | ||||
Date Awarded | 06/29/2011 | Date Work Began | 08/10/2011 | ||||
Date Contract Executed | 08/01/2011 | Open To Traffic | 10/17/2011 | ||||
Date NTP Issued | 08/01/2011 | Actual Completion Date | 10/17/2011 | ||||
Current Contract Amount | $354,193.63 |
Total to Date |
Prev to Date |
This Estimate |
||
Original Amount | $354,193.63 |
Total Earnings | $321,662.63 |
$310,172.81 |
$11,489.82 |
|
Percent Complete | 90.82 |
Stockpiled Materials | $0.00 |
$0.00 |
$0.00 |
|
Funds Available | $32,531.00 |
Gross Earnings | $321,662.63 |
$310,172.81 |
$11,489.82 |
|
Total Change Orders | $0.00 |
Other Adjustments | $0.00 |
$0.00 |
$0.00 |
|
TOTAL | $321,662.63 |
$310,172.81 |
$11,489.82 |
|||
Contract Id | 112222 | Change Order Summary |
County | CHRISTIAN | ||||||
Estimate Nbr | 0003 | Project Number | FD05 024 0107 019-026 | |||||||
Contractor | TODD COUNTY CRUSHED STONE LLC D/B/A PENNYRILE ASPHALT | Period | 11/06/2011 TO 05/11/2012 | |||||||
CHANGE ORDERS HISTORY | ||||||||||
CHANGE ORDER NBR | DESCRIPTION | STATUS | APPROVAL DATE | TOTAL CO AMOUNT | CONTRACT TIME ADJUSTED | |||||
CONTRACT ADJUSTMENTS HISTORY
Contract Adjustments |
|
|
Adjustment Description | Est No |
Adjustment Amount |
Line Item Adjustments History | |||||||||
PROJECT | ITEM NBR | DESCRPITION | TYPE | EST NO | ADJ QUANTITY |
UNIT PRICE |
ADJUSTED AMOUNT |
Contract Id | 112222 | COMMONWEALTH OF KENTUCKY |
County | CHRISTIAN | ||||||
Contract No | C1, C2 | TRANSPORTATION CABINET |
Primary Project Number | MP02401071101 | ||||||
Estimate Nbr | 0003 | Period | 11/06/2011 TO 05/11/2012 | |||||||
Contractor | TODD COUNTY CRUSHED STONE LLC D/B/A PENNYRILE ASPHALT | |||||||||
Project | MP02401071101 | Fed/State Project Number | FD05 024 0107 019-026 | Category | 0001 ROADWAY | |||||||
LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
0010 | AGGREGATE FOR MAILBOX TURNOUTS | 00077 | TON | 100.00 | 100.000 | 27.090 | 27.090 | 15.00 | 406.35 | |||
0020 | LEVELING & WEDGING PG64-22 | 00190 | TON | 725.00 | 725.000 | 734.840 | 734.840 | 56.45 | 41,481.71 | |||
0030 | CL2 ASPH SURF 0.38D PG64-22 | 00301 | TON | 4,195.00 | 4,195.000 | 4,189.880 | 4,189.880 | 56.45 | 236,518.72 | |||
0040 | SIGNS | 02562 | SQFT | 470.00 | 470.000 | 508.000 | 508.000 | 5.00 | 2,540.00 | |||
0050 | MAINTAIN & CONTROL TRAFFIC | 02650 | LS | 1.00 | 1.000 | 1.000 | 0.000 | 1.000 | 4,500.00 | 4,500.00 | 4,500.00 | |
0060 | MOBILIZATION FOR MILL & TEXT | 02676 | LS | 1.00 | 1.000 | 1.000 | 1.000 | 2,100.00 | 2,100.00 | |||
0070 | ASPHALT PAVE MILLING & TEXTURING | 02677 | TON | 50.00 | 50.000 | 50.000 | 50.000 | 110.00 | 5,500.00 | |||
0080 | PAVE STRIPING-TEMP PAINT-4 IN | 06510 | LF | 18,205.00 | 18,205.000 | 20,842.000 | 20,842.000 | 0.19 | 3,959.98 | |||
0090 | PAVE STRIPING-PERM PAINT-4 IN | 06514 | LF | 91,500.00 | 91,500.000 | 9,227.000 | 26,648.000 | 35,875.000 | 0.22 | 2,029.94 | 7,892.50 | |
0100 | PAVE MARKING-THERMO X-WALK-12 IN | 06566 | LF | 160.00 | 160.000 | 75.000 | 75.000 | 9.25 | 693.75 | |||
0110 | PAVE MARKING-THERMO STOP BAR-24IN | 06568 | LF | 102.00 | 102.000 | 67.000 | 67.000 | 18.50 | 1,239.50 | |||
0120 | FUEL ADJUSTMENT | 10020NS | DOLL | 6,725.00 | 6,725.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
0130 | ASPHALT ADJUSTMENT | 10030NS | DOLL | 11,850.00 | 11,850.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
0140 | RUMBLE STRIPS-SAWED-12 IN | 23232EC | LF | 43,560.00 | 43,560.000 | 42,914.000 | 42,914.000 | 0.23 | 9,870.22 | |||
Project | MP02401071101 | Fed/State Project Number | FD05 024 0107 019-026 | Category | 0002 DEMOBILIZATION | |||||||
0150 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 1.000 | 0.000 | 1.000 | 4,959.88 | 4,959.88 | 4,959.88 | |
SUBTOT | $11,489.82 |
$321,662.62 |
||||||||||
LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
SUBTOT | $0.00 |