Report_Id:   112031   Est NO  0007

Date:03/28/2013

COMMONWEALTH OF KENTUCKY

TRANSPORTATION CABINET


Contract ID 112031 Estimate Number 0007 Estimate Type PROGRESS
District Office LEXINGTON (07300)  Renfroe, Katy E.

Contractor L-M ASPHALT PARTNERS LTD D/B/A ATS CONSTRUCTION ADDR SN 1 VC Code VC0000106272
PO BOX 11849
LEXINGTON , KY , 40578
Pay Period 07/26/2012  TO  02/06/2013
Date Approved 02/21/2013
Primary Proj Number MP03400271101
Project No. FD05 034 0027 003-006, FD05 034 1927 000-001
Primary County FAYETTE
Name of Road US 27 AND KY 1927 IN FAYETTE COUNTY
Description US 27 AND KY 1927 IN FAYETTE COUNTY
     
     
Date Let 02/18/2011 Formal Acceptance 07/18/2011
Date Awarded 03/01/2011 Date Work Began 05/04/2011
Date Contract Executed 03/17/2011 Open To Traffic 07/18/2011
Date NTP Issued 03/17/2011 Actual Completion Date 07/18/2011

Current Contract Amount

$1,300,831.90

Total to Date

Prev to Date

This Estimate

Original Amount

$1,298,534.59

Total Earnings

$1,174,184.42

$1,169,386.88

$4,797.54

Percent Complete

90.26

Stockpiled Materials

$0.00

$0.00

$0.00

Funds Available

$126,647.48

Gross Earnings

$1,174,184.42

$1,169,386.88

$4,797.54

Total Change Orders

$2,297.31

Other Adjustments

$0.00

$0.00

$0.00

TOTAL

$1,174,184.42

$1,169,386.88

$4,797.54

Contract Id 112031

Change Order Summary

County FAYETTE
Estimate Nbr 0007 Project Number FD05 034 0027 003-006, FD05 034 1927 000-001
Contractor L-M ASPHALT PARTNERS LTD D/B/A ATS CONSTRUCTION Period 07/26/2012  TO  02/06/2013
 
 
CHANGE ORDERS HISTORY  
CHANGE ORDER NBR DESCRIPTION STATUS APPROVAL DATE TOTAL CO AMOUNT CONTRACT TIME ADJUSTED
001 Lot Pay Adjustment Override Approved 05/03/2012 $0.00 0.0
002 Loop Lead In Feeder Approved 07/09/2012 $2,297.31 0.0
 
 
 
 

CONTRACT ADJUSTMENTS HISTORY

Contract Adjustments

 

 

Adjustment Description

Est No

Adjustment Amount

Line Item Adjustments History
PROJECT ITEM NBR DESCRPITION TYPE EST NO

ADJ QUANTITY

UNIT PRICE

ADJUSTED AMOUNT

Contract Id 112031

COMMONWEALTH OF KENTUCKY

County FAYETTE
Contract Type ASRS   ASPHALT RESURFACING

TRANSPORTATION CABINET

Primary Project Number MP03400271101
Estimate Nbr 0007 Period 07/26/2012  TO  02/06/2013
Contractor L-M ASPHALT PARTNERS LTD D/B/A ATS CONSTRUCTION
 
Project MP03400271101 Fed/State Project Number FD05 034 0027 003-006 Category 0001 ROADWAY
LINE ITEM NUMBER ITEM DESCRIPTION ITEM NO. UNIT PLAN QTY CURRENT QUANTITY QUANTITY PAID THIS EST QUANTITY PAID PREV. EST QUANTITY PAID TO DATE UNIT PRICE AMOUNT PAID THIS EST AMOUNT PAID TO DATE
0010 LEVELING & WEDGING PG64-22 00190 TON 314.00 314.000 420.700 420.700 68.95 29,007.26
0020 CL3 SMA SURF 0.38A PG76-22 00397 TON 7,260.00 7,260.000 6,512.300 6,512.300 96.10 625,832.03
0030 SIGNS 02562 SQFT 650.00 650.000 865.000 865.000 8.40 7,266.00
0040 MAINTAIN & CONTROL TRAFFIC US 127 02650 LS 1.00 1.000 1.000 1.000 26,260.00 26,260.00
0050 PORTABLE CHANGEABLE MESSAGE SIGN 02671 EACH 4.00 4.000 4.000 4.000 2,000.00 8,000.00
0060 MOBILIZATION FOR MILL & TEXT US 127 02676 LS 1.00 1.000 1.000 1.000 3,450.00 3,450.00
0070 ASPHALT PAVE MILLING & TEXTURING 02677 TON 6,860.00 6,860.000 6,069.480 6,069.480 19.00 115,320.12
0080 SIDEWALK-4 IN CONCRETE 02720 SQYD 175.00 175.000 124.300 124.300 205.00 25,481.50
0090 ARROW PANEL 02775 EACH 4.00 4.000 2.000 2.000 950.00 1,900.00
0100 LOOP WIRE 04830 LF 23,054.00 23,054.000 7,416.000 7,416.000 0.23 1,705.68
0110 CABLE-NO. 14/1 PAIR 04850 LF 3,120.00 3,120.000 3,184.000 3,184.000 1.35 4,298.40
0120 LOOP SAW SLOT AND FILL 04895 LF 8,937.00 8,937.000 2,636.000 2,636.000 7.50 19,770.00
0130 PAVE STRIPING-TEMP PAINT-4 IN 06510 LF 20,000.00 20,000.000 35,798.000 35,798.000 0.24 8,591.52
0140 PAVE STRIPING-PERM PAINT-4 IN 06514 LF 20,000.00 20,000.000 27,927.000 27,927.000 0.24 6,702.48
0150 PAVE MARKING-THERMO X-WALK-6 IN 06565 LF 3,290.00 3,290.000 15,864.000 15,864.000 2.50 39,660.00
0160 PAVE MARKING-THERMO STOP BAR-24IN 06568 LF 1,178.00 1,178.000 987.000 987.000 6.00 5,922.00
0170 PAVE MARKING-THERMO CROSS-HATCH 06569 SQFT 1,700.00 1,700.000 1,019.000 1,019.000 4.00 4,076.00
0180 PAVE MARKING-DOTTED LANE EXTEN 06572 LF 100.00 100.000 291.000 291.000 2.00 582.00
0190 PAVE MARKING-THERMO CURV ARROW 06574 EACH 33.00 33.000 42.000 42.000 70.00 2,940.00
0200 PAVEMENT MARKER TYPE V-MW 06589 EACH 420.00 420.000 190.000 190.000 19.50 3,705.00
0210 PAVEMENT MARKER TYPE V-BY 06591 EACH 460.00 460.000 772.000 772.000 19.50 15,054.00
0220 REMOVE PAVEMENT MARKER TYPE V 06600 EACH 800.00 800.000 800.000 800.000 5.00 4,000.00
0230 FUEL ADJUSTMENT 10020NS DOLL 9,808.00 9,808.000 3,263.420 3,263.420 1.00 3,263.42
0240 ASPHALT ADJUSTMENT 10030NS DOLL 17,283.00 17,283.000 30,788.150 30,788.150 1.00 30,788.15
0250 DETECTABLE WARNINGS 23158ES505 SQFT 960.00 960.000 841.000 841.000 24.00 20,184.00
0260 PAVE MARK THERMO-LANE REDUCTION ARROW 23607EC EACH 1.00 1.000 1.000 1.000 300.00 300.00
8000 LOT PAY ADJUSTMENT 10000NS DOLL 0.00 0.001 0.000 0.000 1.00 0.00
8001 CONDUIT-2 IN for loop lead in feeders 04795 LF 0.00 73.000 73.000 73.000 31.47 2,297.31
Project MP03400271101 Fed/State Project Number FD05 034 0027 003-006 Category 0002 DEMOBILIZATION
0270 DEMOBILIZATION 02569 LS 1.00 1.000 0.250 0.000 0.250 16,618.41 4,154.60 4,154.60

SUBTOT

$4,154.60

$1,020,511.47

LNNBR STOCKPILE ADJUSTMENTS

UNIT

ADJ. QUANTITY

EST NBR

UNIT PRICE

ADJUSTED AMOUNT

SUBTOT

$0.00

 

 

 

Project MP03419271101 Fed/State Project Number FD05 034 1927 000-001 Category 0001 ROADWAY
LINE ITEM NUMBER ITEM DESCRIPTION ITEM NO. UNIT PLAN QTY CURRENT QUANTITY QUANTITY PAID THIS EST QUANTITY PAID PREV. EST QUANTITY PAID TO DATE UNIT PRICE AMOUNT PAID THIS EST AMOUNT PAID TO DATE
0010 LEVELING & WEDGING PG64-22 00190 TON 164.00 164.000 163.860 163.860 68.95 11,298.14
0020 ASPHALT MIX FOR PAVEMENT WEDGE 00263 TON 75.00 75.000 104.740 104.740 70.45 7,378.93
0030 SIGNS 02562 SQFT 310.00 310.000 285.000 285.000 8.40 2,394.00
0040 MAINTAIN & CONTROL TRAFFIC KY 1927 02650 LS 1.00 1.000 1.000 1.000 1,560.00 1,560.00
0050 MOBILIZATION FOR MILL & TEXT KY 1927 02676 LS 1.00 1.000 1.000 1.000 1,725.00 1,725.00
0060 ASPHALT PAVE MILLING & TEXTURING 02677 TON 560.00 560.000 417.460 417.460 19.00 7,931.74
0070 ARROW PANEL 02775 EACH 2.00 2.000 0.000 0.000 950.00 0.00
0080 LOOP WIRE 04830 LF 1,280.00 1,280.000 1,014.000 1,014.000 0.23 233.22
0090 LOOP SAW SLOT AND FILL 04895 LF 465.00 465.000 351.000 351.000 7.50 2,632.50
0100 PAVE STRIPING-TEMP PAINT-4 IN 06510 LF 12,000.00 12,000.000 3,748.000 3,748.000 0.24 899.52
0110 PAVE STRIPING-PERM PAINT-4 IN 06514 LF 12,000.00 12,000.000 21,279.000 21,279.000 0.24 5,106.96
0120 PAVE MARKING-THERMO STOP BAR-24IN 06568 LF 104.00 104.000 85.000 85.000 6.00 510.00
0130 PAVE MARKING-THERMO CROSS-HATCH 06569 SQFT 1,370.00 1,370.000 1,159.000 1,159.000 4.00 4,636.00
0140 PAVE MARKING-THERMO STR ARROW 06573 EACH 2.00 2.000 2.000 2.000 65.00 130.00
0150 PAVE MARKING-THERMO CURV ARROW 06574 EACH 26.00 26.000 27.000 27.000 70.00 1,890.00
0160 FUEL ADJUSTMENT 10020NS DOLL 4,177.00 4,177.000 984.860 984.860 1.00 984.86
0170 ASPHALT ADJUSTMENT 10030NS DOLL 2,371.00 2,371.000 4,345.870 4,345.870 1.00 4,345.87
0180 CL3 ASPH SURF 0.38A PG64-22 22906ES403 TON 1,495.00 1,495.000 1,410.550 1,410.550 70.45 99,373.24
8000 LOT PAY ADJUSTMENT 10000NS DOLL 0.00 0.001 0.000 0.000 1.00 0.00
Project MP03419271101 Fed/State Project Number FD05 034 1927 000-001 Category 0002 DEMOBILIZATION
0190 DEMOBILIZATION 02569 LS 1.00 1.000 0.250 0.000 0.250 2,571.75 642.93 642.93

SUBTOT

$642.93

$1,174,184.41

LNNBR STOCKPILE ADJUSTMENTS

UNIT

ADJ. QUANTITY

EST NBR

UNIT PRICE

ADJUSTED AMOUNT

SUBTOT

$0.00