Report_Id: 153200 Est NO 0003 |
Date:06/22/2015 |
COMMONWEALTH OF KENTUCKY
TRANSPORTATION CABINET
| Contract ID | 153200 | Estimate Number | 0003 | Estimate Type | PROGRESS | ||
| District Office | MADISONVILLE (02360) West, Matthew B. | ||||||
| Contractor | J H RUDOLPH & CO INC AND SUBSIDIARIES | ADDR SN 0 VC Code VC0000025886 | |||||
| PO BOX 5226 | |||||||
| EVANSVILLE , IN , 47716-5226 | |||||||
| Pay Period | 04/24/2015 TO 05/07/2015 | ||||||
| Date Approved | 05/17/2015 | ||||||
| Primary Proj Number | 0203001401401 | ||||||
| Project No. | CB06 030 0140 000-003, CB06 030 0142 000-004, CB06 030 0657 000-001, CB06 030 0661 000-002, CB06 030 1207 002-006, CB06 030 2127 005-007 | ||||||
| Primary County | DAVIESS | ||||||
| Name of Road | VARIOUS ROUTES IN DAVIESS COUNTY | ||||||
| Description | VARIOUS ROUTES IN DAVIESS COUNTY | ||||||
| Date Let | 01/30/2015 | Formal Acceptance | |||||
| Date Awarded | 02/11/2015 | Date Work Began | 04/06/2015 | ||||
| Date Contract Executed | 03/13/2015 | Open To Traffic | |||||
| Date NTP Issued | 03/13/2015 | Actual Completion Date | 05/18/2015 | ||||
| Current Contract Amount | $906,220.62 |
Total to Date |
Prev to Date |
This Estimate |
||
| Original Amount | $906,220.62 |
Total Earnings | $738,377.17 |
$389,403.71 |
$348,973.46 |
|
| Percent Complete | 81.48 |
Stockpiled Materials | $0.00 |
$0.00 |
$0.00 |
|
| Funds Available | $167,843.45 |
Gross Earnings | $738,377.17 |
$389,403.71 |
$348,973.46 |
|
| Total Change Orders | $0.00 |
Other Adjustments | $0.00 |
$0.00 |
$0.00 |
|
| TOTAL | $738,377.17 |
$389,403.71 |
$348,973.46 |
|||
| Contract Id | 153200 | Change Order Summary |
County | DAVIESS | ||||||
| Estimate Nbr | 0003 | Project Number | CB06 030 0140 000-003, CB06 030 0142 000-004, CB06 030 0657 000-001, CB06 030 0661 000-002, CB06 030 1207 002-006, CB06 030 2127 005-007 | |||||||
| Contractor | J H RUDOLPH & CO INC AND SUBSIDIARIES | Period | 04/24/2015 TO 05/07/2015 | |||||||
| CHANGE ORDERS HISTORY | ||||||||||
| CHANGE ORDER NBR | DESCRIPTION | STATUS | APPROVAL DATE | TOTAL CO AMOUNT | CONTRACT TIME ADJUSTED | |||||
CONTRACT ADJUSTMENTS HISTORY
| Contract Adjustments |
|
|
| Adjustment Description | Est No |
Adjustment Amount |
| Line Item Adjustments History | |||||||||
| PROJECT | ITEM NBR | DESCRPITION | TYPE | EST NO | ADJ QUANTITY |
UNIT PRICE |
ADJUSTED AMOUNT |
||
| Contract Id | 153200 | COMMONWEALTH OF KENTUCKY |
County | DAVIESS | ||||||
| Contract Type | ASRS ASPHALT RESURFACING | TRANSPORTATION CABINET |
Primary Project Number | 0203001401401 | ||||||
| Estimate Nbr | 0003 | Period | 04/24/2015 TO 05/07/2015 | |||||||
| Contractor | J H RUDOLPH & CO INC AND SUBSIDIARIES | |||||||||
| Project | 0203001401401 | Fed/State Project Number | CB06 030 0140 000-003 | Category | ||||||||
| LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
| Project | 0203001401401 | Fed/State Project Number | CB06 030 0140 000-003 | Category | 0001 PAVING | |||||||
| 0049 | DGA BASE | 00001 | TON | 610.00 | 610.000 | 0.000 | 0.000 | 36.10 | 0.00 | |||
| 0050 | TEMPORARY SIGNS | 02562 | SQFT | 250.00 | 250.000 | 112.000 | 112.000 | 8.50 | 952.00 | |||
| 0051 | MAINTAIN & CONTROL TRAFFIC KY 140 | 02650 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 2,700.00 | 0.00 | |||
| 0052 | CL2 ASPH SURF 0.38D PG64-22 | 00301 | TON | 1,920.00 | 1,920.000 | 289.460 | 1,651.050 | 1,940.510 | 71.60 | 20,725.33 | 138,940.51 | |
| 0053 | LEVELING & WEDGING PG64-22 | 00190 | TON | 175.00 | 175.000 | 179.150 | 179.150 | 76.20 | 13,651.23 | |||
| 0054 | MOBILIZATION FOR MILL & TEXT KY 140 | 02676 | LS | 1.00 | 1.000 | 1.000 | 1.000 | 2,000.00 | 2,000.00 | |||
| 0055 | ASPHALT PAVE MILLING & TEXTURING | 02677 | TON | 20.00 | 20.000 | 20.000 | 20.000 | 57.00 | 1,140.00 | |||
| 0056 | PAVE STRIPING-PERM PAINT-4 IN | 06514 | LF | 27,496.00 | 27,496.000 | 5,396.000 | 18,147.000 | 23,543.000 | 0.22 | 1,187.12 | 5,179.46 | |
| 0057 | PAVE STRIPING-TEMP PAINT-4 IN | 06510 | LF | 13,748.00 | 13,748.000 | 2,846.000 | 2,846.000 | 0.20 | 569.20 | |||
| 0059 | ASPHALT ADJUSTMENT | 10030NS | DOLL | 8,191.00 | 8,191.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
| 0060 | FUEL ADJUSTMENT | 10020NS | DOLL | 3,261.00 | 3,261.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
| Project | 0203001401401 | Fed/State Project Number | CB06 030 0140 000-003 | Category | 0002 DEMOBILIZATION | |||||||
| 0058 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 4,004.45 | 0.00 | |||
| SUBTOT | $21,912.45 |
$162,432.40 |
||||||||||
| LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
| SUBTOT | $0.00 |
|||||||||||
| Project | 0203001421401 | Fed/State Project Number | CB06 030 0142 000-004 | Category | ||||||||
| LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
| Project | 0203001421401 | Fed/State Project Number | CB06 030 0142 000-004 | Category | 0001 PAVING | |||||||
| 0061 | TEMPORARY SIGNS | 02562 | SQFT | 210.00 | 210.000 | 32.000 | 240.000 | 272.000 | 8.50 | 272.00 | 2,312.00 | |
| 0062 | MAINTAIN & CONTROL TRAFFIC KY 142 | 02650 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 6,800.00 | 0.00 | |||
| 0063 | CL2 ASPH SURF 0.38D PG64-22 | 00301 | TON | 2,240.00 | 2,240.000 | 2,234.830 | 0.000 | 2,234.830 | 71.60 | 160,013.82 | 160,013.82 | |
| 0064 | DGA BASE | 00001 | TON | 225.00 | 225.000 | 0.000 | 0.000 | 36.10 | 0.00 | |||
| 0065 | LEVELING & WEDGING PG64-22 | 00190 | TON | 203.00 | 203.000 | 211.220 | 0.000 | 211.220 | 76.20 | 16,094.96 | 16,094.96 | |
| 0066 | MOBILIZATION FOR MILL & TEXT KY 142 | 02676 | LS | 1.00 | 1.000 | 1.000 | 1.000 | 2,000.00 | 2,000.00 | |||
| 0067 | ASPHALT PAVE MILLING & TEXTURING | 02677 | TON | 95.00 | 95.000 | 95.000 | 95.000 | 57.00 | 5,415.00 | |||
| 0068 | PAVE STRIPING-THERMO-12 IN Y | 06547 | LF | 430.00 | 430.000 | 0.000 | 0.000 | 5.00 | 0.00 | |||
| 0069 | BASE FAILURE REPAIR | 03240 | SQYD | 245.00 | 245.000 | 253.650 | 253.650 | 160.00 | 40,584.00 | |||
| 0070 | PAVE STRIPING-PERM PAINT-4 IN | 06514 | LF | 27,800.00 | 27,800.000 | 27,002.000 | 0.000 | 27,002.000 | 0.22 | 5,940.44 | 5,940.44 | |
| 0071 | PAVE STRIPING-TEMP PAINT-4 IN | 06510 | LF | 13,900.00 | 13,900.000 | 5,741.000 | 0.000 | 5,741.000 | 0.20 | 1,148.20 | 1,148.20 | |
| 0073 | ASPHALT ADJUSTMENT | 10030NS | DOLL | 9,551.00 | 9,551.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
| 0074 | FUEL ADJUSTMENT | 10020NS | DOLL | 3,803.00 | 3,803.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
| 0075 | BARRICADE-TYPE III | 02014 | EACH | 2.00 | 2.000 | 2.000 | 0.000 | 2.000 | 100.00 | 200.00 | 200.00 | |
| Project | 0203001421401 | Fed/State Project Number | CB06 030 0142 000-004 | Category | 0002 DEMOBILIZATION | |||||||
| 0072 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 5,653.22 | 0.00 | |||
| SUBTOT | $183,669.43 |
$396,140.83 |
||||||||||
| LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
| SUBTOT | $0.00 |
|||||||||||
| Project | 0203006571401 | Fed/State Project Number | CB06 030 0657 000-001 | Category | ||||||||
| LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
| Project | 0203006571401 | Fed/State Project Number | CB06 030 0657 000-001 | Category | 0001 PAVING | |||||||
| 0001 | PAVE STRIPING-TEMP PAINT-4 IN | 06510 | LF | 4,000.00 | 4,000.000 | 0.000 | 0.000 | 0.20 | 0.00 | |||
| 0002 | PAVE STRIPING-PERM PAINT-4 IN | 06514 | LF | 8,000.00 | 8,000.000 | 7,552.000 | 0.000 | 7,552.000 | 0.22 | 1,661.44 | 1,661.44 | |
| 0003 | ASPHALT PAVE MILLING & TEXTURING | 02677 | TON | 20.00 | 20.000 | 20.000 | 20.000 | 57.00 | 1,140.00 | |||
| 0004 | MOBILIZATION FOR MILL & TEXT KY 657 | 02676 | LS | 1.00 | 1.000 | 1.000 | 1.000 | 2,000.00 | 2,000.00 | |||
| 0005 | LEVELING & WEDGING PG64-22 | 00190 | TON | 43.00 | 43.000 | 41.660 | 0.000 | 41.660 | 76.20 | 3,174.49 | 3,174.49 | |
| 0006 | DGA BASE | 00001 | TON | 150.00 | 150.000 | 0.000 | 0.000 | 36.10 | 0.00 | |||
| 0007 | CL2 ASPH SURF 0.38D PG64-22 | 00301 | TON | 475.00 | 475.000 | 472.020 | 0.000 | 472.020 | 71.60 | 33,796.63 | 33,796.63 | |
| 0008 | MAINTAIN & CONTROL TRAFFIC KY 657 | 02650 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 1,900.00 | 0.00 | |||
| 0009 | TEMPORARY SIGNS | 02562 | SQFT | 230.00 | 230.000 | 56.000 | 56.000 | 8.50 | 476.00 | |||
| 0010 | FUEL ADJUSTMENT | 10020NS | DOLL | 806.00 | 806.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
| 0011 | ASPHALT ADJUSTMENT | 10030NS | DOLL | 2,025.00 | 2,025.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
| Project | 0203006571401 | Fed/State Project Number | CB06 030 0657 000-001 | Category | 0002 DEMOBILIZATION | |||||||
| 0012 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 1,071.47 | 0.00 | |||
| SUBTOT | $38,632.56 |
$438,389.40 |
||||||||||
| LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
| SUBTOT | $0.00 |
|||||||||||
| Project | 0203006611401 | Fed/State Project Number | CB06 030 0661 000-002 | Category | ||||||||
| LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
| Project | 0203006611401 | Fed/State Project Number | CB06 030 0661 000-002 | Category | 0001 PAVING | |||||||
| 0013 | FUEL ADJUSTMENT | 10020NS | DOLL | 2,129.00 | 2,129.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
| 0014 | ASPHALT ADJUSTMENT | 10030NS | DOLL | 5,348.00 | 5,348.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
| 0015 | PAVE STRIPING-TEMP PAINT-4 IN | 06510 | LF | 7,500.00 | 7,500.000 | 0.000 | 0.000 | 0.20 | 0.00 | |||
| 0016 | PAVE STRIPING-PERM PAINT-4 IN | 06514 | LF | 15,000.00 | 15,000.000 | 14,444.000 | 0.000 | 14,444.000 | 0.22 | 3,177.68 | 3,177.68 | |
| 0017 | ASPHALT PAVE MILLING & TEXTURING | 02677 | TON | 30.00 | 30.000 | 30.000 | 30.000 | 57.00 | 1,710.00 | |||
| 0018 | MOBILIZATION FOR MILL & TEXT KY 661 | 02676 | LS | 1.00 | 1.000 | 1.000 | 1.000 | 2,000.00 | 2,000.00 | |||
| 0019 | LEVELING & WEDGING PG64-22 | 00190 | TON | 88.00 | 88.000 | 83.330 | 0.000 | 83.330 | 76.20 | 6,349.74 | 6,349.74 | |
| 0020 | CL2 ASPH SURF 0.38D PG64-22 | 00301 | TON | 1,280.00 | 1,280.000 | 1,330.050 | 0.000 | 1,330.050 | 71.60 | 95,231.58 | 95,231.58 | |
| 0021 | DGA BASE | 00001 | TON | 405.00 | 405.000 | 0.000 | 0.000 | 36.10 | 0.00 | |||
| 0022 | TEMPORARY SIGNS | 02562 | SQFT | 230.00 | 230.000 | 128.000 | 128.000 | 8.50 | 1,088.00 | |||
| 0023 | MAINTAIN & CONTROL TRAFFIC KY 661 | 02650 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 2,800.00 | 0.00 | |||
| Project | 0203006611401 | Fed/State Project Number | CB06 030 0661 000-002 | Category | 0002 DEMOBILIZATION | |||||||
| 0024 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 2,634.14 | 0.00 | |||
| SUBTOT | $104,759.00 |
$547,946.40 |
||||||||||
| LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
| SUBTOT | $0.00 |
|||||||||||
| Project | 0203012071401 | Fed/State Project Number | CB06 030 1207 002-006 | Category | ||||||||
| LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
| Project | 0203012071401 | Fed/State Project Number | CB06 030 1207 002-006 | Category | 0001 PAVING | |||||||
| 0026 | FUEL ADJUSTMENT | 10020NS | DOLL | 2,687.00 | 2,687.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
| 0027 | ASPHALT ADJUSTMENT | 10030NS | DOLL | 6,748.00 | 6,748.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
| 0028 | PAVE STRIPING-TEMP PAINT-4 IN | 06510 | LF | 11,000.00 | 11,000.000 | 0.000 | 0.000 | 0.20 | 0.00 | |||
| 0029 | PAVE STRIPING-PERM PAINT-4 IN | 06514 | LF | 22,000.00 | 22,000.000 | 17,650.000 | 17,650.000 | 0.22 | 3,883.00 | |||
| 0030 | ASPHALT PAVE MILLING & TEXTURING | 02677 | TON | 25.00 | 25.000 | 25.000 | 25.000 | 57.00 | 1,425.00 | |||
| 0031 | MOBILIZATION FOR MILL & TEXT KY 1207 | 02676 | LS | 1.00 | 1.000 | 1.000 | 1.000 | 2,000.00 | 2,000.00 | |||
| 0032 | LEVELING & WEDGING PG64-22 | 00190 | TON | 111.00 | 111.000 | 110.470 | 110.470 | 76.20 | 8,417.81 | |||
| 0033 | DGA BASE | 00001 | TON | 515.00 | 515.000 | 0.000 | 0.000 | 36.10 | 0.00 | |||
| 0034 | CL2 ASPH SURF 0.38D PG64-22 | 00301 | TON | 1,615.00 | 1,615.000 | 1,618.360 | 1,618.360 | 71.60 | 115,874.57 | |||
| 0035 | MAINTAIN & CONTROL TRAFFIC KY 1207 | 02650 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 2,800.00 | 0.00 | |||
| 0036 | TEMPORARY SIGNS | 02562 | SQFT | 230.00 | 230.000 | 88.000 | 88.000 | 8.50 | 748.00 | |||
| Project | 0203012071401 | Fed/State Project Number | CB06 030 1207 002-006 | Category | 0002 DEMOBILIZATION | |||||||
| 0025 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 3,312.37 | 0.00 | |||
| SUBTOT | $0.00 |
$680,294.79 |
||||||||||
| LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
| SUBTOT | $0.00 |
|||||||||||
| Project | 02030212714R1 | Fed/State Project Number | CB06 030 2127 005-007 | Category | ||||||||
| LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
| Project | 02030212714R1 | Fed/State Project Number | CB06 030 2127 005-007 | Category | 0001 PAVING | |||||||
| 0037 | TEMPORARY SIGNS | 02562 | SQFT | 250.00 | 250.000 | 64.000 | 64.000 | 8.50 | 544.00 | |||
| 0038 | MAINTAIN & CONTROL TRAFFIC KY 2127 | 02650 | LS | 1.00 | 1.000 | 1.000 | 1.000 | 2,000.00 | 2,000.00 | |||
| 0039 | CL2 ASPH SURF 0.38D PG64-22 | 00301 | TON | 625.00 | 625.000 | 623.900 | 623.900 | 71.60 | 44,671.24 | |||
| 0040 | DGA BASE | 00001 | TON | 180.00 | 180.000 | 0.000 | 0.000 | 36.10 | 0.00 | |||
| 0041 | LEVELING & WEDGING PG64-22 | 00190 | TON | 57.00 | 57.000 | 59.670 | 59.670 | 76.20 | 4,546.85 | |||
| 0042 | MOBILIZATION FOR MILL & TEXT KY 2127 | 02676 | LS | 1.00 | 1.000 | 2.000 | 2.000 | 2,000.00 | 4,000.00 | |||
| 0043 | ASPHALT PAVE MILLING & TEXTURING | 02677 | TON | 15.00 | 15.000 | 30.000 | 30.000 | 57.00 | 1,710.00 | |||
| 0044 | PAVE STRIPING-PERM PAINT-4 IN | 06514 | LF | 3,000.00 | 3,000.000 | 2,774.000 | 2,774.000 | 0.22 | 610.28 | |||
| 0045 | PAVE STRIPING-TEMP PAINT-4 IN | 06510 | LF | 1,500.00 | 1,500.000 | 0.000 | 0.000 | 0.20 | 0.00 | |||
| 0047 | ASPHALT ADJUSTMENT | 10030NS | DOLL | 2,666.00 | 2,666.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
| 0048 | FUEL ADJUSTMENT | 10020NS | DOLL | 1,062.00 | 1,062.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
| Project | 02030212714R1 | Fed/State Project Number | CB06 030 2127 005-007 | Category | 0002 DEMOBILIZATION | |||||||
| 0046 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 1,324.35 | 0.00 | |||
| SUBTOT | $0.00 |
$738,377.17 |
||||||||||
| LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
| SUBTOT | $0.00 |
|||||||||||