Report_Id: 123230 Est NO 0005 |
Date:11/07/2012 |
COMMONWEALTH OF KENTUCKY
TRANSPORTATION CABINET
Contract ID | 123230 | Estimate Number | 0005 | Estimate Type | PROGRESS | ||
District Office | PIKEVILLE (12300) Weddington, Derrick P. (Paxton), P.E. | ||||||
Contractor | MOUNTAIN ENTERPRISES INC | ADDR SN 0 VC Code VC0000008864 | |||||
PO 13130 | |||||||
LEXINGTON , KY , 40583-3130 | |||||||
Pay Period | 10/08/2012 TO 10/21/2012 | ||||||
Date Approved | 10/30/2012 | ||||||
Primary Proj Number | 12098019512R2 | ||||||
Project No. | CB06 098 0195 000-003, CB06 098 0292 000-006, CB06 098 0366 000-005, CB06 098 0612 002-005, CB06 098 1426 002-004, CB06 098 3418 000-005, CB06 098 3416 000-002 | ||||||
Primary County | PIKE | ||||||
Name of Road | VARIOUS ROUTES IN PIKE COUNTY | ||||||
Description | VARIOUS ROUTES IN PIKE COUNTY | ||||||
Date Let | 06/15/2012 | Formal Acceptance | |||||
Date Awarded | 06/27/2012 | Date Work Began | 07/30/2012 | ||||
Date Contract Executed | 07/12/2012 | Open To Traffic | |||||
Date NTP Issued | 07/12/2012 | Actual Completion Date | |||||
Current Contract Amount | $1,362,911.00 |
Total to Date |
Prev to Date |
This Estimate |
||
Original Amount | $1,362,911.00 |
Total Earnings | $1,287,397.23 |
$1,026,032.25 |
$261,364.98 |
|
Percent Complete | 94.46 |
Stockpiled Materials | $0.00 |
$0.00 |
$0.00 |
|
Funds Available | $75,513.77 |
Gross Earnings | $1,287,397.23 |
$1,026,032.25 |
$261,364.98 |
|
Total Change Orders | $0.00 |
Other Adjustments | $0.00 |
$0.00 |
$0.00 |
|
TOTAL | $1,287,397.23 |
$1,026,032.25 |
$261,364.98 |
|||
Contract Id | 123230 | Change Order Summary |
County | PIKE | ||||||
Estimate Nbr | 0005 | Project Number | CB06 098 0195 000-003, CB06 098 0292 000-006, CB06 098 0366 000-005, CB06 098 0612 002-005, CB06 098 1426 002-004, CB06 098 3418 000-005, CB06 098 3416 000-002 | |||||||
Contractor | MOUNTAIN ENTERPRISES INC | Period | 10/08/2012 TO 10/21/2012 | |||||||
CHANGE ORDERS HISTORY | ||||||||||
CHANGE ORDER NBR | DESCRIPTION | STATUS | APPROVAL DATE | TOTAL CO AMOUNT | CONTRACT TIME ADJUSTED | |||||
CONTRACT ADJUSTMENTS HISTORY
Contract Adjustments |
|
|
Adjustment Description | Est No |
Adjustment Amount |
Line Item Adjustments History | |||||||||
PROJECT | ITEM NBR | DESCRPITION | TYPE | EST NO | ADJ QUANTITY |
UNIT PRICE |
ADJUSTED AMOUNT |
Contract Id | 123230 | COMMONWEALTH OF KENTUCKY |
County | PIKE | ||||||
Contract Type | ASRS ASPHALT RESURFACING | TRANSPORTATION CABINET |
Primary Project Number | 12098019512R2 | ||||||
Estimate Nbr | 0005 | Period | 10/08/2012 TO 10/21/2012 | |||||||
Contractor | MOUNTAIN ENTERPRISES INC | |||||||||
Project | 12098019512R2 | Fed/State Project Number | CB06 098 0195 000-003 | Category | 0001 ROADWAY | |||||||
LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
0010 | SIGNS | 02562 | SQFT | 150.00 | 150.000 | 0.000 | 0.000 | 0.01 | 0.00 | |||
0020 | MAINTAIN & CONTROL TRAFFIC KY 195 | 02650 | LS | 1.00 | 1.000 | 1.000 | 1.000 | 2,500.00 | 2,500.00 | |||
0030 | CL2 ASPH SURF 0.38D PG64-22 | 00301 | TON | 1,425.00 | 1,425.000 | 1,424.180 | 1,424.180 | 90.30 | 128,603.45 | |||
0040 | PAVE STRIPING-PERM PAINT-4 IN | 06514 | LF | 24,000.00 | 24,000.000 | 23,170.000 | 23,170.000 | 0.24 | 5,560.80 | |||
0050 | ASPHALT ADJUSTMENT | 10030NS | DOLL | 3,433.00 | 3,433.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
0060 | FUEL ADJUSTMENT | 10020NS | DOLL | 1,948.00 | 1,948.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
Project | 12098019512R2 | Fed/State Project Number | CB06 098 0195 000-003 | Category | 0002 DEMOBILAZATION | |||||||
0070 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 2,247.72 | 0.00 | |||
SUBTOT | $0.00 |
$136,664.25 |
||||||||||
LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
SUBTOT | $0.00 |
Project | 12098029212R1 | Fed/State Project Number | CB06 098 0292 000-006 | Category | 0001 ROADWAY | |||||||
LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
0010 | SIGNS | 02562 | SQFT | 210.00 | 210.000 | 0.000 | 0.000 | 0.01 | 0.00 | |||
0020 | MAINTAIN & CONTROL TRAFFIC KY 292 | 02650 | LS | 1.00 | 1.000 | 1.000 | 0.000 | 1.000 | 3,000.00 | 3,000.00 | 3,000.00 | |
0030 | CL2 ASPH SURF 0.38D PG64-22 | 00301 | TON | 2,300.00 | 2,300.000 | 2,287.120 | 0.000 | 2,287.120 | 90.30 | 206,526.93 | 206,526.93 | |
0040 | LEVELING & WEDGING PG64-22 | 00190 | TON | 400.00 | 400.000 | 395.460 | 0.000 | 395.460 | 90.30 | 35,710.03 | 35,710.03 | |
0050 | PAVE STRIPING-PERM PAINT-4 IN | 06514 | LF | 60,000.00 | 60,000.000 | 67,200.000 | 0.000 | 67,200.000 | 0.24 | 16,128.00 | 16,128.00 | |
0060 | PAVE STRIPING-TEMP PAINT-4 IN | 06510 | LF | 2,500.00 | 2,500.000 | 0.000 | 0.000 | 0.19 | 0.00 | |||
0070 | ASPHALT ADJUSTMENT | 10030NS | DOLL | 6,505.00 | 6,505.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
0080 | FUEL ADJUSTMENT | 10020NS | DOLL | 3,691.00 | 3,691.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
Project | 12098029212R1 | Fed/State Project Number | CB06 098 0292 000-006 | Category | 0002 DEMOBILIZATION | |||||||
0090 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 3,922.06 | 0.00 | |||
SUBTOT | $261,364.97 |
$398,029.22 |
||||||||||
LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
SUBTOT | $0.00 |
Project | 12098036612R1 | Fed/State Project Number | CB06 098 0366 000-005 | Category | 0001 ROADWAY | |||||||
LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
0010 | SIGNS | 02562 | SQFT | 150.00 | 150.000 | 0.000 | 0.000 | 0.01 | 0.00 | |||
0020 | MAINTAIN & CONTROL TRAFFIC KY 366 | 02650 | LS | 1.00 | 1.000 | 1.000 | 1.000 | 3,500.00 | 3,500.00 | |||
0030 | CL2 ASPH SURF 0.38D PG64-22 | 00301 | TON | 2,900.00 | 2,900.000 | 2,892.290 | 2,892.290 | 90.30 | 261,173.78 | |||
0040 | LEVELING & WEDGING PG64-22 | 00190 | TON | 200.00 | 200.000 | 184.190 | 184.190 | 90.30 | 16,632.35 | |||
0050 | PAVE STRIPING-PERM PAINT-4 IN | 06514 | LF | 18,000.00 | 18,000.000 | 36,000.000 | 36,000.000 | 0.24 | 8,640.00 | |||
0060 | ASPHALT ADJUSTMENT | 10030NS | DOLL | 7,468.00 | 7,468.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
0070 | FUEL ADJUSTMENT | 10020NS | DOLL | 4,238.00 | 4,238.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
Project | 12098036612R1 | Fed/State Project Number | CB06 098 0366 000-005 | Category | 0002 DEMOBILIZATION | |||||||
0080 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 4,541.28 | 0.00 | |||
SUBTOT | $0.00 |
$687,975.37 |
||||||||||
LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
SUBTOT | $0.00 |
Project | 12098061212R2 | Fed/State Project Number | CB06 098 0612 002-005 | Category | 0001 ROADWAY | |||||||
LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
0010 | SIGNS | 02562 | SQFT | 150.00 | 150.000 | 0.000 | 0.000 | 0.01 | 0.00 | |||
0020 | MAINTAIN & CONTROL TRAFFIC KY 612 | 02650 | LS | 1.00 | 1.000 | 1.000 | 1.000 | 2,500.00 | 2,500.00 | |||
0030 | CL2 ASPH SURF 0.38D PG64-22 | 00301 | TON | 1,500.00 | 1,500.000 | 1,500.000 | 1,500.000 | 90.30 | 135,450.00 | |||
0040 | LEVELING & WEDGING PG64-22 | 00190 | TON | 55.00 | 55.000 | 52.900 | 52.900 | 90.30 | 4,776.87 | |||
0050 | PAVE STRIPING-PERM PAINT-4 IN | 06514 | LF | 23,130.00 | 23,130.000 | 21,089.000 | 21,089.000 | 0.24 | 5,061.36 | |||
0060 | ASPHALT ADJUSTMENT | 10030NS | DOLL | 3,746.00 | 3,746.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
0070 | FUEL ADJUSTMENT | 10020NS | DOLL | 2,126.00 | 2,126.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
Project | 12098061212R2 | Fed/State Project Number | CB06 098 0612 002-005 | Category | 0002 DEMOBILIZATION | |||||||
0080 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 2,429.91 | 0.00 | |||
SUBTOT | $0.00 |
$835,763.60 |
||||||||||
LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
SUBTOT | $0.00 |
Project | 12098142612R1 | Fed/State Project Number | CB06 098 1426 002-004 | Category | 0001 ROADWAY | |||||||
LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
0010 | SIGNS | 02562 | SQFT | 170.00 | 170.000 | 0.000 | 0.000 | 0.01 | 0.00 | |||
0020 | MAINTAIN & CONTROL TRAFFIC KY 1426 | 02650 | LS | 1.00 | 1.000 | 1.000 | 1.000 | 2,500.00 | 2,500.00 | |||
0030 | CL2 ASPH SURF 0.38D PG64-22 | 00301 | TON | 1,015.00 | 1,015.000 | 1,004.810 | 1,004.810 | 90.30 | 90,734.34 | |||
0050 | PAVE STRIPING-PERM PAINT-4 IN | 06514 | LF | 28,200.00 | 28,200.000 | 28,500.000 | 28,500.000 | 0.24 | 6,840.00 | |||
0060 | ASPHALT ADJUSTMENT | 10030NS | DOLL | 2,445.00 | 2,445.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
0070 | FUEL ADJUSTMENT | 10020NS | DOLL | 1,388.00 | 1,388.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
Project | 12098142612R1 | Fed/State Project Number | CB06 098 1426 002-004 | Category | 0002 DEMOBILIZATION | |||||||
0080 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 1,659.80 | 0.00 | |||
SUBTOT | $0.00 |
$935,837.94 |
||||||||||
LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
SUBTOT | $0.00 |
Project | 12098241812R1 | Fed/State Project Number | CB06 098 3418 000-005 | Category | 0001 ROADWAY | |||||||
LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
0010 | SIGNS | 02562 | SQFT | 170.00 | 170.000 | 0.000 | 0.000 | 0.01 | 0.00 | |||
0020 | MAINTAIN & CONTROL TRAFFIC KY 3418 | 02650 | LS | 1.00 | 1.000 | 1.000 | 1.000 | 3,000.00 | 3,000.00 | |||
0030 | CL2 ASPH SURF 0.38D PG64-22 | 00301 | TON | 2,800.00 | 2,800.000 | 2,778.810 | 2,778.810 | 90.30 | 250,926.54 | |||
0040 | LEVELING & WEDGING PG64-22 | 00190 | TON | 350.00 | 350.000 | 343.460 | 343.460 | 90.30 | 31,014.43 | |||
0050 | ASPHALT ADJUSTMENT | 10030NS | DOLL | 7,589.00 | 7,589.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
0060 | FUEL ADJUSTMENT | 10020NS | DOLL | 4,306.00 | 4,306.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
Project | 12098241812R1 | Fed/State Project Number | CB06 098 3418 000-005 | Category | 0002 DEMOBILIZATION | |||||||
0070 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 4,631.81 | 0.00 | |||
SUBTOT | $0.00 |
$1,220,778.92 |
||||||||||
LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
SUBTOT | $0.00 |
Project | 12098341612R1 | Fed/State Project Number | CB06 098 3416 000-002 | Category | 0001 ROADWAY | |||||||
LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
0010 | SIGNS | 02562 | SQFT | 150.00 | 150.000 | 0.000 | 0.000 | 0.01 | 0.00 | |||
0020 | MAINTAIN & CONTROL TRAFFIC KY 3416 | 02650 | LS | 1.00 | 1.000 | 1.000 | 1.000 | 2,500.00 | 2,500.00 | |||
0030 | CL2 ASPH SURF 0.38D PG64-22 | 00301 | TON | 700.00 | 700.000 | 687.680 | 687.680 | 90.30 | 62,097.50 | |||
0040 | PAVE STRIPING-PERM PAINT-4 IN | 06514 | LF | 8,000.00 | 8,000.000 | 8,420.000 | 8,420.000 | 0.24 | 2,020.80 | |||
0050 | ASPHALT ADJUSTMENT | 10030NS | DOLL | 1,686.00 | 1,686.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
0060 | FUEL ADJUSTMENT | 10020NS | DOLL | 957.00 | 957.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
Project | 12098341612R1 | Fed/State Project Number | CB06 098 3416 000-002 | Category | 0002 DEMOBILIZATION | |||||||
0070 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 1,103.18 | 0.00 | |||
SUBTOT | $0.00 |
$1,287,397.23 |
||||||||||
LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
SUBTOT | $0.00 |