Report_Id: 123123 Est NO 0003 |
Date:11/07/2012 |
COMMONWEALTH OF KENTUCKY
TRANSPORTATION CABINET
| Contract ID | 123123 | Estimate Number | 0003 | Estimate Type | PROGRESS | ||
| District Office | LOUISVILLE (05320) Gossom, Ryan J., P.E. | ||||||
| Contractor | H G MAYS CORPORATION | ADDR SN 0 VC Code VC0000088058 | |||||
| BOX 797 | |||||||
| FRANKFORT , KY , 40602 | |||||||
| Pay Period | 09/07/2012 TO 10/18/2012 | ||||||
| Date Approved | 10/30/2012 | ||||||
| Primary Proj Number | 0510607141201 | ||||||
| Project No. | CB06 106 0322 000-001, CB06 106 0714 000-009 | ||||||
| Primary County | SHELBY | ||||||
| Name of Road | VARIOUS ROUTES IN SHELBY COUNTY | ||||||
| Description | VARIOUS ROUTES IN SHELBY COUNTY | ||||||
| Date Let | 06/15/2012 | Formal Acceptance | |||||
| Date Awarded | 06/27/2012 | Date Work Began | 08/08/2012 | ||||
| Date Contract Executed | 07/12/2012 | Open To Traffic | |||||
| Date NTP Issued | 07/12/2012 | Actual Completion Date | 09/07/2012 | ||||
| Current Contract Amount | $585,086.42 |
Total to Date |
Prev to Date |
This Estimate |
||
| Original Amount | $585,086.42 |
Total Earnings | $527,954.44 |
$526,723.96 |
$1,230.48 |
|
| Percent Complete | 90.24 |
Stockpiled Materials | $0.00 |
$0.00 |
$0.00 |
|
| Funds Available | $57,131.98 |
Gross Earnings | $527,954.44 |
$526,723.96 |
$1,230.48 |
|
| Total Change Orders | $0.00 |
Other Adjustments | $0.00 |
$0.00 |
$0.00 |
|
| TOTAL | $527,954.44 |
$526,723.96 |
$1,230.48 |
|||
| Contract Id | 123123 | Change Order Summary |
County | SHELBY | ||||||
| Estimate Nbr | 0003 | Project Number | CB06 106 0322 000-001, CB06 106 0714 000-009 | |||||||
| Contractor | H G MAYS CORPORATION | Period | 09/07/2012 TO 10/18/2012 | |||||||
| CHANGE ORDERS HISTORY | ||||||||||
| CHANGE ORDER NBR | DESCRIPTION | STATUS | APPROVAL DATE | TOTAL CO AMOUNT | CONTRACT TIME ADJUSTED | |||||
CONTRACT ADJUSTMENTS HISTORY
| Contract Adjustments |
|
|
| Adjustment Description | Est No |
Adjustment Amount |
| Line Item Adjustments History | |||||||||
| PROJECT | ITEM NBR | DESCRPITION | TYPE | EST NO | ADJ QUANTITY |
UNIT PRICE |
ADJUSTED AMOUNT |
||
| Contract Id | 123123 | COMMONWEALTH OF KENTUCKY |
County | SHELBY | ||||||
| Contract Type | ASRS ASPHALT RESURFACING | TRANSPORTATION CABINET |
Primary Project Number | 0510607141201 | ||||||
| Estimate Nbr | 0003 | Period | 09/07/2012 TO 10/18/2012 | |||||||
| Contractor | H G MAYS CORPORATION | |||||||||
| Project | 0510603221201 | Fed/State Project Number | CB06 106 0322 000-001 | Category | 0001 ROADWAY | |||||||
| LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
| 0010 | SIGNS | 02562 | SQFT | 230.00 | 230.000 | 0.000 | 0.000 | 0.01 | 0.00 | |||
| 0020 | MAINTAIN & CONTROL TRAFFIC KY 322 | 02650 | LS | 1.00 | 1.000 | 1.000 | 1.000 | 1,675.00 | 1,675.00 | |||
| 0030 | CL2 ASPH SURF 0.38D PG64-22 | 00301 | TON | 570.00 | 570.000 | 522.670 | 522.670 | 55.64 | 29,081.35 | |||
| 0040 | ASPHALT MIX FOR PAVEMENT WEDGE | 00263 | TON | 125.00 | 125.000 | 113.070 | 113.070 | 55.64 | 6,291.21 | |||
| 0050 | LEVELING & WEDGING PG64-22 | 00190 | TON | 39.00 | 39.000 | 38.210 | 38.210 | 55.64 | 2,126.00 | |||
| 0060 | ASPHALT PAVE MILLING & TEXTURING | 02677 | TON | 31.00 | 31.000 | 26.880 | 26.880 | 35.97 | 966.87 | |||
| 0070 | MOBILIZATION FOR MILL & TEXT KY 322 | 02676 | LS | 1.00 | 1.000 | 1.000 | 1.000 | 2,500.00 | 2,500.00 | |||
| 0080 | PAVE STRIPING-PERM PAINT-4 IN | 06514 | LF | 8,279.00 | 8,279.000 | 7,904.000 | 7,904.000 | 0.10 | 790.40 | |||
| 0090 | PAVE STRIPING-TEMP PAINT-4 IN | 06510 | LF | 8,279.00 | 8,279.000 | 0.000 | 0.000 | 0.01 | 0.00 | |||
| 0100 | ASPHALT ADJUSTMENT | 10030NS | DOLL | 1,768.00 | 1,768.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
| 0110 | FUEL ADJUSTMENT | 10020NS | DOLL | 1,003.00 | 1,003.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
| Project | 0510603221201 | Fed/State Project Number | CB06 106 0322 000-001 | Category | 0002 DEMOBILIZATION | |||||||
| 0120 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 719.44 | 0.00 | |||
| SUBTOT | $0.00 |
$43,430.85 |
||||||||||
| LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
| SUBTOT | $0.00 |
|||||||||||
| Project | 0510607141201 | Fed/State Project Number | CB06 106 0714 000-009 | Category | 0001 ROADWAY | |||||||
| LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
| 0010 | SIGNS | 02562 | SQFT | 390.00 | 390.000 | 48.000 | 0.000 | 48.000 | 0.01 | 0.48 | 0.48 | |
| 0020 | MAINTAIN & CONTROL TRAFFIC KY 714 | 02650 | LS | 1.00 | 1.000 | 1.000 | 1.000 | 10,200.00 | 10,200.00 | |||
| 0030 | CL2 ASPH SURF 0.38D PG64-22 | 00301 | TON | 5,580.00 | 5,580.000 | 5,322.290 | 5,322.290 | 55.64 | 296,132.21 | |||
| 0040 | ASPHALT MIX FOR PAVEMENT WEDGE | 00263 | TON | 2,115.00 | 2,115.000 | 1,987.430 | 1,987.430 | 55.64 | 110,580.60 | |||
| 0050 | LEVELING & WEDGING PG64-22 | 00190 | TON | 574.00 | 574.000 | 958.570 | 958.570 | 55.64 | 53,334.83 | |||
| 0060 | ASPHALT PAVE MILLING & TEXTURING | 02677 | TON | 108.00 | 108.000 | 63.420 | 63.420 | 35.97 | 2,281.21 | |||
| 0070 | MOBILIZATION FOR MILL & TEXT KY 714 | 02676 | LS | 1.00 | 1.000 | 1.000 | 1.000 | 2,500.00 | 2,500.00 | |||
| 0080 | PAVE STRIPING-PERM PAINT-4 IN | 06514 | LF | 176,080.00 | 176,080.000 | 82,382.000 | 82,382.000 | 0.10 | 8,238.20 | |||
| 0090 | PAVE STRIPING-TEMP PAINT-4 IN | 06510 | LF | 83,860.00 | 83,860.000 | 2,604.000 | 2,604.000 | 0.01 | 26.04 | |||
| 0100 | PAVE MARKING-THERMO R 6 FT | 06562 | EACH | 4.00 | 4.000 | 4.000 | 0.000 | 4.000 | 65.00 | 260.00 | 260.00 | |
| 0110 | PAVE MARKING-THERMO STOP BAR-12IN | 06567 | LF | 40.00 | 40.000 | 110.000 | 0.000 | 110.000 | 5.00 | 550.00 | 550.00 | |
| 0120 | PAVE MARKING-R/R XBUCKS 16 IN | 06563 | LF | 64.00 | 64.000 | 84.000 | 0.000 | 84.000 | 5.00 | 420.00 | 420.00 | |
| 0130 | ASPHALT ADJUSTMENT | 10030NS | DOLL | 19,921.00 | 19,921.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
| 0140 | FUEL ADJUSTMENT | 10020NS | DOLL | 11,305.00 | 11,305.000 | 0.000 | 0.000 | 1.00 | 0.00 | |||
| Project | 0510607141201 | Fed/State Project Number | CB06 106 0714 000-009 | Category | 0002 DEMOBILIZATION | |||||||
| 0150 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 7,424.73 | 0.00 | |||
| SUBTOT | $1,230.48 |
$527,954.44 |
||||||||||
| LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
| SUBTOT | $0.00 |
|||||||||||